FormSF30_A0001.pdf
PDF 1 MB Posted
- Attached to
- Renovation to Woods Hole Office - NOAA, NMFS, Northeast Fisheries Science Center, Woods Hole, MA
- Solicitation number
- WC-133F-15-RQ-0499
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_2.pdf | ||
| WC-133F-15-RQ-0499_Drawings.pdf | ||
| WC-133F-15-RQ-0499.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NSN 7540-01-152-8070 STANDARD FORM 30. (Rev. 10-83) Previous Edition unusable Prescribed by GSA FAR (48 CFR) 53.243
Page of Pages AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code
2. AMENDMENT MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (if applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than item 6) CODE
(x) 9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
8. NAME AND ADDRESS OF CONTRACTOR (NO., Street, Country, State and ZIP Code)
CODE FACILITY CODE
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning ______ copies of amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OR OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
Check One
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _______ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 16B. UNITED STATES OF AMERICA
(Signature of person authorized to sign)
15C. DATE SIGNED
(Signature of Contracting Officer)
16C. DATE SIGNED
Attachment Page
PAGE 2 OF 19 WC-133F-15-RQ-0499/A0001
The SOLICITATION is amended as follows:
1. SOLICITATION: The required response date/time has change June 19, 2015 at 2 p.m. CST.
2. The following Provision and Clause has been added by Reference:
a. 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
3. The following Provision and Clause has been added by full text:
a. 52.203-98, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements— Representation (DEVIATION 2015-02)
b. 52.252-6, Authorized Deviations in Clauses (APR 1984)
c. Representation by Corporations Regarding an Unpaid
Delinquent Tax Liability or a Felony Conviction Under Any Federal Law (Class Deviation) (March 2015)
d. Submittal of Invoices
4. STATEMENT OF WORK: A revised Statement of Work is attached to this amendment. NOTE: Deleted text is shown with strikethrough. Added text is shown with underline.
5. DRAWING: Drawing Number 5 “2nd Floor Office Modernization.”
6. Incorporates Davis Bacon General Wage Decision Number MA150001
05/08/2015 MA1 or the most recent Davis Bacon General Wage Decision.
7. All other terms and conditions remain unchanged and in full force.
PAGE 3 OF 19 WC-133F-15-RQ-0499/A0001
52.203-98, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements—Representation (DEVIATION 2015-02)
Insert the following provision in all solicitations that will use Federal funds, including solicitations for the acquisition of commercial items under FAR part 12.
PROHIBITION ON CONTRACTING WITH ENTITIES THAT REQUIRE CERTAIN INTERNAL CONFIDENTIALITY
AGREEMENTS—REPRESENTATION (FEB 2015)
(a) In accordance with section 743 of Division E, Title VII, of the Consolidated and
Further Continuing Resolution Appropriations Act, 2015 (Pub. L. 113-235), Government agencies are not permitted to use funds appropriated (or otherwise made available) under that or any other Act for contracts with an entity that requires employees or subcontractors of such entity seeking to report fraud, waste, or abuse to sign internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting such waste, fraud, or abuse to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information.
(b) The prohibition in paragraph (a) of this provision does not contravene requirements applicable to Standard Form 312, Form 4414, or any other form issued by a Federal department or agency governing the nondisclosure of classified information.
(c) Representation. By submission of its offer, the Offeror represents that it does not require employees or subcontractors of such entity seeking to report fraud, waste, or abuse to sign internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting such waste, fraud, or abuse to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information.
(End of provision)
PAGE 4 OF 19 WC-133F-15-RQ-0499/A0001
52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any COMMERCE ACQUISITION REGULATION (CAR) (48 CFR Part 1352 clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of Clause)
PAGE 5 OF 19 WC-133F-15-RQ-0499/A0001
Representation by Corporations Regarding an Unpaid Delinquent Tax Liability or a Felony Conviction Under Any Federal Law (Class Deviation) (March 2015)
(1) In accordance with Sections 744 and 745 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235), none of the funds made available by the Consolidated and Further Continuing Appropriations Act, 2015 funding may be used to enter into a contract with any corporation that-
(a) Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where an awarding agency is aware of the conviction, unless the agency has considered suspension or debarment of the corporation and has made a determination that this further action is not necessary to protect the interests of the Government, or
(b) Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless the agency has considered suspension or debarment of the corporation and made a determination that this further action is not necessary to protect the interests of the Government.
(2) The Offeror represents that, as of the date of this offer -
(a) It is [ ] is not [ ] a corporation that was convicted of a felony criminal violation under a Federal law within the preceding 24 months.
(b) It is [ ] is not [ ] a corporation that has any unpaid
Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability.
(End of provision)
PAGE 6 OF 19 WC-133F-15-RQ-0499/A0001
Submittal of Invoices
SUBMITTAL OF INVOICES
The Contractor shall prepare and submit an invoice to the Contracting Officer's Representative (COR) for approval [with a copy to the Contracting Officer for information]. All payments shall be submitted by the 10th day of the subsequent month.
To constitute a proper invoice, the contractor's invoice shall be prepared in accordance with and contain all elements specified in, the paragraph entitled "Contractor's Invoice" of the applicable prompt payment provision of the contract (e.g., FAR 52.232-25 Prompt Payment, FAR 52.232-26 Prompt Payment for Fixed-Price Architect Engineer Contracts, or FAR 52.232-27 Prompt Payment for Construction Contracts). For contracts and orders for commercial items and services, paragraph(g) of FAR 52.212-4 entitled "Invoices" applies.
If the invoice does not comply with the applicable prompt payment provision of the contract, the COR will return it to the contractor within seven (7) days after the date the designated office received the invoice along with a statement as to the reasons why it is not a proper invoice.
(End of Clause)
PAGE 7 OF 19 WC-133F-15-RQ-0499/A0001
Statement Of Work Woods Hole Office Upgrades
5/20/2015
SECTION 01
GENERAL REQUIRMENTS
PART 1 GENERAL
1.01 DESCRIPTION
A. Work shall be completed at the NMFS/Northeast Fisheries Science Center, located at 166 Water Street Woods Hole, Ma. 02543-1026.
B. Demolition of block walls, metal and wood stud walls, electrical, suspended ceilings, lights, doors and frames and other work described within the contract documents.
C. Installation of new metal furring wall support system, metal stud walls, gypsum, electrical, suspended ceiling, lights, painting, walls, carpeting, doors and frames, Ductless AC/heat pump, and other work described within the contract documents.
D. Contractor shall be required to relocate, and/or move any obstacle preventing work from meeting all requirements within the contract documents.
E. Relocation office furniture, bookcase, file cabinets, printers, books and other office equipment and furniture.
1.02 CONTACT INFORMATON
A. Mr. Jack Emberg is the Contracting Officer Represenative (COR). Mr. Emberg is located at the NMFS/Northeast Fisheries Science Center, located at 166 Water Street Woods Hole, Ma. 02543 and can be reached at 508-495-2219 or by email jack.emberg@noaa.gov.
B. Mr. Nicholas DeGuire is the Contracting Officer (CO). Mr. Emberg is located at the NMFS/Northeast
Fisheries Science Center, located at 601 E. 12th Street, Room 1734, Kansas City, MO 64106 and can be reached at 816-426-2367 or by email nicholas.j.deguire@noaa.gov.
1.03 EXTENT OF WORK
A. Provide all labor, material, supplies, tools, equipment, and supervision necessary to complete the work described and shown in the drawings, specifications, accordance with the manufacturer’s most current specifications and details to ensure the requirements in the contract documents, meet or exceed best practices as recommended by manufacture(s), NEC, BOCA, NFPA, UL, ASTM and other standard not specifically listed.
B. The contractor shall be fully knowledgeable of all requirements of the contract documents and shall make themselves aware of all job site conditions that will affect their work.
C. Room dimensions shown on plans are approximate and not to scale. Contractor shall verify ALL dimensions prior to submitting bid.
D. Demolition includes but not limited to:
1. Block walls, wood and metal walls,
2. Suspended ceiling and lights,
3. Steel frame, steel doors,
4. Relocation of electrical outlets,
5. Relocation of Data network outlets, PAGE 8 OF 19 WC-133F-15-RQ-0499/A0001
6. Carpeting,
7. Wall paneling and other wall coverings,
8. Gypsum,
9. Electrical outlets and switches,
10. Cut door frame openings,
11. Legally dispose all debris.
E. Supply and install but not limited to:
1. Suspended ceiling system,
2. Furring and metal stud system capable of supporting gypsum walls,
3. Gypsum,
4. Painting (2 coats) and priming (1 coat),
5. Carpet and sub carpet,
6. Lights,
7. Duplex electrical outlets, light switches, and wiring,
8. IT outlets with pull strings,
9. Patch block walls were demolition took place,
10. Thresholds,
11. Trim work,
12. Metal Stud walls,
13. Insulation and sound proofing,
14. Relocate existing furniture, book cases, file draws, curtains, and other office equipment
15. New Doors, frames, hardware, and locks,
16. Ductless AC and heat pump,
17. Ceiling fans,
18. Other requirements as described in the statement of work or as shown on the drawings.
19. Fully adhered carpet transition strip.
1.04 SUBMITTALS
A. Five (5) working days prior to start of work, the contractor shall submit the following:
1. Samples and manufacturer’s data per the contact documents.
1.05 PRODUCT DELIVERY, STORAGE AND HANDLING
A. Deliver materials to the job site in the manufacturer’s original, unopened containers or wrappings with the manufacturer’s name, brand name and installation instructions intact and legible. Deliver in sufficient quantity to permit work to continue without interruption.
B. Comply with the manufacturer’s written instructions for proper material storage.
C. Any materials which are found to be damaged shall be removed and replaced at the contractor’s expense.
1.06 WORK SEQUENCE
A. Care shall be exercised to provide protection for of the building and equipment within the building. Do not disrupt activities in occupied spaces.
1.07 USE OF THE PREMISES
A. Before beginning work, the contractor shall secure approval from the building owner’s representative for the following:
1. Areas permitted for personnel parking.
2. Access to the site.
3. Areas permitted for storage of materials and debris.
4. Security: Obey the owner’s requirements for personnel identification, inspection and other security measures.
PAGE 9 OF 19 WC-133F-15-RQ-0499/A0001
1.08 EXISTING CONDITIONS
A. If discrepancies are discovered between the existing conditions and those noted on the drawings, immediately notify the COR.
i. Upon receipt of Bidding Documents verify documents are complete. Notify COR if documents are incomplete. Immediately notify COR upon finding discrepancies or omissions in Bidding Documents.
1.09 FACILITIES AND CONTROLS
A. The contractor shall remove all debris from the job site in a timely and legally acceptable manner so as to not detract from the aesthetics or the functions of the building.
B. Due to the office environment and continuation of mission requirements the contractor shall include in his/her bid price a stoppage of work during the course of the project. This should include interruption or stoppage of work for three (3) hours per week.
1.10 JOB SITE PROTECTION
A. The contractor shall adequately protect building and site from damage while performing the required work.
Provide canvas, boards and sheet metal (properly secured) as necessary for protection and remove protection material at completion. The contractor shall repair or be responsible for costs to repair all property damaged during the roofing application.
B. During the contractor’s performance of the work, the building owner will continue to occupy the existing building. The contractor shall take precautions to prevent the spread of dust and debris. The contractor shall provide labor and materials to construct, maintain and remove necessary temporary enclosures to prevent dust or debris in the construction area(s) from entering the remainder of the building.
C. Protect against fire and flame spread. Maintain proper and adequate fire extinguishers within fifty (50) feet of any open flames. If any heated or flamed application is utilized a 15 lb or larger fire extinguisher shall be within 25’ reach or closer at all times.
1.11 SAFETY
A. The contractor shall be responsible for all means and methods as they relate to safety and shall comply with all applicable OSHA, NEC, NFPA, EPA 40 CFR Part 745, local, state and federal requirements. Safety shall be the responsibility of the general contractor. All related personnel shall be instructed daily to be mindful of the full time requirement to maintain a safe environment for the facility’s occupants including staff, visitors, customers and the occurrence of the general public on or near the site.
B. The contractor shall keep the project site in a neat an orderly condition at all times.
C. Five days prior to start of work contractor shall submit a safety plan. To include but not limited, open flames, debris, cleanup, and emergency procedures.
D. It is the contractor’s responsibility to ensure all employees; sub-contractors, venders, and other company representative adhere to all safety rules, regulations, policies and practices.
1.12 WORKMANSHIP
A. All work shall be of highest quality and in strict accordance with the manufacturer’s published specifications and to the building owner’s satisfaction.
B. There shall be a site superintendent on the job site at all times while work is in progress. Site superintendent shall be an employee of the general contractor. Worker and sub contractor shall not permitted on the site without the presence of the designated site superintendent.
1.13 QUALITY ASSURANCE
PAGE 10 OF 19 WC-133F-15-RQ-0499/A0001
A. Unless otherwise noted in the contract documents, contractor shall comply with the manufacturer’s current specifications and details.
B. Provide adequate number of experienced workmen regularly engaged in this type of work who are skilled in the application techniques of the materials specified. Provide at least one thoroughly trained and experienced superintendent on the job at all times when work is in progress. Once the site superintendant has been identify he/she shall remain on the project until completion. Any changes to the site superintendant shall require written notification at least two working days in advance of proposed change.
C. There shall be no deviations made from this specification or the approved shop drawings without the prior written approval of the Contracting Officer Any deviation from the manufacturer’s installation procedures must be supported by a written certification on the manufacturer’s letterhead and presented for the specifier’s consideration.
D. All substitutions requests for products, equipment, materials and methods described within the contract documents shall be submitted to the COR. Substitutions request are not permitted prior to the Notice to Proceed. Substitute products will be considered when the request is submitted in writing to the COR and coordinated through the Contracting Officer. The Government will have seven (7) working days to approve /disapprove substitution request. Substitution request shall not result in schedule extensions. Substitution request shall include:
i. Two complete copies of the manufacturers technical data and cut sheets, with sufficient information and product data to allow the COR to make a timely decision,
ii. The reason for the substitution,
iii. A comparison of delivery time,
iv. Samples,
v. Substitutions shall meet or exceed all requirements of specified materials, products, equipment and methods described within the contract documents,
vi. Contractor shall not be entitled to extra compensation for substitution request whether approved or disapproved,
vii. If the cost of the substitution is less than the specified products, materials, equipment or methods the difference in cost shall be credit to the government.
viii. Certified cost of specified and proposed products, equipment, materials and methods.
1.14 JOB CONDITIONS, CAUTIONS AND WARNINGS
A. Material Safety Data Sheets (MSDS) must be on location at all times during the transportation, storage and application of materials. A separate set shall be given to the COTR five (5) days prior to starting of the work.
1.15 WARRANTY
A. Provide manufacturer’s warranty covering both labor and material with no dollar limitation.
PART 3 EXECUTION
3.01 GENERAL
A. Comply with the manufacturer’s published instructions for the installation of specified products, and installation requirements per the contract documents.
PAGE 11 OF 19 WC-133F-15-RQ-0499/A0001
3.09 CLEAN UP
A. Perform daily clean-up to collect all wrappings, empty containers, paper, and other debris from the project site. Upon completion, all debris must be disposed of in a legally acceptable manner.
***END OF SECTION***
SECTION 09 20
GYPSUM BOARD/STEEL STUD/SOUND PROOFING/CEILING/BASE
COVE/ASSEMBLIES/DOORS/CARPET/LIGHTS
PART 1 GENERAL
1.1 SUMMARY
A. Section includes gypsum board, framing walls systems, insulation, door systems, base cove and drop ceiling.
1.2 SUBMITTALS
A. Product Data: Submit data on gypsum board, walls systems, insulation and drop ceiling.
1.3 QUALITY ASSURANCE
1. Perform Work in accordance with ASTM C754 - Standard Specification for Installation of Steel
Framing Members to Receive Screw-Attached Gypsum Board.
2. C645 - Standard Specification for Nonstructural Steel Framing Members.
3. ASTM E119 - Standard Test Methods for Fire Tests of Building Construction and Materials
PART 2 PRODUCTS
2.1 GYPSUM BOARD, WALL ASSEBLIES, CEILING ASSEMBLIES, SOUND PROOFING, LIGHTING, DOORS.
A. Manufacturers Fire Rated (FR) Gyp Board:
1. BPB Americas Inc.,
2. G-P Gypsum Corp.,
3. National Gypsum Co.,
4. United States Gypsum Co...
B. Manufacturers Sound Proofing Insulation:
1. Quiet Proof,
2. Approved equal
C. Manufacturers Ceiling Tile:
1. Armstrong Model 1774, Dune Angled Tegular HumiGaurd Plus, Dune Tegular with Silhouette®
XL 9/16" suspension system 1/4" Reveal (Conference Room Only)
2. Armstrong DP 935.
D. Lights:
1. Recessed Downlighting, Prescolite, 8LFLED5G435KWTUN SPSC#39111515
E. Doors 1 Office doors are to measure 36” W x 80” H:
a. USA Fire Door,
b. Pioneer,
c. Doorsmart USA,
d. Ceco Door.
PAGE 12 OF 19 WC-133F-15-RQ-0499/A0001
F. Sound Proof Barrier
1. Acoustimac or approved equal.
G. Dimmer Switch
1. Lutron Lighting Dimmer, slide, 3 way, with on/off rocker, SF-103P-WH
H. Ceiling Fan
1. 36" Modern Fan Altus Hugger Brushed Aluminum Ceiling Fan, Style # Y0911
2.2 COMPONENTS
A. Gypsum Board Materials: ASTM C1396/C1396M
1. Fire Rated 5/8” Gypsum Board, maximum available length in place.
B. Metal Stud, Framing and Furring system:
1. ASTM C754 20 ga.
C. Sound Proof Mass loaded Vinyl Barrier:
1. 1/8 “ thick
2. STC values between 10-45.
D. Sound Proofing Insulation:
1. Thickness will vary depending on metal framing
2. Requires supports per manufactures recommendation.
3. Dense packed cotton fibers.
E. Metal Doors and Frames: All office doors are to measure 36” W x 80” H
1. Interior Doors (1.5 hr Fire Rated): 1-3/4 inch thick
2. Level II – Model 2, narrow lite (14” x 20”), Glazing to meet or exceed all fire rated requirements. Glazing shall be frosted.
3. Face: nominal 18 gage, seamless.
4. End Closure: Channel, 0.04 inches thick,
5. Sound Rated Door: STC of 26, in accordance with ASTM E413.
6. Primer: ANSI A250.10 rust inhibitive type.
7. Shop Finish: Baked enamel or Thermosetting epoxy, color as selected by COTR.
8. Adjust door for smooth and balanced door movement.
9. Hardware and frame per manufacturer recommendation and meet or exceed contract document requirements.
10. Lock set cores for each door shall be Government Furnished Equipment.
11. Meet or exceed requirements per References;
a. ANSI A250.8 - Recommended Specifications for Standard Steel Doors and Frames,
b. ASTM E84 - Standard Test Method for Surface Burning Characteristics of Building Materials,
c. ASTM E413 - Classification for Rating Sound Insulation,
d. NFPA 80 - Standard for Fire Doors, Fire Windows,
e. Standard Door Institute 108 - Recommended Selection and Usage Guide for Standard Steel Doors,
f. UL10B- Fire test of Door Assemblies.
F. Carpet: Contractor shall install commercial grade 2’ X 2’ tile carpet.
1. Carpet tiles shall be tufted loop pile, 100% nylon Type 6; Meet or exceed the following; Density :
minimum of 6000 ounce per cubic yard per ASTM 418; Static resistance per NFPA 99; Pile Height: 0.187 inch average maximum; Pile thickness: 0.150 inch average minimum; Yarn weight: 26 ounce per square;
Anti-microbial; Backing Integrity: No De-lamentation for 10 years;
2. Carpet shall be high grade indoor/outdoor commercial grade 28oz. solution dyed nylon carpet with stain guard.
3. Carpet tiles shall have a ten year warranty for wear, tuft bind, edge ravel, zippering
4. Carpet tiles shall have a ten year warranty for wear, tuft bind, edge ravel, zippering, delimitation, dimensional stability and soil and stain resistance,
5. Carpet shall meet or exceed Standard 104, ANSI A1117.1, NFPA 258, and ASTM E662.
PAGE 13 OF 19 WC-133F-15-RQ-0499/A0001
G. Lights
1. Recessed
a. 3500K, 1175lm, 14.4W,
b. Dimmable,
c. Energy Star rated,
d. Housing material – Aluminum.
H. Ceiling Grid:
1. Fire Rated Grid: ASTM C635 components die cut and interlocking.
2. Accessories: Stabilizer bars, clips, splices, edge moldings, and other required accessories for suspended grid system.
3. Grid Materials: Commercial quality cold rolled steel with galvanized coating.
4. Exposed grid surface width: 15/16 inch with reveal and ¼” for conference room.
5. Grid Finish: color to selected by COTR.
6. Support Channels and Hangers: Galvanized steel, size and type to suit application and ceiling system flatness requirements specified.
7. Wire Support Hangers 4’ O.C.
I. Ceiling Fan
1. Brushed aluminum hugger motor finish.
2. Three brushed aluminum finish blade.
3. 36" blade span.
4. 12 degree blade pitch.
5. 153x18mm motor size.
6. Includes 4-speed wall control operation.
7. Fan is 12" high from ceiling to switch housing.
8. Canopy is 6" wide.
2.3 Quality Control
A. Gypsum Board Accessories: ASTM C1047; metal corner beads, edge trim, and expansion joints.
B. Joint Materials: ASTM C475/C475M, reinforcing tape, joint compound, and water.
C. Adhesive: ASTM C557.
D. Gypsum Board Screws: ASTM C954, ASTM C1002; length to suit application.
E. ANSI A250.8 - Recommended Specifications for Standard Steel Doors and Frames
F. ASTM E413 - Classification for Rating Sound Insulation
G. NFPA 80 - Standard for Fire Doors, Fire Windows
H. Standard Door Institute 108 - Recommended Selection and Usage Guide for Standard Steel Doors
I. UL 10B - Fire Tests of Door Assemblies
J. Carpet, minimum of 6000 ounce per cubic yard per ASTM 418
K. Static resistance carpet NFPA 99
L. Carpet and Rug Installation Standard 104
M. Carpet and Rug Installation ANSI A1117.1
N. Carpet and Rug Installation NFPA 258
O. Carpet and Rug Installation ASTM E662, PAGE 14 OF 19 WC-133F-15-RQ-0499/A0001
P. Sound Rated Door ASTM E413
Q. Primer Rust Inhibitive ANSI A250.10
PART 3 EXECUTION
3.1 EXAMINATION
A. Verify site conditions are ready to receive work.
3.2 INSTALLATION
A. Gypsum Board:
1. Install 5/8” fire rated gypsum board.
2. Fasten gypsum board to framing with screws 8 inch O.C. type S gyp board screw.
3. Place control joints consistent with lines of building spaces.
4. Place corner beads at external corners. Use longest practical length. Place edge trim where gypsum board abuts dissimilar materials.
B. Joint Treatment:
1. Tape, fill, and sand exposed joints, edges, and corners to produce smooth surface ready to receive finishes.
C. Steel Studs and Runners: ASTM C754.
1. Non-structural Studs: Cold-formed galvanized steel C-studs, Dietrich ProSTUD™(or approved equal) drywall studs, 20 gage.
a. Splicing of vertical studs is prohibited.
b. Steel stud spacing shall be 24” on center.
c. Add channels/runners to top and bottom of framing.
d. Do not drill into 9” x 9” vinyl floor tile, contains ACM. Secure to floor with construction adhesive when runners are on top of 9” x 9” floor tiles.
E. Sound Proofing Insulation:
1. Place vapor retarder/barrier outside wall only. Tape seal tears or cuts in vapor retarder
2. Secure to framing per manufacturer recommendation,
3. Add sound proofing supports per manufactures recommendations.
4. Trim neatly to fit spaces. Fill miscellaneous gaps and voids.
F. Base Cove:
1. Install 1" X 4" wood cove molding around wall base; apply to all rooms and hallways.
2. New wood surfaces and moldings to be prepared to a smooth even finish, paint per painting specifications.
G. Doors and Frames:
1. Install doors and frames according to the manufactures recommendation and section 2.3 of this section whichever is greater.
H. Carpet:
1.Install carpet according to the manufactures recommendation and section 2.3 of this section whichever is greater. Include carpet transition strip, fully adhered to floor.
2. Supply one (1) case or 20 spare (whichever is greater) carpet tiles to the COR.
3. See Section 1.
I. Ceiling Fans
a. Add support, bracing and other support system to ensure fan operates without vibration, wobble, or uneven rotation.
b. Install and support per manufacture recommendations.
J. Sound Proofing Mass Loaded Vinyl:
PAGE 15 OF 19 WC-133F-15-RQ-0499/A0001
a. Per manufacture recommendations and section 2.3 of this section whichever is greater.
*** END OF SECTION ***
SECTION 09 90 00
PAINTING AND COATING
PART 1 GENERAL
1. 1 SUMMARY
A. Section includes surface preparation and field application of paints, stains, varnishes, and other coatings.
1.2 SUBMITTALS
A.Product Data: Submit data on finishing products
B.Samples: Submit paper chip samples, 1” x 1” in size illustrating range of colors and textures.
C.Submit MSDS sheets for all paints, stains, primers and other paint products being utilized.
1.3 CLOSEOUT SUBMITTALS
A.Operation and Maintenance Data: Submit maintenance and cleaning instructions.
1.4 QUALITY ASSURANCE
A.Follow all federal, state and local standards.
B.Apply paint and primer per manufacturer’s recommendation.
1.5 ENVIRONMENTAL REQUIREMENTS
A.Store and apply materials in environmental conditions required by manufacturer's instructions.
B.Ventilate if required or directed by the COR.
PART 2 PRODUCTS
2.1 PAINTS AND PRIMERS
A. Manufacturers: PPG Architectural Finishes Model: Pure Performance
B. Primers must be from same manufacture and meet manufactures recommendation for the product being applied.
C. Acceptable manufacturers meeting or exceeding the PPG Pure Performance include:
i. Coronado Paints.
ii. Devoe Paint Co.
iii. Duron Inc.
iv. ICI Paint Store
2.2 COMPONENTS
Paint shall have the following characteristics:
Mildew resistant on paint film
PAGE 16 OF 19 WC-133F-15-RQ-0499/A0001
Zero VOC Minimal odor Excellent wash ability
Accessory Materials: Linseed oil, shellac, turpentine, paint thinners and other materials required to achieve finishes specified.
3 EXECUTION
3.1 EXAMINATION
A. Verify substrate conditions are ready to receive work. Notify COR 2 working days in advance of application for walk through and inspection.
3.2 PREPARATION
A. Correct minor defects and clean surfaces affecting work of this section.
B. Remove electrical plates, hardware, light fixture trim, escutcheons, and fittings prior to preparing surfaces or applying finishes.
C. Gypsum Board Surfaces: Fill minor defects with filler compound. Spot prime defects after repair.
D. Do not allow over spray or odors to enter other parts of the facility. Take all measure to contain over spray and odors.
E. Supply sufficient fresh air in the work area.
3.3 APPLICATION
A. Sand surfaces lightly between coats to achieve required finish.
B. Cleaning: As work proceeds, promptly remove finishes where spilled, splashed, or spattered.
3.5 SCHEDULE - INTERIOR SURFACES
A. Plaster, Gypsum Board, Base Cove, and Wood Surfaces:
One coat of primer sealer.
Two coats of acrylic paint.
3.6 SCHEDULE - COLORS
COR will determine color scheme.
Within 7 working days of receipt of color samples from the contractor, the COR will deliver a schedule of colors for each room.
*** END OF SECTION ***
SECTION 15720 - Ductless Mini Split Air Conditioner and Heat Pump
PART 1 GENERAL
3.3 SUMMARY
A. Section includes Ductless Air Conditioner and Heat Pump .
B. Manufacture and Install in accordance with;
PAGE 17 OF 19 WC-133F-15-RQ-0499/A0001
1. American Bearing Manufacturers Association:
a. ABMA 9 - Load Ratings and Fatigue Life for Ball Bearings.
b. ABMA 11 - Load Ratings and Fatigue Life for Roller Bearings.
2. Air Movement and Control Association International, Inc.:
a. AMCA 99 - Standards Handbook.
b. AMCA 210 - Laboratory Methods of Testing Fans for Aerodynamic Performance Rating.
c. AMCA 300 - Reverberant Room Method for Sound Testing of Fans.
d. AMCA 301 - Methods for Calculating Fan Sound Ratings from Laboratory Test Data.
3. Air-Conditioning and Refrigeration Institute:
a. ARI 410 - Forced-Circulation Air-Cooling and Air-Heating Coils.
4. National Electrical Manufacturers Association:
a. NEMA MG 1 - Motors and Generators.
5. Underwriters Laboratories Inc.:
a. UL 900 - Air Filter Units.
b. UL - Fire Resistance Directory.
3.4 SUBMITTALS
A. Shop Drawings: Indicate assembly, unit dimensions, weight loading, required clearances, construction details, field connection details, and electrical characteristics and connection requirements.
B. Product Data, Submit the following:
1. Published Literature: Indicate capacities, ratings, gages and finishes of materials, and electrical characteristics and connection requirements.
2. Filters: Data for filter media, filter performance data, filter assembly, and filter frames.
3. Fans: Performance and fan curves with specified operating point plotted, power, RPM.
4. Sound Power Level Data: Fan outlet and casing radiation at rated capacity.
5. Dampers: Include leakage, pressure drop, and sample calibration curves. Indicate materials, construction, dimensions, and installation details.
6. Electrical Requirements: Power supply wiring including wiring diagrams for interlock and control wiring.
Indicate factory installed and field installed wiring.
C. Manufacturer's Installation Instructions.
D. Mounting plan on plan for compressor.
3.5 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: Submit instructions for lubrication, filter replacement, motor and drive replacement, spare parts lists, and wiring diagrams.
3.6 QUALITY ASSURANCE
A. Perform Work in accordance with all federal, State, standards, all listed reference and manufacturers recommendation.
B. Maintain one copy of each document on site.
3.7 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this section with minimum five documented experience.
B. Installer: Company specializing in performing Work of this section with minimum five years documented experience approved by manufacturer.
PAGE 18 OF 19 WC-133F-15-RQ-0499/A0001
3.8 DELIVERY, STORAGE, AND HANDLING
A. Accept units and components on site in factory protective containers, with factory shipping skids and lifting lugs.
Inspect for damage.
B. Protect units from weather and construction traffic by storing in dry, roofed location.
3.9 WARRANTY
A. Furnish five year manufacturer warranty for air handling units, including all parts and labor.
PART 4 PRODUCTS
4.1 AIR HANDLING UNITS
A. Manufacturers:
1. Trane, Lennox, American Standard (24 Ton Ductless Air Conditioner and heat pump) 220/V/60 Hz.
a. 3 dimensional air flow with turbo operation and auto restart,
b. Auto and 3-speed fan, on/off 24 hour timer and sleep mode,
c. Highly efficient permanent washable filters,
d. Wall mounted, led display, exterior pre charged condenser with anti corrosion coated coils,
e. Tubing insulation, drain hose, defrost wire, pipe wraps, hardware.
PART 5 EXECUTION
5.1 INSTALLATION
A. Install in accordance with manufacturer recommendations, and as specified in contract documents.
B. Do not penetrate roof or EDPM. Secure condenser to withstand hurricane category 5 wind forces.
C. Mount all tubing drain hoses, power on outside of bulling , connect to wall every 3 feet.
D. Insulate tubing and other condenser parts as required by manufacture, standards, state and federal codes.
E. Furnish services of factory trained representative to leak test, refrigerant pressure test, evacuate, dehydrate, charge, start-up, calibrate controls, and instruct Owner on operation and maintenance.
F. Demonstrate unit operation and maintenance.
***END OF SECTION ***
PAGE 19 OF 19 WC-133F-15-RQ-0499/A0001
| Descript: See Attached |
| Descript1: |
| AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT: |
| IDCode: |
| pdfpage1: 1 |
| Pages: 19 |
| DocNo: A0001 |
| EffDate: JUN 11, 2015 |
| ReqNo: NFFM7020-15-02339 |
| ProjNo: |
| IssuedByCode: AJ830023 |
| IssuedBy: NOAA/AGO/EAD |
601 E 12TH STREET
ROOM 1734
KANSAS CITY MO 64106
| AdminByCode: |
| AdminBy: See Block 6 |
| ContractorCode: |
| FacCode: |
| SolChg: Yes |
| AwdChg: Off |
| SolNo: WC-133F-15-RQ-0499 |
| SolDate: MAY 22, 2015 |
| AwdNo: |
| AwdDate: |
| NoCopies: 1 |
| Amended: Yes |
| OffrExt: Yes |
| OffrNoEx: Off |
| ApprData: See Schedule |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).: |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| SignName: |
| SignTitl: |
| ContDate: |
| ContrOfficerInfo: |
| CODate: |
| Contractor Info: |
| ContractorPOC: |
| Contractor: |
| ModAmount: |
| Header: |
| 15B. CONTRACTOR/OFFEROR: |
| Footer1: |
| signature: |
File details come from the government source that posted it. Updated .