This document is a Performance Work Statement (PWS) for inspecting Well B at the Eielson Air Force Base (EAFB) Water Treatment Facility. The contractor shall provide all personnel, labor, equipment, supervision, and tools necessary to conduct a video inspection of the well casing, screen, and associated equipment to determine the well's current condition and suitability for continued use. Key tasks include a physical inspection of the wellhead and pump, video inspection, disinfection, and operational testing. The contractor shall provide preliminary and final reports within 30 and 60 days, respectively, after completing the inspection. Relevant regulations include UFC 3-230-1, AFMAN 32-1072, and ANSI/AWWA standards.
The related federal contract opportunity is for inspecting Well F, Building 3427, at the EAFB Water Treatment Facility, in addition to Well B. A site visit is scheduled for August 21, 2024, and interested contractors must provide personnel details by August 16, 2024. The end goal is to determine the current condition of the wells and whether further investment is warranted.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage Determinations.pdf | ||
| Well F Performance Work Statement.pdf | ||
| Solicitation - FA500424Q0031 with addendum.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement
Inspect Well B, Bldg 3430 for the EAFB Water Treatment Facility
Eielson Air Force Base March 2024
Prepared By: Sylvin B. Carter
Description of Requirement
1. BACKGROUND/GENERAL SCOPE
1.1 Eielson AFB (EAFB) is served by one water supply system that includes five (5) water wells and a 2.16 MGD water treatment facility to meet EPA, DOD primary and secondary drinking water standards and ADEC (Alaska Department of Environmental Conservation) Alaska Drinking Water Standards, Alaska Drinking Water regulations under section 18 AAC 80. The existing raw groundwater supply currently meets EPA regulations. The groundwater is obtained from four (4) wells (A, B, E, F) located throughout the base. An additional well (No. 7) is located on the southeast end of the runway and is tied directly into the water distribution without treatment, except for chlorine disinfection and a corrosion inhibitor which is added at Wellhouse No. 7. This wellhouse only operates upon a high demand, low pressure situation (fire flow demand scenario typically) in this area of the distribution system.
Over time as a water well ages, the rate at which water may be pumped (commonly referred to as the well yield, flow, or performance) tends to decrease especially in wells that were not particularly properly developed when they were first drilled. B Well, (Bldg 3430) was first established in the 1950s and was drilled to a depth of 89.5 feet with the well casing being 12 inches in diameter. The well has a static water level of 8.8 feet below the top of the steel casing and had a yield of 900 gpm. Because Well B has highest levels of PFC contamination of all the source water wells used for potable water production it is seldom used. However, the government is still leaning forward with getting Well B video inspected to verify the well’s current condition as it still viable option for source water for potable water production. When a well’s production begins to reduce this reduction can be attributed to many different changes in the well or to the physical condition of equipment such as decreased water level in the well, decreased specific capacity, increased sand or sediment content in the water, incrustation from mineral deposits, bio-fouling by the growth of microorganisms, physical plugging of the aquifer by sediment, well screen or casing corrosion including to damage to the well pump.
1.2 The contractor shall provide all personnel, labor, equipment, supervision and tools necessary IAW UFC 3-230-1, Change 1, WATER TREATMENT; AFMAN 32-1072, WATER-WELL DRILLING OPERATIONS; ANSI/AWWA Standard A100-20, WATER WELLS; 18 AAC 80, DRINKING WATER, Alaska Drinking Water Regulations or any other applicable military, state, federal and environmental regulations or industry standards not mentioned herein this document to Inspect Well B, Bldg 3430 at the EAFB Water Treatment Facility. The end goal of this project is to ensure the government knows the current condition of the well casing, screen, down pipe any other pertinent equipment or structures necessary for Well B that would enable the government to determine if further investment is warranted. This would be based off information gathered from the closed-circuit video inspection of the parts of the well deemed necessary for its proper operation.
1.3 The contractor shall first be responsible for conducting a complete physical inspection of the exterior of the wellhead seal and pump, pump motor then a video inspection of the internal condition of the well casing, well screen, pump stages/bowls and any other pertinent associated equipment needed for the efficient/necessary operation of the well.
The contractor will be responsible for the physical removal and reinstallation of all equipment that would enable them to perform the video inspection of the well. The equipment that was reinstalled must be fully operational at the conclusion of the inspection.
1.4 Before the contractor re-installs the equipment removed for the closed-circuit video inspection the contractor shall comply with the requirements IAW ANSI/AWWA Standard C654-13, DISINFECTION OF WELLS and thoroughly disinfect the well. Allow the well to rest for at least 12 hours before pulling samples for coliform bacteria. If the test results confirm a negative presence of coliform bacteria the contractor shall re-install the refurbished well pump and motor or install the new well pump and motor. The contractor shall provide written notification to government of the negative coliform bacteria test results.
1.5 With the well pump and motor and any other necessary equipment correctly installed the contactor shall conduct all necessary/required operational tests of the re-installed existing pump and motor and complete necessary/required documentation per the requirements of AWWA Standard A100-20, WATER WELLS.
1.6 The contractor shall provide a preliminary report within 30 calendar days followed by the final report to include the video inspection to the government within 60 calendar days after completion of this project. The contractor shall provide the government both physical and electronic copies of video inspection preliminary and final reports.
1.7 The contractor shall ensure proper transport and disposal of all waste materials IAW
Eielson AFB, ADEC, and EPA HAZWaste regulations and requirements as part of this project.
1.8 The contractor shall be responsible for the coordination and completion of all documentation that is required to meet ADEC regulations in the event the well design is changed because of this project for final approval to construct and/or operate. The government shall be provided with electronic/hard copies off all documents that are provided to ADEC.
2 LOCATION
2.1 EAFB is located approximately 26 miles southeast of Fairbanks, Alaska. The Water Treatment Plant is in Building 3228. This facility is accessible from Central Avenue and is contained within the secured portion of the base. Please follow instructions posted on the sign at the front gate of the Water Treatment Facility for entry.
3 GENERAL INFORMATION
3.1 Contractor shall supply names of customer service representatives who will be always available. Contractor must be available during the period of Oct - Dec 2024 and maintain proper coordination with COR.
3.2 The well is enclosed in a heated building that has roof access to facilitate in the inspection/removal of the well casing, motor, and/or pump.
4.0 DELIVERABLES
Description Due Date The contractor shall first be responsible for conducting a complete physical inspection of the exterior of the wellhead seal and pump, pump motor then a video inspection of the internal condition of the well casing, well screen, pump stages/bowls and any other pertinent associated equipment needed for the efficient/necessary operation of the well. The contractor will be responsible for the physical removal and reinstallation of all equipment that would enable them to perform the video inspection of the well. The equipment that was reinstalled must be fully operational at the conclusion of the closed-circuit video inspection.
Within 45 calendar days after being given NTP by the contracting officer.
Contractor shall conduct coliform bacteria testing and provide the government with negative test results confirming the well is free of any coliform bacteria contamination.
Within 3 calendar days of properly disinfecting the well.
Contractor shall provide the government with electronic and physical copies of the preliminary report followed by a final report and closed-circuit video inspection of the well.
Within 30 calendar days of the completion of the closed-circuit video inspection provide the government the preliminary report and within 60 calendar days the final report and closed-circuit video inspection.
5. SUPPLEMENTAL INFORMATION
5.1. The following personnel are representatives for this project:
Mr. Sylvin B. Carter, Water Systems Superintendent:
Phone#: 907-377-1449, E-mail: sylvin.carter.1@us.af.mil
SSgt Michael Bethune, Water Treatment Plant NCOIC:
Phone#: 907-377-5148, E-mail: michael.bethune@us.af.mil
5.2. Base Notification - The Contractor shall contact one of the representatives identified above no later than 72 hours before starting site operations so base access can be obtained.
5.3. Site Visit - The contractor shall become thoroughly familiar with all details of the process to ensure proper water treatment. The contractor will advise the contracting officer of any discrepancies before performing any work.
5.4. Protection of Government Property and Personnel - The contractor shall protect Government and non-Government property and personnel on-base from inconvenience, damage, or injury of any nature.
5.4.1. The contractor shall accomplish the work in accordance with applicable Base Safety and Fire Prevention regulations, Air Force regulations, and such other measures as deemed applicable.
5.4.2. Damages of any nature caused by this work shall be repaired or damaged property replaced at no expense to the Government.
5.4.3. If the contractor does not satisfactorily repair or replace the damaged property, the
Government reserves the right to make the necessary corrections.
5.4.4. The contractor shall reimburse the Government for consequential damages and for all materials and labor used for the corrections.
5.5. The contractor is responsible for the storage and safekeeping of all material to be used in the completion of work.
5.6. The contractor shall keep the work area clean of all debris. The contractor shall keep storage areas clean and orderly. The contractor shall dispose of all wastes and not allow them to accumulate.
5.7. The contractor shall comply with base regulations regarding Hazardous Materials
(HAZMAT) and ensure procedures meet all applicable policies, publications, and protocols in this contract. Provide Bio-environmental engineer service with a Safety Data Sheet (SDS) on all first time purchase of hazardous items obtained through local sources of supply and obtain approval prior to purchase.
5.8. The Government will provide emergency medical treatment and emergency patient transportation service for contractor personnel who are injured or become critically ill while at Eielson AFB. Treated personnel will be responsible for reimbursing the mailto:sylvin.carter.1@us.af.mil mailto:michael.bethune@us.af.mil government for the cost of medical treatment and patient transportation at the current inpatient or outpatient treatment rate.
5.9. The contractor shall ensure each employee obtains pass and identification items as applicable for contractor personnel and contractor-owned vehicles. The contractor will maintain a current list of employees.
5.10. The list will include employee names along with information required in the REAL ID. (REAL ID compliance information website: https://www.dhs.gov/real-id enforcement-brief.) This list is required to be provided to the contracting officer and t h e servicing security forces organization, to include updated copies for any changes during the duration of the contract.