Statement of Work
75 KB Posted
- Solicitation number
- WC133W-10-RQ-0359
About this file
Statement of Work (SOW)
Text of this file
Rev. 2/15/09
NWS
Statement of Work
Lawn Service and other grounds keeping Requirements
Scope:
The contractor shall provide all tools, equipment, materials and supervision for the duties required to care for all of the grounds within the boundaries of the Weather Forecast Office as described in this statement of work.
Description of Work:
The Contractor shall;
Weekly:
| 1. | Mow all grassy areas on the property. |
| 2. | Trim with a string trimmer around the buildings, driveway, sidewalks, equipment and |
other stationary objects.
| 3. | Rake, as needed, to remove excess clippings, leaves or other debris. |
| 4. | Use a broom or a blower to remove clippings from the parking areas and sidewalks. |
| 5. | Remove weeds or grasses growing in shrubbery areas or mulch-covered areas. |
| 6. | Use an edger to cut along all sidewalks and other edges as necessary. |
| 7. | Bag and remove all clippings and debris from the site using approved methods which |
follow all Federal, State and Local laws and regulations.
Additional Requirements:
The Contractor shall:
| 1. | Prune and trim all shrubbery at the appropriate time in the Spring and Fall. |
| 2. | Fertilize lawn, trees, and shrubs, and treat for weeds, crabgrass and insects. These |
applications shall follow a schedule of:
| a. | Spring - Pre-emergent, fertilizer, and broadleaf weed and crabgrass control. |
| b. | Late Spring - Slow release fertilizer and broadleaf weed and crabgrass control. |
| c. | Summer - insect control (including grubs) application. |
| d. | Fall - Broadleaf weed control and micronutrients. |
3. Additional work not covered in specifications, may be required upon request by the MIC.
Contractor will be compensated for the additional work at an hourly rate, which should be included in the contract.
Inspections and Acceptance:
The Meteorologist in Charge or their designee has designated authority to make a full inspection to see that the contract is completed per the statement of work. The contractor will be notified immediately if any items are sub-standard.
Location:
It is the intent for this Statement of Work that the work specified will commence at a negotiated date when the contract has been awarded. The location is:
National Weather Service
Chicago Weather Forecast Office
1234 Airport Road
Romeoville, IL 60446-1804
FFG Rev. 02/15/08 Section 5c Page 1
Terms of the SOW:
| 1. | The Contractor will bill on a monthly basis in arrears for the service provided. |
| 2. | The contractor, if remotely located, shall designate a representative local to the contract |
site, with contact numbers, for the government's local representative to communicate with about the quality or work, progress, and technical details of the project.
3. The government reserves the right to waive lawn care or request lawn care to ensure the grounds keep a well-maintained appearance.
| 4. | The Contractor shall ensure that all debris is cleaned up before they leave. |
| 5. | The Contractor shall ensure that no hoses or tools are left out or placed (used) in such a |
way that they become a trip hazard or impede normal access to the buildings and property.
-END OF SOW
FFG Rev. 02/15/08 Section 5c Page 2
Other files
| File | Type | Posted |
|---|---|---|
| WC133W-10-RQ-0359 | — | |
| Wage Determination | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .