This pre-solicitation notice seeks capability statements for the Roman Space Telescope pressure transducer procurement. Interested parties should submit no more than a 10-page capability statement by June 15, 2020 indicating ability to serve as prime contractor or subcontractor. The statement should demonstrate meeting requirements described in the attached draft statement of work, specification, and deliverables list. Responses must include company information and whether the business is small, disadvantaged, 8(a), HUBZone, or woman-owned. The Government may consider set-asides and goals based on responses. NASA/Goddard Space Flight Center will use submissions for competition planning. No award exists; interested parties should monitor beta.SAM.gov for any resultant solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| WFIRST-PROP-SOW-0017-_SSdraft.pdf | ||
| WFIRST-PROP-SPEC-0053-_D4.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Effective Date: <Date> Expiration Date: <Date> [as required]
CHECK https://ipdtdms.gsfc.nasa.gov/
TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE.
National Aeronautics and Space Administration
Goddard Space Flight Center Greenbelt, Maryland
WFIRST-PROP-LIST-0019, Revision [-, A]
Wide Field Infrared Survey Telescope (WFIRST), Code 448
Pressure Transducer Deliverable Items List and Schedule
(DILS)
DRAFT
Month Day, Year https://ipdtdms.gsfc.nasa.gov/
<Document Short Title> WFIRST-XXX-LIST-XXXX, Revision Number i
Pressure Transducer Deliverable Items List and Schedule
(DILS)
Review/Signature/Approval Page
Prepared by:
Wanyi Ng
Approved by:
Electronic Approval available on-line at: https://ipdtdms.gsfc.nasa.gov/
Pressure Transducer DILS WFIRST-PROP-LIST-0019, Revision Number ii
Preface This document is a Wide Field Infrared Survey Telescope (WFIRST) Configuration Management (CM)-controlled document. Changes to this document require prior approval of the applicable Configuration Control Board (CCB) Chairperson or designee.
Proposed changes shall be submitted to the WFIRST CM Office (CMO), along with supportive material justifying the proposed change.
In this document, a requirement is identified by “shall,” a good practice by “should,” permission by “may” or “can,” expectation by “will,” and descriptive material by “is.”
Questions or comments concerning this document should be addressed to:
WFIRST Configuration Management Office Mail Stop 448 Goddard Space Flight Center Greenbelt, Maryland 20771 iii
Change History Log
Revision Effective Date Description of Changes (Reference the CCR & CCB/ERB Approval Date) iv
Table of TBDs/TBRs/TBSs [optional]
Item No. Location Summary Individual/ Organization
Actionee
Due Date v
Table of Contents
1 INTRODUCTION
1.1 Purpose
1.2 Scope
1.3 Related Documentation
1.3.1 Applicable Documents [and Forms]
1.3.2 Reference Documents
2 DELIVERABLES
APPENDIX A ABBREVIATIONS AND ACRONYMS
List of Tables
Table 1. Data Delivery Documentation and Schedule
1 INTRODUCTION
1.1 Purpose
The Wide Field InfraRed Survey Telescope (WFIRST) is a mission responding to the 2010 National Research Council New Worlds, New Horizons (NWNH) Astronomy and Astrophysics Decadal Survey top priority recommendation in the large space mission category. The science program includes two dedicated investigations to tackle outstanding questions in dark energy research and exoplanet exploration, and includes a substantial General Observer program to enable targeted investigations of astrophysical phenomena to advance other goals from the Decadal Survey. A coronagraph instrument is included in the payload for purposes of advancing the present state of the art of coronagraph technology. This document is the Wide Field Infrared Survey Telescope (WFIRST) Pressure Transducer Deliverable Items List and Schedule (DILS).
1.2 Scope
This document lists all of the deliverables for pressure transducer, the SOW paragraph number where the deliverable is described further, the type of response required from NASA GSFC, the format of the deliverable, and the schedule for delivery.
1.3 Related Documentation
The latest versions of all documents below should be used. WFIRST documents can be obtained from URL: https://ipdtdms.gsfc.nasa.gov/.
1.3.1 Applicable Documents [and Forms]
The following documents are referenced within this document and are directly applicable or contain policies or other directive matters that are binding for the contents of this document. In the event of conflict between an Applicable Document and the content of this document, the WFIRST Project Configuration Change Board has the final authority for conflict resolution.
Document Number Title
WFIRST-PROP-SOW-
WFIRST Pressure Transducer Statement of Work (SOW)
1.3.2 Reference Documents
The following documents are referenced herein and amplify or clarify the information presented in this document. These documents are not binding on the content of this document.
Document Number Title
WFIRST-PROP-SPEC-
WFIRST Pressure Transducer Specification
2 DELIVERABLES
Description: This provides the Title of the deliverable item.
Reference: This provides the reference back to the pertinent document calling out the deliverable.
Category:
A = Approval – Items in this category require approval from the National Aeronautics and Space Administration (NASA)/Goddard Space Flight Center (GSFC) Contracting Officer (CO). In general, documents shall be provided in contractor format as long as required content, as specified in the Wide Field Infrared Survey Telescope (WFIRST) Pressure Transducer Statement of Work (WFIRST-PROP-SOW-0017 is addressed. The NASA GSFC CO reserves the time-limited right of disapproval for each submission.
The time-limited period is 30 working days from receipt of documents.
R= Review – Items in this category do not require formal NASA GSFC CO approval, but will be reviewed by the GSFC or its designated representatives in order to determine contractor effectiveness in meeting contract objectives. When Government review reveals inadequacies, the contractor may be requested to correct the inadequacies. GSFC will review and comment within 20 working days of receipt.
I = Information – Items in this category are informal and are for information only.
Format: This provides the format for the deliverable. For documents, the following format applies:
E = Electronic – Provide submittal in electronic format to the COR, and Contracting Officer. The vendor and COR shall jointly determine the type of electronic format (e.g., Word, Excel, PowerPoint, PDF, MATLAB) acceptable for each deliverable.
Table 1. Data Delivery Documentation and Schedule
Item
Description Reference Category Category/Format
1 SOW Compliance Matrix SOW 2.1 With Proposal Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
2 Weekly Status Report SOW 2.2 Weekly Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
For Information Purposes.
3 Milestone List SOW 2.2 With Proposal
4 Notifications SOW 2.3 Seven (7) calendar days in advance of all mandatory hardware inspections, test activities, TIM’s, and deliveries.
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
5 Kick Off Meeting SOW 2.4.1 Fourteen (14) calendar days after contract award
In person at Contractor Facility.
Review Required.
6 Kick Off Meeting Presentation
Package SOW 2.4.1 Three (3) working days before the meeting Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required
7 Design Conformance Review
(DCR)
SOW 2.4.2 Three (3) months after Award of Contract
In person at Contractor Facility.
Review Required.
8 Design Conformance Review
Presentation Package SOW 2.4.2 Fourteen (14) calendar days before DCR Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
9 Design Conformance Review Minutes
SOW 2.4.2 Fourteen (14) calendar days after completion of DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
10 Reserved
11 Reserved
Description Reference Category Category/Format
12 Flight Unit(s) Pre-Ship Review (PSR)
SOW 2.4.5 Seven (7) calendar days prior to delivery of each
Flight Unit
In person at Contractor Facility.
Approval Required.
13 Flight Unit(s) Pre-Ship Review Presentation Package
SOW 2.4.5 At PSR Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
14 Flight Unit(s) End Item Data Package(s) (EIDP)
SOW
2.4.5, 6.7.3, 6.9.3, 6.9.6, 6.10.2
With each delivered Flight Unit and available at PSR Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
15 TIM SOW 2.4.6 As Negotiated In person at Contractor Facility.
Review Required.
16 Interface Control Document(s) SOW 3.1 Preliminary at Kick-off
Meeting, Final at fourteen (14) calendar days before
DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
17 Drawing Package SOW 3.2 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
18 Computer-Aided Design (CAD) Models
SOW 3.3 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
For Information Purposes.
19 Structural Analysis Report SOW 3.4 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
20 Structural Finite Element Model
SOW 3.5 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
Description Reference Category Category/Format
21 Thermal Analysis Report SOW 3.6 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
22 Thermal Model & Documentation
SOW 3.7 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
23 Radiation Hardness Analysis Report
SOW 3.8 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
24 Error Analysis Report SOW 3.15 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
25 Reserved
26 User/Instruction Manual SOW 3.17 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required
27 Reserved
28 Verification Plan (Including Verification Matrix)
SOW 5.1,
6.7.1
Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
29 Individual Verification Test Plan(s) (if needed)
SOW 5.1 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
30 Verification Test Procedure(s) SOW 5.2 Twenty-eight (28) calendar days before start of testing and as changes occur.
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
31 Verification Test Report(s) SOW 5.3 At PSR Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Description Reference Category Category/Format
Review Required.
32 Mission Assurance
Implementation Plan / Quality Assurance Plan
SOW 6.1,
6.5
Twenty-eight (28) calendar days after contract award
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
33 Class I Configuration Management (CM) Changes
SOW 6.2 Seven (7) calendar days after Contractor CM review
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
34 Class II CM Changes SOW 6.2 Seven (7) calendar days after Contractor CM review
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
35 Radiation Test Plans (if applicable)
SOW 6.8.6 Twenty-eight (28) calendar days prior to test.
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
36 Radiation Test Reports SOW 6.8.6 Fourteen (14) calendar days after test
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
37 Recertification Plans for EEE Parts > 5 years old (if applicable)
SOW 6.8.7 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
See
As-Built Materials List SOW 6.9.3 As part of EIDP (DILS #14) Thirty (30) days prior to
PSR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
38 Materials Usage Agreement SOW 6.9.4 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
See
Materials Certificate of Compliance
SOW
6.9.5.4.5, 6.9.6
As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Description Reference Category Category/Format
39 Additive Manufacturing & Qualification Plan SOW
6.9.5.2.2
Thirty (30) calendar days before hardware fabrication
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
40 Fastener Integrity Control Plan SOW
6.9.5.4.1
Thirty (30) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
41 List of Critical Fasteners
SOW
6.9.5.4.1
Thirty (30) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
See
Cleanliness Certification Report
SOW 6.8.2 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
42 Thermal Vacuum Bakeout Plan
SOW
6.10.3
Twenty-eight (28) calendar days prior to beginning of Thermal Vacuum Bakeout
Tests
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
43 Thermal Vacuum Bakeout Test Results (if not part of Thermal Vacuum Report)
SOW
6.10.3
Fourteen (14) calendar days after completion of Thermal
Vacuum Bakeout Tests
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
44 Pressure Transducer Flight Unit(s) Qty: 4 Pressure Transducer Spare Unit(s) Qty: 1
SOW 4.2 12 months after contract award (ACA)
As specified in Clause
GSFC 52.247-94
Approval Required.
45 Pressure Transducer Connector Saver(s)
SOW 4.3 With Item #44 As specified in Clause
GSFC 52.247-94
Approval Required.
46 Pressure Transducer
Supporting Hardware SOW 4.4 With Item #44 As specified in Clause
GSFC 52.247-94
Approval Required.
47 Reserved
Description Reference Category Category/Format
48 As-Designed Materials & Processes List
SOW 6.9.3 Thirty (30) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
49 Qualification by Similarity Report
SOW 2.8 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
50 Reliability Analysis Report SOW 3.9 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
51 Failure Modes and Effects Criticality Analysis (FMECA) Report
SOW 3.10 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
52 Worst Case Analysis (WCA) SOW 3.11 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
53 Anomaly Reporting Plan SOW 6.5 Thirty (30) calendar days after contract award
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
54 Anomaly Review Board (ARB) Minutes
SOW 6.5 24 hours after scheduled
ARB
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
55 EEE Parts Control Plan SOW 6.8.1 Thirty (30) days after contract award
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
56 EEE Parts List SOW 6.8.1 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
57 Stress Derating Analysis SOW 3.12 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Description Reference Category Category/Format
58 Alternate Printed Circuit Board Standard Report (if applicable)
SOW 6.8.2 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
59 Printed Circuit Board (PCB) Procurement Plan
SOW 6.8.2 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
60 Printed Circuit Board (PCB) Test Coupons
SOW 6.8.3 At ATRR format to the COR and
Contracting Officer.
Review Required.
61 Printed Circuit Board (PCB) Test Data
SOW 6.8.3 At PSR format to the COR and
Contracting Officer.
Review Required.
62 Documentation on Use of Water Soluble Flux
SOW 6.8.4 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
63 Lead Free Control Plan SOW 6.8.5 Thirty (30) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
64 Materials and Process Selection, Control, and Implementation Plan
SOW 6.9.1 Fourteen (14) calendar days before DCR format to the COR and
Contracting Officer.
Review Required.
65 Contamination Control Plan SOW 6.10.1
Fourteen (14) calendar days format to the COR and
Contracting Officer.
Review Required.
66 Foreign Object Debris Plan SOW 6.10.4
Thirty (30) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
67 Inputs to System Safety Program Plan (SSPP)
SOW
6.11.1 format to the COR and
Contracting Officer.
Description Reference Category Category/Format
68 Safety Requirements Compliance Checklist
SOW
6.11.2 format to the COR and
Contracting Officer.
Review Required.
69 Safety Data Package, Including Preliminary Hazard Analysis
SOW 3.13 Fourteen (14) calendar days format to the COR and
Contracting Officer.
Review Required.
70 Operations Hazard Analysis (OHA) and Hazard Verification Tracking Log
(VTL)
SOW
6.11.3.1 format to the COR and
Contracting Officer.
Review Required.
71 Reliability Program Plan
(RPP)
SOW
6.12.1 format to the COR and
Contracting Officer.
Review Required.
72 Trend Data Report SOW 3.14 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
73 Limited Life Items Plan SOW 6.12.2
Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
74 Kickoff Meeting Minutes SOW 2.4.1 Three (3) working days after Kickoff Meeting
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
75 Qualification Test Readiness Review (QTRR) (if applicable)
SOW 2.4.3 Seven (7) calendar days before start of Qualification Testing on first Flight Unit
In person at Contractor Facility.
Review Required.
76 QTRR Package (if applicable) SOW 2.4.3 Fourteen (14) calendar days prior to QTRR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
77 Qualification Test Procedure(s) (if applicable)
SOW 2.4.3 Twenty-eight (28) calendar days before QTRR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
78 Reserved
Description Reference Category Category/Format
79 QTRR Minutes (if applicable) SOW 2.4.3 Three (3) working days after QTRR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
80 Acceptance Test Readiness Review (ATRR)
SOW 2.4.4 Seven (7) calendar days before start of Acceptance Testing on first Flight Unit
In person at Contractor Facility.
Review Required.
81 ATRR Package SOW 2.4.4 Fourteen (14) calendar days before ATRR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
82 Acceptance Test Procedures SOW 2.4.4 Twenty-eight (28) days before ATRR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
83 ATRR Minutes SOW 2.4.4 Three (3) working days after ATRR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
84 Reserved
85 Vendor’s Welding and Inspection Procedure
SOW 6.9.7 Twenty-one (21) calendar days after DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
86 Part Notification of Failure (if applicable)
SOW
6.8.10
Twenty-four (24) hours after part failure determination
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
Appendix A Abbreviations and Acronyms
Abbreviation/ Acronym
DEFINITION
ACA After contract award CIR Configuration Initial Release CCB Configuration Control Board CCR Configuration Change Request CM Configuration Management CMO Configuration Management Office CO Contracting Officer COR Contracting Officer's Representative DCR Design Conformance Review DILS Deliverable Items List and Schedule EEE Electrical, Electronic, and Electromechanical EIDP End Item Data Package(s) FMEA Failure Modes and Effects Analysis FMECA Failure Modes and Effects Criticality Analysis GIDEP Government Industry Data Exchange Program GSE Ground Support Equipment GSFC Goddard Space Flight Center I Information INST Instrument NASA National Aeronautics and Space Administration NDE Nondestructive Evaluation PDL Product Design Lead PEM Plastic Encapsulated Microcircuit PER Pre-Environmental Review PSR Pre-Ship Review PWB Printed Wiring Board R Review SOW Statement of Work TBD To Be Determined TBR To Be Resolved TIM Technical Interchange Meeting WFIRST Wide Field Infrared Survey Telescope Yrs years
| 1 Introduction |
| 1.1 Purpose |
| 1.2 Scope |
| 1.3 Related Documentation |
| 1.3.1 Applicable Documents [and Forms] |
| 1.3.2 Reference Documents |
| 2 Deliverables |
| Appendix A Abbreviations and Acronyms |
File details come from the government source that posted it. Updated .