Water Main Replacement Building 500 Questions and Answers.pdf

PDF 111 KB Posted

Attached to
M500 Water Main Replacement, Maxwell AFB
Solicitation number
PNQS2603400002
Issued by

About this file

This is a Questions and Answers document for a Water Main Replacement project at Building 500, providing clarification on contract requirements and project specifications for bidders.

The project involves replacing 100 feet of existing 12-inch water main pipe located at depths ranging from 4 to 7.5 feet. The replacement pipe shall be C900 type, and contractors must backfill with sand and gravel compacted to 95 percent. An asphalt overlay of 3 inches is required. Pressure testing must be conducted using a hydrostatic standing pressure test at 90 PSI or 150 percent of working pressure, with contractors responsible for installing their own test valves. The project duration is 150 days maximum from Notice to Proceed. Maxwell AFB's 42 CES/CEO will handle utility locating and marking, hot work permits, and excavation permits, with markings provided to the contractor after NTP is issued. The contractor shall provide project supervision, while 42 CES/CEO serves as the Technical Monitor. Bonding requirements—including Bid Guarantee, Performance Bond, and Payment Bond—must be submitted with the proposal. The contractor is responsible for scheduling work, which may occur on weekends or weekdays at their discretion. If the contractor damages the water valve during work, repair or replacement is the contractor's responsibility. Civil drawings and service information are not available. No services or tees are included in the repair scope. The work scope is limited to items outlined in the Statement of Work, and no bidders list is available.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Water Main Replacement Building 500 Questions

Questions Answers

1. Are there any available drawings that specify the size of the existing pipe? There are no available drawings. Please reference the Statement of Work. The existing pipe is a 12” pipe.

2. If such drawings or plans are not available, could you provide a designated pipe size for bidders to reference? Establishing a standard size will help maintain a level playing field and prevent the need for potential change orders due to discrepancies after bidding, especially given the notable price variations between pipe sizes.

12” 12”

3. Additionally, do we have information on the depth at which the existing pipe is installed?

Please reference the Statement of Work. The existing pipe ranges from 4’ to 7.5’ deep.

Typo…this is in feet not inches.

4. Could you please clarify whether the government will handle marking the surrounding utilities before any excavation begins, or if this responsibility should be included by the contractor in their bid package?

42CES/CEO will be responsible for locating and marking all on-site utilities. Utility markings will be scheduled and provided to the contractor after notice to proceed is issued.

5. Could you please confirm whether the following bonding requirements will be required with the proposal or upon award:

• Bid Guarantee (Bid Bond)

• Performance Bond

• Payment Bond

Yes, bonding requirements will be required with the proposal.

6. Will we need to get blood hound out to locate?

No. Maxwell CE handles locating services, hot work, and Excavation Permits

7.776. Will we need to get blood hound out to locate?

7. How much of an overlay for asphalt?

3”

3”

8.

8. Will this be required to be done on the weekends or Mon-Friday?

As the Contractor schedules.

9. Will we need to back fill with sand & gravel?

Yes and compacted to 95%

Yes and compact to 95%

10. Will AFB be responsible for turning off the water & will we need to replace the valve in the event the valve doesn't hold?

No, but if you break it you must fix it.

11. We are to use 100ft as the length to replace in our bid?

Yes

12. Please verify and provide and provide the water line pipe type (C900, CL200, etc.)

C900

C900

13. Please verify and provide the pressure testing requirements, bac t testing also

Hydronic standing pressure test @ 90 PSI, or 150% of Working Pressure

14. Please verify and provide valve installation for testing

The contractor shall install his own test valves

15. Please verify and provide any services or tees in the repair section none

None

16. Please verify and provide any civil drawings

None known

17. Please verify and provide any civil drawings

None known

18. Please verify and provide the allowable outage times, 1 week, 2 weeks etc. to complete the repairs and testing

This timing will be provided by the Contractor. We will schedule the time needed to make this repair.

19. Please verify if there are any damages found outside of water line repair part of scope of work

The work approved is outlined in the SOW

20. Please verify who will be responsible for line locates by MAFB or 811

42CES/CEO

42 CES/CEO

21. Please verify the duration of days for the project.

150150150

150 (max) from the NTP per SOW

22. Please verify who will oversee the project, Maxwell AFB or the local county/municipality who owns/operates the water line

Contractor shall provide supervision. 42 CES/CEO will be the Tech Monitor

23. Can you please send me the bidders list for this project?

No, there is no bidders list.

File details come from the government source that posted it. Updated .