Water Main Replacement Building 500 Questions and Answers.pdf
PDF 111 KB Posted
- Attached to
- M500 Water Main Replacement, Maxwell AFB
- Solicitation number
- PNQS2603400002
About this file
This is a Questions and Answers document for a Water Main Replacement project at Building 500, providing clarification on contract requirements and project specifications for bidders.
The project involves replacing 100 feet of existing 12-inch water main pipe located at depths ranging from 4 to 7.5 feet. The replacement pipe shall be C900 type, and contractors must backfill with sand and gravel compacted to 95 percent. An asphalt overlay of 3 inches is required. Pressure testing must be conducted using a hydrostatic standing pressure test at 90 PSI or 150 percent of working pressure, with contractors responsible for installing their own test valves. The project duration is 150 days maximum from Notice to Proceed. Maxwell AFB's 42 CES/CEO will handle utility locating and marking, hot work permits, and excavation permits, with markings provided to the contractor after NTP is issued. The contractor shall provide project supervision, while 42 CES/CEO serves as the Technical Monitor. Bonding requirements—including Bid Guarantee, Performance Bond, and Payment Bond—must be submitted with the proposal. The contractor is responsible for scheduling work, which may occur on weekends or weekdays at their discretion. If the contractor damages the water valve during work, repair or replacement is the contractor's responsibility. Civil drawings and service information are not available. No services or tees are included in the repair scope. The work scope is limited to items outlined in the Statement of Work, and no bidders list is available.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA330026R00120002 SF 30.pdf | ||
| Attachment 1 Specifications.pdf | ||
| Attachment 3 AF 3052 Construction Cost Breakdown.xlsx | XLSX spreadsheet | |
| Attachment 2 Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Water Main Replacement Building 500 Questions
Questions Answers
1. Are there any available drawings that specify the size of the existing pipe? There are no available drawings. Please reference the Statement of Work. The existing pipe is a 12” pipe.
2. If such drawings or plans are not available, could you provide a designated pipe size for bidders to reference? Establishing a standard size will help maintain a level playing field and prevent the need for potential change orders due to discrepancies after bidding, especially given the notable price variations between pipe sizes.
12” 12”
3. Additionally, do we have information on the depth at which the existing pipe is installed?
Please reference the Statement of Work. The existing pipe ranges from 4’ to 7.5’ deep.
Typo…this is in feet not inches.
4. Could you please clarify whether the government will handle marking the surrounding utilities before any excavation begins, or if this responsibility should be included by the contractor in their bid package?
42CES/CEO will be responsible for locating and marking all on-site utilities. Utility markings will be scheduled and provided to the contractor after notice to proceed is issued.
5. Could you please confirm whether the following bonding requirements will be required with the proposal or upon award:
• Bid Guarantee (Bid Bond)
• Performance Bond
• Payment Bond
Yes, bonding requirements will be required with the proposal.
6. Will we need to get blood hound out to locate?
No. Maxwell CE handles locating services, hot work, and Excavation Permits
7.776. Will we need to get blood hound out to locate?
7. How much of an overlay for asphalt?
3”
3”
8.
8. Will this be required to be done on the weekends or Mon-Friday?
As the Contractor schedules.
9. Will we need to back fill with sand & gravel?
Yes and compacted to 95%
Yes and compact to 95%
10. Will AFB be responsible for turning off the water & will we need to replace the valve in the event the valve doesn't hold?
No, but if you break it you must fix it.
11. We are to use 100ft as the length to replace in our bid?
Yes
12. Please verify and provide and provide the water line pipe type (C900, CL200, etc.)
C900
C900
13. Please verify and provide the pressure testing requirements, bac t testing also
Hydronic standing pressure test @ 90 PSI, or 150% of Working Pressure
14. Please verify and provide valve installation for testing
The contractor shall install his own test valves
15. Please verify and provide any services or tees in the repair section none
None
16. Please verify and provide any civil drawings
None known
17. Please verify and provide any civil drawings
None known
18. Please verify and provide the allowable outage times, 1 week, 2 weeks etc. to complete the repairs and testing
This timing will be provided by the Contractor. We will schedule the time needed to make this repair.
19. Please verify if there are any damages found outside of water line repair part of scope of work
The work approved is outlined in the SOW
20. Please verify who will be responsible for line locates by MAFB or 811
42CES/CEO
42 CES/CEO
21. Please verify the duration of days for the project.
150150150
150 (max) from the NTP per SOW
22. Please verify who will oversee the project, Maxwell AFB or the local county/municipality who owns/operates the water line
Contractor shall provide supervision. 42 CES/CEO will be the Tech Monitor
23. Can you please send me the bidders list for this project?
No, there is no bidders list.