Air conditioner coil replacement for ice plant
Atlantic Oceanographic and Meteorological Laboratory Statement of Work
Version 2.1 5/26/2010
Presented by:
Hector L. Casanova
Gregory Banes i
Contents
1. INTRODUCTION
2. SCOPE
3. GENERAL
3.1. CHILLER SPECIFICATIONS
4. REFERENCES:
5. REQUIREMENTS
5.1. FREON:
5.2. CONDENSER COILS:
5.3. CONDENSER FANS:
6. LIST OF GOVERNMENT FURNISHED MATERIAL
A. N/A
7. TECHNICAL TASKS
7.1. EVALUATE EXISTING COIL SYSTEM
7.2. COIL INSTALLATION
7.3. TESTING AND CERTIFICATION
8. DELIVERABLES
9. SPECIAL CONSIDERATIONS
9.1. SITE VISIT IS REQUIRED
9.2. BID OPTIONS TO CONSIDER FOR THIS PROJECT
9.3. COMPLETION DATE:
9.4. COORDINATION:
APPENDIX
NOAA/AOML
May 26, 2010
1. Introduction
The Atlantic Oceanographic and Meteorological Laboratory, located on Virginia Key Florida is a 6-story (5 floors and basement) research facility owned by the National Oceanic and Atmospheric Administration. The facility is served by a single York Codepack Chiller system (which replaced the facilities original chiller), located in the 4th floor, is connected to a cooling tower, via condenser water pumps and chilled water pumps. The main chiller is in good working order. An off peak thermal ice storage chiller and storage system, located in the ground level, was added to the plant via a program with Florida Power & Light (FP&L). There are currently 2 years remaining on this 10-year energy services project arrangement with FP&L.
2. Scope This Statement of Work (SOW) details the requirements for replacement, installation and testing of mechanical and electrical components to change the coils system inside the ground level chiller.
3. General
3.1. Chiller specifications
The ground level chiller is located on ground level, close to the south side of the building towards the Rickenbacker Causeway.
• Volts/Ph/HZ: 460V/3/60Hz
• Tonnage: 180 tons
• Model Number: YCAS0180EC46YFA
• Refrigerant: R22
• Single point power connection with non-fused disconnect switch and separate system circuit breakers
• York rotary twin-screw compressor. Independent refrigerant circuits with liquid line stop valves with charging ports, liquid line filter driers, liquid line solenoid stop valves, moisture indicator-sight glasses and direct- acting thermal expansion valves
• Direct expansion type shell and tube cooler with ½” insulation
• Air-cooled condenser with 3-pahse totally enclosed fan motors, sub-cooling circuit and ambient control to 25°
• Unit RIS vibration isolators
See Appendix for more information.
4. References:
a. Millennium Air Cooled Screw Liquid Chillers (STYLE G) - FORM 201.19-EG1 (803).
Available upon request.
5. Requirements
5.1. Freon:
a. Freon shall be recovered and stored on site for recharge.
5.2. Condenser coils:
a. The bad condenser coils shall be removed from the station and stored on site for removal by NOAA facility personnel
5.3. Condenser fans:
a. Condenser fans shall be removed and stored in a safe location as not to be scratch, dented or damage in any form and reinstall on a later time, after coils have been replaced.
6. List of Government Furnished Material
a. N/A
7. Technical Tasks
7.1. Evaluate existing coil system
a. Evaluate existing coils for integrity and capacity.
7.2. Coil Installation
a. Work with AOML personnel to determine the exact position where condenser fans will be temporarily stored.
b. The new condenser shall be coated with Polly blend urethane that is designed to resist corrosive effects of salt laden coastal environments, and inhibits mold and mildew growth.
c. Condenser fans will be reinstalled and tested for proper rotation.
d. Prior to departing for the day, the chiller will be on pressure test for morning recharge liquid line filters will need to be replaced, as they are exposed to environmental exposure.
7.3. Testing and Certification
a. The new condenser coils shall be install and leak tested overnight with dry nitrogen.
The chiller will be recharge pending on overnight leak test results.
b. Circuits will be properly evacuated and recharged. Circuits and fans will be checked for proper operation.
c. Certify results
8. Deliverables
a. Proper working condenser coil system and chiller.
b. Certification or report pertaining to leak tests and proper chiller operations
c. All manuals and data sheets from any new pieces of installed equipment
d. Warranty paperwork
9. Special considerations
9.1. Site visit is required
9.2 Replace condenser coils duel circuit system and fans and install new condenser coils keeping the older 150 ton York unit running (located on the 4th floor) to cool the building.
9.3. Completion Date:
a. All work shall be completed no later than 8 weeks after being awarded.
Kevin.J.Buum Sticky Note Accepted set by Kevin.J.Buum
Kevin.J.Buum Sticky Note Accepted set by Kevin.J.Buum
Kevin.J.Buum Sticky Note Unmarked set by Kevin.J.Buum
Kevin.J.Buum Sticky Note Unmarked set by Kevin.J.Buum
Kevin.J.Buum Cross-Out
Kevin.J.Buum Cross-Out
Kevin.J.Buum Cross-Out
Kevin.J.Buum Cross-Out All work shall be completed AS SOON AS POSSIBLE, but no later than 8 weeks from the date of award. This replacement is a high priority that requires RUSH DELIVERY and INSTALLATION.
Kevin.J.Buum Cross-Out
Kevin.J.Buum Cross-Out
Kevin.J.Buum Sticky Note Accepted set by Kevin.J.Buum
9.4. Coordination:
a. Close coordination with NOAA personnel to ensure a successful project completion.
The contact persons are as follows:
Greg Banes 305-361-4456 Hector Casanova 305-361-4544
Appendix
YORK INTERNATIONAL32 YORK INTERNATIONAL
FORM 201.19-EG1
MODEL NUMBER YCAS
0130EC 0140EC 0150EC 0160EC 0170EC 0180EC 0200EC 0210EC 0230EC
General Unit Data Unit Capacity at ARI Conditions, Tons 121.1 130.1 145.3 157.1 164.3 171.6 186.7 194.8 209.1 Number of Independent Refrigerant Circuits 2 2 2 2 2 2 2 2 2 Refrigerant Charge, R-22, Ckt.-1 / Ckt.-2, lbs. 180 / 180 180 / 180 180 / 190 190 / 190 190 / 190 190/190 220/220 220/220 220/220 Oil Charge, Ckt.-1 / Ckt.-2, gallons 5 / 5 5 / 5 5 / 5 5 / 5 5 / 5 5 / 5 5 / 5 5 / 5 5 / 5 Shipping Weight:
Aluminum Fin Coils, lbs. 9,888 10,110 10,599 10,583 10,694 10,805 11,849 11,970 12,081 Copper Fin Coils, lbs. 11,154 11,376 11,865 11,849 11,960 12,071 13,441 13,552 13,663 Operating Weight:
Aluminum Fin Coils, lbs. 10,315 10,537 11,263 11,247 11,358 11,469 12,513 12,634 12,745 Copper Fin Coils, lbs. 11,581 11,803 12,529 12,513 12,624 12,735 14,105 14,216 14,327 Compressors, DXS Semihermetic Twin Screw Quantity per Chiller 2 2 2 2 2 2 2 2 2 Nominal Ton Size, Ckt.-1 / Ckt.-2 62 / 62 68 / 68 78 / 68 78 / 78 85 / 78 85/85 95/95 105/95 105/105 Refrigerant Economizer, Ckt.-1 / Ckt.-2 No / No Yes / Yes No / Yes No / No Yes / No Yes / Yes No / No Yes / No Yes / Yes Condensers, High Efficiency Fin / Tube with Integral Subcooler Total Chiller Coil Face Area, ft2 256 256 256 256 256 256 320 320 320 Number of Rows 3 3 3 3 3 3 3 3 3 Fins per Inch 13 13 13 13 13 13 13 13 13
CONDENSER FANS
Number, Ckt.-1 / Ckt.-2 4 / 4 4 / 4 4 / 4 4 / 4 4 / 4 4 / 4 5 / 5 5 / 5 5 / 5 Standard Fans Fan Motor, HP / kW 2 / 1.8 2 / 1.8 2 / 1.8 2 / 1.8 2 / 1.8 2 / 1.8 2 / 1.8 2 / 1.8 2 / 1.8 Fan & Motor RPM 1140 1140 1140 1140 1140 1140 1140 1140 1140 Fan Diameter, inches 35.4 35.4 35.4 35.4 35.4 35.4 35.4 35.4 35.4 Fan Tip Speed, feet/min. 10,575 10,575 10,575 10,575 10,575 10,575 10,575 10,575 10,575 Total Chiller Airflow, CFM 114,400 114,400 114,400 114,400 114,400 114,400 143,000 143,000 143,000 Low Noise Fans Fan Motor, HP / kW 2 / 1.53 2 / 1.53 2 / 1.53 2 / 1.53 2 / 1.53 2 / 1.8 2 / 1.8 2 / 1.8 2 / 1.8 Fan & Motor Speed, RPM 840 840 840 840 840 1140 1140 1140 1140 Fan Diameter, inches 35.4 35.4 35.4 35.4 35.4 35.4 35.4 35.4 35.4 Fan Tip Speed, feet/min. 7,792 7,792 7,792 7,792 7,792 10,575 10,575 10,575 10,575 Total Chiller Airflow, cfm 112,400 112,400 112,400 112,400 112,400 114,400 143,000 143,000 143,000 High Static Fans Fan Motor, HP / kW 5 / 3.79 5 / 3.79 5 / 3.79 5 / 3.79 5 / 3.79 5 / 3.79 5 / 3.79 5 / 3.79 5 / 3.79 Fan & Motor RPM 1140 1140 1140 1140 1140 1,140 1,140 1,140 1,140 Fan Diameter, inches 35.4 35.4 35.4 35.4 35.4 35.4 35.4 35.4 35.4 Fan Tip Speed, feet/min. 10,575 10,575 10,575 10,575 10,575 10,575 10,575 10,575 10,575 Total Chiller Airflow, CFM (@0.4" additional static) 114,400 114,400 114,400 114,400 114,400 114,400 143,000 143,000 143,000 Evaporator, Direct Expansion Water Volume, gallons 53 53 55 55 55 55 79 79 79 Maximum1 Water Side Pressure, PSIG 150 150 150 150 150 150 150 150 150 Maximum Refrigerant Side Pressure, PSIG 350 350 350 350 350 350 350 350 350 Minimum Chilled Water Flow Rate, GPM 138 138 200 200 200 200 250 250 250 Maximum Chilled Water Flow Rate, GPM 525 525 600 600 600 600 750 750 750 Water Connections, inches 8 8 8 8 8 8 8 8 8
Physical Data
1 Optional 300 PSIG Waterside available
ENGLISH UNITS
YORK INTERNATIONAL10 YORK INTERNATIONAL
Temperatures and Flows
TEMPERATURE AND FLOWS
(English Units)
NOTES:
1. For leaving brine temperature below 40°F (4.4°C), contact your nearest YORK office for application requirements.
2. For leaving water temperature higher than 55°F (12.8°C), contact the nearest YORK office for application guidelines.
3. The evaporator is protected against freezing to -20°F (-28.8°C) with an electric heater as standard.
MODEL
NUMBER
YCAS
LEAVING WATER
TEMPERATURE (°F)
COOLER FLOW
(GPM3) AIR ON CONDENSER (°F)
MIN.1 MAX.2 MIN. MAX. MIN. MAX
0130EC 40 55 138 525 0 125
0140EC 40 55 138 525 0 125
0150EC 40 55 200 600 0 125
0160EC 40 55 200 600 0 125
0170EC 40 55 200 600 0 125
0180EC 40 55 200 600 0 125
0200EC 40 55 250 750 0 125
0210EC 40 55 250 750 0 125
0230EC 40 55 250 750 0 125
0250EC 40 55 225 800 0 125
0270EC 40 55 225 800 0 125
0300EC 40 55 255 800 0 125
0330EC 40 55 255 800 0 125
0360EC 40 55 300 1060 0 125
0400EC 40 55 330 1060 0 125
0440EC 40 55 330 1060 0 125
YORK INTERNATIONAL36 YORK INTERNATIONAL
LD03742
Dimensions – YCAS0130 - 0180 (English)
NOTES:
1. Placement on a level surface free of obstructions (including snow, for winter operation) or air recirculation ensures rated performance, reli-able operation and ease of maintenance. Site restrictions may compromise minimum clearances indicated below, resulting in unpredictable air flow patterns and possible diminished performance. YORK’s unit controls will optimize operation without nuisance high pressure safety cutout; however, the system designer must consider potential performance degradation. Access to the unit control center assumes the unit is no higher than on spring isolators. Recommended minimum clearances: Side to wall - 6'; rear to wall - 6'; control panel end to wall - 4'; top
- no obstructions allowed; distance between adjacent units - 10'. No more than one adjacent wall may be higher than the unit.
LD03742a
MODELS MODELS
DIMENSION 130 - 140 150 - 180
P 17-1/4" 18"
YORK INTERNATIONAL36 YORK INTERNATIONAL
LD03744
LD03743
CENTER OF GRAVITY (Copper)
YCAS X Y Z
0130 103.5" 44.4" 40.7" 0140 103.5" 44.4" 40.7" 0150 108.2" 43.0" 39.2" 0160 108.4" 43.1" 39.1" 0170 108.4" 43.1" 39.1" 0180 108.4" 43.1" 39.1"
CENTER OF GRAVITY (Alum.)
YCAS X Y Z
0130 101.3" 44.4" 37.8" 0140 101.3" 44.4" 37.8" 0150 106.7" 42.8" 36.2" 0160 107.0" 43.0" 36.2" 0170 107.0" 43.0" 36.2" 0180 107.0" 43.0" 36.2"
Other files
| File | Type | Posted |
|---|---|---|
| WC133R-10-RQ-0998 | — | |
| Wage Determination | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .