This is a delivery schedule specification document for bread products required by the Federal Bureau of Prisons at FCI Manchester. Weekly bread deliveries are mandated for the period from June 1, 2026, through September 30, 2026, with delivery windows strictly between 8:00 a.m. and 2:00 p.m. EST. Federal holiday deliveries are not accepted. The Food Service Department will contact the contractor weekly to specify quantities needed, with all orders coordinated through authorized individuals to be identified at contract award. Deliveries must be palletized and scheduled in advance with the Food Services Warehouse prior to each delivery date.
The document establishes strict compliance requirements for product condition and temperature control: non-frozen perishable foods must arrive between 34°F and 41°F, canned goods above 34°F and unfrozen, and frozen foods at 0°F or below, with any evidence of prior thawing resulting in automatic refusal. All items must meet solicitation specifications and are subject to inspection and testing for up to three days, with non-conforming products either repaired, replaced, or reperformed at no additional cost to the government. Vendors are responsible for picking up rejected items within two weeks of notification at their own expense. Failure to maintain delivery schedules without excusable delay or meet contract specifications will negatively impact the contractor's past performance record and affect future award eligibility.
Text of this file
FCI Manchester Deliver Schedule– Requirement: Bread products Delivery Schedule: Weekly
FCI Manchester Food Service Department requires weekly delivery of bread products.
The period of performance will be June 1st, 2026, through September 30th, 2026.
Please specify the delivery schedule on solicitation. Deliveries must be made between the hours of 8:00 am and 2:00 pm EST. Federal holiday deliveries will not be accepted.
The quantities listed in the solicitation and any subsequent award are estimated maximum throughout the quarter.
The ordering procedures are as such. Weekly, the local food services administration will contact you to notify you of the quantities required to be delivered to the Food Services warehouse for the upcoming week. The notification of the authorized individuals to order will be identified at the time of the award.
Upon Award, the Food Service Warehouse must be contacted prior to delivery for approval or adjustments in delivery schedule. Delivery schedules will be strictly enforced. Failure to deliver within the established time frame will be considered as nonconformance to the terms of the contract.
| All items will be closely inspected. |
| All deliveries must be palletized. |
All non-frozen, perishable foods must be delivered between 34 degrees F and 41 degrees F.
All canned goods must be delivered above 34 degrees F and not frozen.
All frozen foods must be delivered at 0 degrees F or below. Any product that indicates prior thawing will be refused.
All certified religious diet items must be marked with the Kosher Symbol on individual packages, or the item will be refused.
| Receipt of delivery may be conditional for a period of three (3) days in order to allow for adequate examination and testing. |
| Some items may require thawing and cooking to determine specifications compliance. |
Items that fail to meet specifications will be refused.
If the product is not accepted, in accordance with FAR 52.212-4 (a), “The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price.”
Items which are conditionally received, and found to be unacceptable, must be picked up at the vendors' expense within two (2) weeks of noncompliance notification.
If the product is not picked up within two (2) weeks, it will be disposed of by warehouse staff.
Items must meet specifications as indicated on the solicitation and award.
All items will be closely inspected prior to acceptance.
See FAR 52.212-4 (a) Inspection and Acceptance.
https://www.acquisition.gov/far/52.212-4?searchTerms=52.212-4"https://www.acquisition.gov/far/52.212-4?searchTerms=52.212-4 Contractor failure to meet delivery schedules without an excusable delay and/or failure to conform to contract specifications will negatively affect the contractor's history of past performance. Past performance information may be used by the Government to make future award decisions and/or may result in a finding that the quoter is not responsible for the award of future requirements.
Other files
| File | Type | Posted |
|---|---|---|
| BRQ 15B11026Q00000013.pdf | ||
| BRQ 15B11026Q00000013.pdf | ||
| BRQ 15B11026Q00000013.pdf | ||
| POST TO SAM.gov FY27 1st QTR BREAD.pdf | ||
| 1. Quote Sheet Cover.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .