About this file

Wayland Union Schools Transportation Building Roof Improvements

This Request for Proposals (RFP) is issued by Wayland Union Schools for roof improvements to the Transportation Building located at 851 Wildcat Drive, Wayland, Michigan 49348. The district seeks sealed bids for roof replacement work on Sections C and D, encompassing approximately 6,770 square feet total (Section C: 1,450 SF; Section D: 5,320 SF). Bidders must submit separate, complete lump-sum prices for two mutually exclusive options: (1) an approved roof recovery and (2) full removal down to the deck and replacement. Both options require installation of a new 60-mil reinforced EPDM roof system with a 20-year manufacturer warranty. The RFP was issued November 20, 2026, with a mandatory pre-bid walkthrough scheduled for December 1, 2026, at 1:00 p.m. Eastern Time at the Transportation Building. Written clarification questions are due December 2, 2026, by 2:00 p.m. Eastern. Sealed proposals must be hand-delivered to the Administration Building, 893 E. Superior Street, Wayland, Michigan 49348, by December 4, 2026, at 10:00 a.m. Eastern Time, with public opening at the same date and time. The Board anticipates consideration on December 14, 2026, subject to board action and funding. Installation and all work completion, including final inspection, punch-list corrections, and document turnover, must be completed by June 30, 2027.

Each bidder must include a lump-sum price for Section C, Section D, and combined totals for each option, along with separate unit prices for wet-insulation replacement and concealed deck repair adjustments. Bid security of at least 5 percent of the larger of the two option prices is required. The existing roof, inspected April 10, 2025, is rated Grade F with EPDM membrane failure, delamination affecting approximately 51 squares, failing wall terminations (120 linear feet), seam failure, punctures, and open corner flashings. Contractors must verify site conditions at the mandatory walkthrough and must be manufacturer-authorized installers. The minimum roof insulation requirement is 5 inches throughout work areas. All bids must include notarized Familial Affidavits and Iran Linked Business Affidavits using district-supplied forms, along with signed Addenda Acknowledgments. Proposals must remain firm for 60 calendar days after opening. For contracts exceeding $50,000, performance and payment bonds at 100 percent of contract amount are required. The district reserves the right to reject any or all bids. No work is authorized until a written contract and notice to proceed are issued.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Wayland Union Schools | Transportation Building Roof 1

Wayland Union Schools

893 E. Superior Street

Wayland, MI 49348

REQUEST FOR PROPOSALS

For

Transportation Building Roof Improvements

Sections C and D

Issuance of this RFP November 20, 2026

Pre-Bid Walkthrough - Mandatory December 1, 2026, at 1:00 p.m. Eastern

Written Clarifications Deadline December 2, 2026, at 2:00 p.m. Eastern

DUE DATE FOR PROPOSALS December 4, 2026, at 10:00 a.m. Eastern

Public Bid Opening December 4, 2026, at 10:00 a.m. Eastern

Pre-Bid: Transportation Building, 851 Wildcat Dr., Wayland, MI 49348. Attendance and sign-in are mandatory.

Sealed bid delivery and opening: Administration Building, 893 E. Superior St., Wayland, MI 49348. Hand-deliver sealed bids by 10:00 a.m. on December 4, 2026.

Questions: Bill McSween, mcsweenw@waylandunion.org, 616-862-3829.

Bid package delivery

Staying for the opening: Park behind the Administration Building and carry your sealed bid inside before 10 a.m.

Drop-off only: Park in front and leave your sealed bid at the front desk before 10 a.m.

Wayland Union Schools | Transportation Building Roof 2

1 OVERVIEW

1.1 PURPOSE

Wayland Union Schools requests sealed bids for roof improvements to Sections C and D, approximately 6,770 square feet total. Submit separate, complete lump-sum prices for (1) an approved roof recovery and (2) full removal down to the deck and replacement. Both options require a new 60-mil reinforced EPDM roof system and the specified 20-year manufacturer warranty.

Roof section Approximate area Scope

C 1,450 SF Include

D 5,320 SF Include

Total 6,770 SF Bid both options

A and B Excluded Protect roofs and warranties; owner believes completed in 2024.

1.2 SELECTION TIMELINE

Event Date and time

Issuance of this RFP November 20, 2026

Mandatory pre-bid walkthrough Tuesday, December 1, 2026, at 1:00 p.m. Eastern

Written clarification questions due December 2, 2026, at 2:00 p.m. Eastern

Sealed proposals due / public opening Friday, December 4, 2026, at 10:00 a.m. Eastern

Anticipated board consideration December 14, 2026, subject to board action and funding

Installation and completion Spring 2027; all work, final inspection, punch-list corrections and document turnover completed by June 30, 2027, before July 1.

The district may adjust the timeline by written addendum. No work is authorized until a written contract and notice to proceed are issued. Coordinate the start date and transportation operations with Bill McSween.

1.3 ATTACHMENTS

A - Proposal Pricing Form B - Familial Affidavit (district-supplied form) C - Iran Linked Business Affidavit (district-supplied form) D - Roof Plan E - Addenda Acknowledgment F - Bus Garage Roof Inspection Report (company headings and inspector identification omitted)

Wayland Union Schools | Transportation Building Roof 3

2 SUBMISSION OF PROPOSALS

2.1 DEADLINE AND DELIVERY

Signed original hard-copy proposals must be delivered in a sealed opaque envelope and received by Friday, December 4, 2026, at 10:00 a.m. Eastern Time at the Administration Building, 893 E. Superior St., Wayland, MI 49348. Mark the envelope as follows:

SEALED PROPOSAL ENCLOSED

Transportation Building Roof Improvements - Sections C and D Wayland Union Schools Attention Bill McSween 893 E. Superior St.

Wayland, MI 49348 Include contractor name, address, email and telephone on the envelope.

No oral, fax or emailed proposals will be accepted. Contractors are responsible for timely delivery. Late bids will not be opened, considered or accepted. All timely bids will be publicly opened and read aloud at 10:00 a.m. on December 4, 2026, at the same Administration Building address. Any interested parties may attend;

no immediate award is promised.

2.2 MANDATORY PRE-BID WALKTHROUGH

Attendance at the December 1, 2026, 1:00 p.m. Eastern Time pre-bid walkthrough is mandatory. Each bidder must have a representative attend and sign the district attendance roster. Bids from firms not represented at the mandatory walkthrough will not be accepted. Inspect Sections C and D, verify roof boundaries and dimensions, and review access, drainage, penetrations, rooftop equipment, wall transitions and interfaces with excluded Sections A and B. Obtain district permission before core cuts or other destructive investigations and restore all test locations watertight the same day.

The walkthrough will help assess recovery suitability versus full replacement. Oral discussions do not change the bid requirements. Any changes, findings that affect pricing, approved substitutions or option requirements will be issued by written addendum to all bidders before the deadline. Continue to price both options unless an addendum states otherwise.

2.3 CLARIFICATIONS AND ADDENDA

Direct written questions by email to Bill McSween, mcsweenw@waylandunion.org, telephone 616-862-3829.

Questions must be received by December 2, 2026, at 2:00 p.m. Eastern Time. [DISTRICT TO SET ADDENDA ACCESS LOCATION] Written addenda govern changes; oral statements do not amend the RFP. All bidders must receive the same pricing information and acknowledge addenda using Attachment E.

Allow sufficient time after clarification of material scope changes; the district may extend the deadline by addendum.

2.4 BID SECURITY AND RESERVATION OF RIGHTS

Each bid must include bid security of at least 5% of the larger of the two total option prices. The options are mutually exclusive. The Board reserves the right to reject any or all bids. Proposals must remain firm for 60 calendar days after opening, subject to district confirmation before issuance. No waiver may override a mandatory legal requirement.

Wayland Union Schools | Transportation Building Roof 4

3 PROPOSAL REQUIREMENTS AND FORMAT

Submit the completed and signed Attachment A and all information listed below. Identify exceptions, substitutions or special conditions in a separate attachment with an explanation. Exceptions are not binding unless expressly accepted in writing by the district. Do not assume approval of a materially different roof assembly or warranty.

- Separate complete lump-sum prices for recovery and full replacement, including Section C, Section D and combined totals, and all stated unit prices.

- Proposed manufacturer, reinforced EPDM system and attachment; insulation type, existing/new thicknesses and R-value; preliminary drainage approach.

- Manufacturer installer authorization, sample warranty and written preliminary manufacturer confirmation of 20-year warranty eligibility for each option.

- Three comparable EPDM roof project references, including recovery experience if bidding recovery; owner contact, completion date, approximate area, system and warranty.

- Proposed superintendent, subcontractors and thermography provider, including qualifications and survey method; licensed trades for equipment coordination.

- Anticipated schedule, product information, exceptions/substitutions, bid security and evidence of ability to provide required insurance and bonds.

- Completed, signed and notarized Familial Affidavit (Attachment B) and Iran Linked Business Affidavit (Attachment C).

- Signed Addenda Acknowledgment (Attachment E).

3.1 REQUIRED AFFIDAVITS

Every bid must include the sworn and notarized familial disclosure covering any relationship between the bidder's owner or employees and Board members or the Superintendent. The supplied district form also addresses the Chief Business Official. The district will not accept a bid without the required disclosure. If a relationship exists, disclose it on a signed and notarized attachment rather than signing an inaccurate no-relationship statement.

Every bid must include the supplied Iran Linked Business Affidavit, signed and notarized. Use the district-supplied forms attached as B and C; their wording is reproduced as supplied.

3.2 EVALUATION

The district will evaluate responsiveness, total evaluated cost for each option, technical suitability, manufacturer warranty eligibility, experience, references, and schedule under its adopted policy. Anticipated board consideration is December 14, 2026; award is subject to board action and funding. No work is authorized until a written contract and notice to proceed are issued.

The contractor bears all proposal preparation costs. Each proposal must be independently prepared without collusion. Use of subcontractors must be disclosed and coordinated with the district; all work remains the prime contractor's responsibility.

Wayland Union Schools | Transportation Building Roof 5

4 CONTRACTOR RESPONSIBILITIES

Maintain transportation operations and emergency access. Perform installation in spring 2027 and complete all work, final inspection, punch-list corrections and closeout by June 30, 2027, before July 1. Coordinate the start date, work hours, deliveries, cranes, staging, odors and bus movements with Bill McSween and the district. Protect buses, staff, contents, paving, landscaping and existing roofs. Barricade work and fall-exposure areas. Provide daily temporary weather protection and secure all materials against wind. Never leave opened roof areas unprotected overnight. Contractor is responsible for damage caused by its work.

Remove debris daily; prevent materials from entering drains. Provide proper disposal, final site cleanup and magnetic sweep where appropriate. Stop and notify the district if suspect hazardous materials or unsafe structural conditions are encountered; do not disturb or conceal those conditions. Obtain written direction before extra work.

4.1 PERMITS AND COORDINATION

Obtain required permits and use licensed trades as applicable. Coordinate safe disconnect, lifting, curb adjustment, reconnection and operational verification of rooftop equipment. Include associated labor and costs. Verify site conditions at the mandatory walkthrough and submit discrepancies in writing before bidding.

Provide product safety information and follow applicable safety, building, energy and environmental requirements. Protect the existing A and B roof areas and their warranties, with compatible watertight tie-ins at the limits of C and D. Contractor is responsible for damage caused by its work.

4.2 SUBMITTALS AND APPROVALS

Before installation, provide product data, assembly details, insulation/R-value schedule, drainage plan, attachment and wind-uplift design, test results, shop drawings, manufacturer eligibility approval, safety/staging plan and schedule. Provide permits and required design-professional approvals. Follow approved details and current manufacturer instructions.

4.3 CONTRACT PRICING

Provide independent complete prices for recovery and full replacement. Include labor, materials, equipment, survey work, ordinary substrate preparation, insulation upgrades, cover board, tapering, drainage work, flashing, equipment coordination, disposal, permits, warranty fees, bonds where required, and all applicable costs. Do not add the option totals together.

Recovery base pricing assumes retained insulation is dry and serviceable after verification. Unknown wet-insulation replacement is a separately measured adjustment under the unit prices on the bid form. Do not include undisclosed wet-area allowances. Full-replacement pricing includes removal and replacement of all existing roofing and insulation within C and D, whether wet or dry. Concealed deck repairs are separately measured under the stated unit prices for either option.

For comparison, the district must publish common evaluation quantities for wet-insulation and concealed deck repair unit prices by addendum before bid close. These quantities are estimates for bid comparison only;

payment is based on approved actual measured work. Bidders must not select their own evaluation quantities.

Wayland Union Schools | Transportation Building Roof 6

5 SPECIFICATIONS

5.1 EXISTING CONDITIONS AND BID LIMITS

Reference: Bus Garage Inspection Report; inspection April 10, 2025. The report copy with company headings and inspector identification omitted is attached as Attachment F.

Existing roof material: The report summary identifies EPDM and failure of the adhesive between the EPDM and the top insulation layer. Exact assembly, membrane thickness and attachment require field verification.

Reported condition: Membrane, flashings and sheet metal are each graded F. Estimated replacement year:

2026.

Reported damage: Wind-related roof delamination/uplift; report describes approximately 51 roofing squares affected. Failing or improperly installed wall termination, approximately 120 linear feet; seam failure; a puncture/rip/tear; and three open corner-flashing locations.

Leaks and moisture: The report documents watertightness defects but does not provide a verified interior leak log or a mapped wet-insulation quantity. Do not treat all damaged areas as confirmed wet insulation.

Existing insulation: The report does not establish insulation type, thickness, layer count, R-value, or moisture extent. Verify by approved core cuts and moisture investigation.

Area discrepancy: Report "Section 3" is listed as 8,984 square feet. This solicitation covers only owner-designated C (1,450 SF) and D (5,320 SF), total 6,770 SF. Report labels and quantities do not establish bid boundaries.

Roof plan and exclusions

Attachment D is the owner-provided roof plan. The "2000" labels indicate the owner-reported last roof work year, not square footage. A and B are marked as 2024 and are excluded from replacement; the district will confirm their status. Include compatible, watertight tie-ins at the C/D work limits while preserving A/B roofs and any existing warranties.

At the walkthrough, reconcile the report area with the plan, confirm that identified defects fall within C/D, identify any undocumented defects, and document the existing deck and assembly. Resolve material scope differences through a district-issued addendum before bids close. The report is historical condition information, not a current moisture survey or an engineered repair design.

Wayland Union Schools | Transportation Building Roof 7

5 SPECIFICATIONS CONTINUED

5.2 ROOF SYSTEM AND BID OPTIONS

Requirements common to both options

Roof system: New 60-mil reinforced EPDM membrane, ASTM D4637, with compatible manufacturer-approved insulation, cover board, adhesives/fasteners, accessories, flashing and edge components. Use a manufacturer-authorized installer. Provide a complete listed/tested assembly appropriate for the verified deck, fire classification and project-specific wind uplift requirements, including perimeter and corner zones.

Insulation: Provide a minimum total of 5 inches of roof insulation throughout the work areas, or greater thickness/R-value as required by applicable code, the approved design or the manufacturer. Do not count cover board as insulation. Use dry, compatible retained insulation only in the recovery option; document its thickness and suitability. Use new roof-grade insulation meeting the applicable material standard, such as ASTM C1289 for polyisocyanurate. Stagger joints in multiple layers; provide approved attachment and cover board as required by the assembly.

Warranty: Include a minimum 20-year manufacturer roof-system warranty covering materials and labor for covered leaks, including membrane, flashing and eligible assembly components. Submit sample terms and exclusions with the bid and written manufacturer confirmation that the proposed recovery or replacement assembly is eligible. Identify any monetary limits, wind limits and maintenance conditions. A 5-inch insulation thickness alone does not establish warranty eligibility or property-insurance coverage. A materially different warranty requires written district approval before bid close.

Option 1 - Approved recovery

Include a qualified infrared thermographic survey of all C/D roof areas before covering; perform under suitable conditions using ASTM C1153 where applicable, verify anomalies by authorized core cuts or other appropriate moisture tests, and provide a marked moisture map, test results and photos. If the assembly cannot be reliably assessed thermographically, submit a supplemental verification method for approval; do not report unsuitable testing as proof of a dry roof.

Retain only dry, sound, securely attached materials eligible for recovery. Remove and replace confirmed wet/deteriorated insulation and associated affected materials to a sound substrate. Repair delamination and loose materials; furnish a compatible separation layer/cover board as required. Include new insulation needed to meet the total thickness and thermal requirements and a complete new membrane and flashing system.

Document layer count, load capacity, attachment and manufacturer/code acceptance. Do not recover a roof that is unsuitable; report the condition to the district.

Option 2 - Full removal and replacement

Remove all existing roofing, insulation and associated roof components in C/D down to the structural deck.

Inspect the deck with the district representative; replace approved deteriorated decking under unit prices.

Furnish new insulation, required vapor/air control layers, cover board, membrane, flashing and accessories as a complete warranted assembly. Include the C/D thermographic survey and verified moisture documentation before demolition when conditions permit, for owner records; do not delay safe replacement to rely on unsuitable survey conditions.

Wayland Union Schools | Transportation Building Roof 8

5 SPECIFICATIONS CONTINUED

5.3 DRAINAGE FLASHING AND EQUIPMENT

Provide positive drainage meeting applicable code, the approved design and manufacturer requirements.

Include tapered insulation, crickets and sumps as needed to correct ponding in the work areas without creating backfalls or trapping water at transitions. Submit the proposed drainage layout, slopes, insulation thicknesses and drainage paths. Do not reduce the required insulation thickness at sumps unless approved in the final design.

Inspect, clean and restore affected roof drains, strainers, scuppers, gutters and downspouts. Include necessary roof-level repairs, replacement and elevation adjustments within C/D to serve the new assembly; verify discharge paths and identify capacity or overflow deficiencies before bidding. Clarify major drainage redesign, new outlets or below-roof piping by addendum so all bidders price the same work.

Contractor is responsible for complete new or manufacturer-approved flashing and roof-edge assemblies at walls, corners, curbs, drains, pipes and penetrations, including blocking/nailers, terminations, counterflashing, edge metal and watertight transitions. Meet applicable edge securement requirements. Coordinate with affected trades for safe disconnect, lifting, curb adjustment, reconnection and operational verification of rooftop equipment; include these costs.

5.4 FINAL INSPECTION AND TURNOVER

Arrange final inspection by the district representative and manufacturer representative as required for warranty issuance. Complete a joint final walkthrough and punch list; correct deficiencies. Demonstrate drainage and equipment operation using approved methods. Deliver issued warranty documents, manufacturer inspection/acceptance, thermography and core-test records, approved repair quantities, as-built roof/drainage information, maintenance instructions, inspection schedule and warranty/service contacts. Final acceptance and payment require complete closeout documents.

All installation, inspection, punch-list corrections, warranty issuance and maintenance/document turnover must be completed by June 30, 2027. Coordinate weather limitations and manufacturer application conditions;

do not install outside approved conditions.

Wayland Union Schools | Transportation Building Roof 9

6 CONTRACTUAL OBLIGATIONS

6.1 FORM OF CONTRACT

This RFP requests offers for a construction contract. Selection alone does not authorize work. The district and successful contractor must execute a written agreement identifying the selected option, scope, accepted unit prices, schedule, contract conditions and authorized changes. No unattached contract form is incorporated by reference.

6.2 BONDS INSURANCE AND LEGAL REQUIREMENTS

For a contract exceeding $50,000, furnish performance and payment bonds as required by MCL 129.201, effective upon award. Proposed district requirement: each bond at 100% of the contract amount, through an authorized surety. Include premiums in bid pricing; district must confirm this proposed term before issuance.

Provide evidence of workers compensation, commercial general liability, automobile liability and any other required insurance. District must establish coverage limits, additional-insured terms and required endorsements in the issued contract conditions before bids are requested.

Contractor must obtain applicable permits and use required licensed trades. Comply with applicable safety, building, energy and environmental requirements. District must confirm architect/engineer involvement, approvals and construction supervision requirements for this project before release.

Confirm applicable state or federal prevailing wage requirements before advertisement and include required rates, contract language, registration and payroll requirements for covered work. [DISTRICT TO

RESOLVE FUNDING AND WAGE REQUIREMENTS]

6.3 CHANGES INVOICING AND PAYMENT

Only written district-authorized changes alter the contract price or scope. Obtain approval and document actual quantities for concealed repairs before covering. Invoices must identify the awarded option, approved unit-price quantities and authorized changes. Final acceptance and payment require corrected punch-list work and complete closeout documents. Payment terms and any retainage must be stated in the final issued agreement.

6.4 COMPLIANCE AND DISTRICT NAME

Comply with applicable laws, permits and district site policies. The agreement is governed by Michigan law.

Contractor may not use the district's name, officials or employees in advertising or imply endorsement without written district authorization. District counsel must finalize indemnification, termination, insurance and other contract terms before public issuance.

6.5 PROPOSAL CHECKLIST

Before sealing the proposal, verify: signed Attachment A; both complete option prices; unit rates;

qualifications and references; technical and warranty information; proposed schedule; bid security; notarized Attachments B and C; Attachment E; and any stated exceptions.

Wayland Union Schools | Transportation Building Roof 10

ATTACHMENT A

PROPOSAL PRICING FORM

Bidder legal name ______________________________________________________

Address ______________________________________________________

Contact / phone / email ______________________________________________________

Each option is an independent complete price for C and D. Prices include all common requirements and warranty fees.

Fill every line; use "not applicable" with an explanation where needed. Do not combine option totals.

Complete lump-sum price Section C Section D C + D total

Option 1 - Recovery $____________ $____________ $____________

Option 2 - Full replacement $____________ $____________ $____________

Recovery excludes unknown wet-insulation replacement quantities, which are adjusted only at the stated unit rates. Full replacement includes removal and new insulation for the entire area; no separate wet-insulation charge applies. Both options exclude unverified concealed deck replacement, adjusted only at the stated rates. Include all other specified work in option prices.

All-inclusive unit price (labor, materials, disposal, overhead and profit) Rate

Recovery: remove/dispose of wet insulation and affected roof material; replace with new insulation matching the verified retained thickness. Added insulation to reach specified total remains in base price.

$________ / SF

Concealed deck replacement - identify verified deck material, thickness and profile:

$________ / SF

Additional concealed blocking/nailer replacement beyond base work - identify size/material:

$________ / LF

Measurement: district-approved net installed area/length. Photograph conditions before covering; obtain written authorization. No concealed-work adjustment without approved quantity records. The district will issue common evaluation quantities before bid close; actual quantities may differ.

Manufacturer / proposed system ______________________________________________________

Attachment method / insulation type and thickness / stated R-value

Warranty term and type / limitations (attach sample) ______________________________________________________

Earliest start: __________________ Working days to completion: __________________

Addenda received (list numbers and dates): _____________________________________

Bid security issuer/type: __________________ Amount: $________________________

Bid prices remain firm for 60 calendar days after opening (proposed district term). List any exceptions on an attached sheet; exceptions may affect responsiveness. Bidder certifies it has examined the issued documents and included all specified work, except expressly identified exceptions.

Authorized signature: __________________________ Date: _____________________

Printed name / title: ______________________________________________________

AFFIDAVIT OF BIDDER

The undersigned, owner or authorized officer of __________________________ (the bidder), pursuant to the familial disclosure requirement, hereby represent and warrant that no familial relationships exist between the bidder or any employee of the bidder, and any member of the Board of Education of Wayland Union Schools, the Superintendent of the District, or the Chief Business Official.

BIDDER:

(Company Name)

By:________________________________________ (Signature)

Title:_______________________________________

STATE OF MICHIGAN )

) SS.

COUNTY OF_________________ )

This instrument was acknowledged before me on the ______ day of _____________________ 20 .

(Notary Public Signature)

___________________________ County, Michigan

My commission expires:_______________________

Acting in the county of:________________________

ATTACHMENT B

IRAN LINKED BUSINESS AFFIDAVIT

All Bids shall be accompanied by a sworn statement disclosing any Iran Linked Business relationship that exists within the owners, including its officers, directors and employees.

The undersigned, owner or authorized officer of _________________________________ (the bidder), pursuant to Michigan Public Act No. 517 of 2012, the “Iran Linked Business” hereby represents and warrants that the bidder, including its officers, directors and employees, is not an “Iran Linked Business” within the meaning of the applicable Public Act, and that in the event bidder is awarded a contract as a result of this RFP, the bidder will not become an “Iran Linked Business” at any time during the course of performing under the contract. The bidder further acknowledges that any person who is found to have submitted a false certification is responsible for a civil penalty of not more than $250,000.00 or 2 times the amount of the contract or proposed contract for which the false certification was made, whichever is greater, the cost of the District investigation, and reasonable attorney fees, in addition to the fine. Moreover, any person who submitted a false certification shall be ineligible to bid on future Requests for Proposals (RFPs) for three (3) years from the date that it is determined that the person has submitted the false certification.

There is not an “Iran Linked Business” that exists within the bidder and/or owner, officers, directors and employees.

Bidder: ___________________________________________________ (Company Name)

By: ___________________________________________________ (Signature)

(Title)

This instrument was acknowledged before me, a Notary Public, in and for

______________________ County, on this _____day of ___________________, 20__, ______________________________________________ SS:

(Notary Public Signature)

My Commission expires: _________________________

Acting in the County of: __________________________

ATTACHMENT C

Wayland Union Schools | Transportation Building Roof 11

ATTACHMENT E

CONTRACTOR ACKNOWLEDGMENT OF ADDENDA

Transportation Building Roof Improvements - Sections C and D

Contractor legal name: _____________________________________________________

The undersigned acknowledges receipt and review of the addenda listed below and includes their requirements in this proposal. Attach additional sheets if necessary.

Addendum number Date issued Date received

[ ] No addenda were issued or received (check only if accurate).

Authorized signature: _____________________________________________________

Printed name and title: ___________________________________________________

Date: __________________________________________________________________

Inspection Report

Prepared For:

Wayland Union Schools Bus Garage 851 Wildcat Dr Wayland, MI 49348

Bus Garage 851 Wildcat Dr Wayland, MI 49348

Site Overview Total Sections: 1 Total Sq/Ft: 8,984

Map Section Name Sq/Ft Grade 3 Section 3 8,984 F

Bus Garage 851 Wildcat Dr Wayland, MI 49348

Composition Section: Section 3 Size: 8,984 Overall Grade: F

Inspection Date: 04/10/2025

Bus Garage 851 Wildcat Dr Wayland, MI 49348

Section Overview Section: Section 3 Size: 8,984

Bus Garage 851 Wildcat Dr Wayland, MI 49348

Observations Section: Section 3 Size: 8,984

Bus Garage 851 Wildcat Dr Wayland, MI 49348

Deficiencies Section: Section 3 Size: 8,984 Overall Grade: F

Inspection Date: 04/10/2025

1 Perimeter - Wall Tie In failing Quantity: 120 LF Deficiency:

The termination from the membrane to the wall is either failing or improperly installed.

Corrective Action:

Remove caulking and or remove and replace termination bar to provide a water tight seal

2 Damaged roof (Emergency) Quantity: 1 null Deficiency:

51 square of roof is D. Elaminated and blowing up need to be replaced a s a p Corrective Action:

Bus Garage 851 Wildcat Dr Wayland, MI 49348

Deficiencies Section: Section 3 Size: 8,984 Overall Grade: F

Inspection Date: 04/10/2025

3 Field - Seam failure (Emergency) Quantity: 5 LF5 Deficiency:

The existing standing seam joint is failing or failed due to wind uplift.

Corrective Action:

Install new batten cap over existing seam or try and use existing seam fastening through the existing seams with fasteners.

4 Membrane - Punctures/Rips/Tears Quantity: 1 EA Deficiency:

These deficiencies are typically caused by heavy foot traffic by other trades, careless mechanical work, careless installation processes or storm related weather events.

Corrective Action:

Clean and prep the area around the puncture, rip or tear and repair according to the existing type of roof system meeting the minimum industry standards for the type of repair needed.

Bus Garage 851 Wildcat Dr Wayland, MI 49348

Deficiencies Section: Section 3 Size: 8,984 Overall Grade: F

Inspection Date: 04/10/2025

5 Perimeter - Corner Flashing Open Quantity: 1 EA Deficiency:

Corner detail is open and needs to be sealed.

Corrective Action:

We will clean and prime the area and install material to ensure water tightness.

6 Perimeter - Corner Flashing Open Quantity: 1 EA Deficiency:

Corner detail is open and needs to be sealed.

Corrective Action:

We will clean and prime the area and install material to ensure water tightness.

Bus Garage 851 Wildcat Dr Wayland, MI 49348

Deficiencies Section: Section 3 Size: 8,984 Overall Grade: F

Inspection Date: 04/10/2025

7 Perimeter - Corner Flashing Open Quantity: 1 EA Deficiency:

Corner detail is open and needs to be sealed.

Corrective Action:

We will clean and prime the area and install material to ensure water tightness.

Bus Garage 851 Wildcat Dr Wayland, MI 49348

Summary Section: Section 3 Size: 8,984 Overall Grade: F

Inspection Date: 04/10/2025

Condition Summary Membrane: F Flashings: F Sheet Metal: F

Overall: F

Estimated Replace: 2026

Wayland Union Schools | Transportation Building Roof 1

DISTRICT RELEASE CHECKLIST

Internal district review page - remove before public issuance. Complete remaining fields and contract/design review; then remove draft labels.

[ ] Confirmed: sealed bids must be hand-delivered by December 4, 2026, at 10:00 a.m. Eastern Time to the Administration Building, 893 E. Superior St., Wayland, MI 49348; public opening at the same location and time. Contact: Bill McSween, mcsweenw@waylandunion.org, 616-862-3829. Question deadline: December 2, 2026, at 2:00 p.m. Eastern. Set addenda access location.

[ ] Confirmed: mandatory pre-bid walkthrough December 1, 2026, at 1:00 p.m. Eastern Time at the Transportation Building, 851 Wildcat Dr. Installation in spring 2027, with all work and closeout completed before July 1, 2027. Prepare attendance roster. Allow adequate time after walkthrough clarifications for pricing; extend the bid deadline if material changes require more time.

[ ] Confirm C/D boundaries and A/B exclusion using the attached plan. Reconcile the report's 8,984-SF area with the 6,770-SF bid area. Verify existing deck, roof layers, insulation and recovery suitability with the design professional/manufacturer.

[ ] Finalize insulation R-value and thickness, drainage/slopes, wind attachment and edge details, and manufacturer warranty acceptance. The requested 5-inch thickness is a minimum project target, not a guarantee of a 20-year warranty or insurance coverage.

[ ] Obtain common estimated wet-insulation/deck repair quantities and publish them for bid comparison. Confirm unit-price definitions match the verified assembly.

[ ] Confirm funding, wage-law applicability, required wage schedules, contractor registration requirements and other required affidavits. Attach district-approved contract conditions and insurance limits; confirm proposed bond percentages and 60-day bid-hold period.

[ ] Confirm authorization to advertise and applicable adopted district policy. Arrange at least one local newspaper advertisement and at least two weeks of public state-site advertisement. Issuance date: November 20, 2026. Verify that the required state-site advertisement is publicly available for a full two weeks before the December 4, 2026, 10:00 a.m. closing time.

[ ] Confirm bid evaluation and board packet deadlines for anticipated December 14 board consideration. Remove this internal page and draft labels; fill all district fields before public posting.

Procurement references: MCL 380.1267 (school construction bidding); MCL 129.201 (public construction bonds); MCL

408.1103 (wage schedules for covered state projects). Official texts: legislature.mi.gov. Reviewed November 16, 2026.