WaitsburgToDaytonPavementRepairsSpecs.pdf
PDF 6 MB Posted
- Attached to
- US 12, Waitsburg to Dayton - Pavement repairs
- Solicitation number
- XE3784, FA Proj 9999(930)
- Issued by
- Cowlitz County, Washington
About this file
This is a pavement repair specifications document for a federally funded project administered by the State of Washington, involving improvements to US 12 in Walla Walla and Columbia Counties. The project scope encompasses crack sealing, hot mix asphalt (HMA) pavement repair at select locations, and traffic control measures across 17 line items. The work is classified as Work Class 4, Asphalt Concrete Paving, with a scheduled duration of 15 working days. The contract includes a 13% federal small business enterprise (SBE) goal as a requirement of federal funding.
The project is federally funded, which establishes the pricing framework and compliance requirements for this pavement repair initiative. No specific information regarding incumbent contractors, site visit requirements, bidders' meetings, award dates, or contract renewal options is contained within the specifications document provided.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For Construction of:
F. A. PROJECT NO .9999(930)
US 12
WAITSBURG TO DAYTON -
PAVEMENT REPAIRS
26Y016 A
CONTENTS 1
INTRODUCTION--------------------------------------------------------------------------------------- 1 3
SPECIAL PROVISIONS 4
DIVISION 1 5
GENERAL REQUIREMENTS 6
DESCRIPTION OF WORK -------------------------------------------------------------------------- 1 7
BID PROCEDURES AND CONDITIONS -------------------------------------------------------- 2 8
Examination of Plans, Specifications and Site of Work ------------------------------------ 2 9
General ------------------------------------------------------------------------------------------------ 2 10
Preparation of Proposal ---------------------------------------------------------------------------- 2 11
Bid Deposit -------------------------------------------------------------------------------------------- 3 12
Public Opening of Proposals --------------------------------------------------------------------- 3 13
Date Of Opening Bids ------------------------------------------------------------------------------ 3 14
Irregular Proposals ---------------------------------------------------------------------------------- 3 15
SCOPE OF THE WORK ----------------------------------------------------------------------------- 3 16
Coordination of Contract Documents, Plans, Special Provisions, Specifications, and 17 Addenda -------------------------------------------------------------------------------------------- 3 18
Procedure, Protest, and Dispute by the Contractor ----------------------------------------- 4 19
CONTROL OF WORK -------------------------------------------------------------------------------- 5 20
Cooperation with Other Contractors ------------------------------------------------------------ 6 21
Speed Safety Camera System Vendor --------------------------------------------------------- 6 22
CONTROL OF MATERIAL--------------------------------------------------------------------------- 6 23
Buy America Requirements ----------------------------------------------------------------------- 6 24
LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC ------------------------ 11 25
Laws To Be Observed ----------------------------------------------------------------------------- 11 26
Unmanned Aircraft Systems (UAS) ------------------------------------------------------------ 11 27
Environmental Regulations ---------------------------------------------------------------------- 11 28
Air Quality -------------------------------------------------------------------------------------------- 11 29
Asbestos Containing Material ------------------------------------------------------------------- 11 30
Load Limits ------------------------------------------------------------------------------------------- 11 31
Wages ------------------------------------------------------------------------------------------------ 12 32
General ---------------------------------------------------------------------------------------------- 12 33
Requirements For Nondiscrimination --------------------------------------------------------- 12 34
PAGE
26Y016 B
Federal Small Business Enterprise Participation ------------------------------------------ 19 1
Federal Agency Inspection ---------------------------------------------------------------------- 28 2
Required Federal Aid Provisions -------------------------------------------------------------- 28 3
Utilities and Similar Facilities ------------------------------------------------------------------- 28 4
PROSECUTION AND PROGRESS ------------------------------------------------------------- 30 5
Subcontracting ------------------------------------------------------------------------------------- 30 6
Subcontractor Approval -------------------------------------------------------------------------- 30 7
Submittal of Executed Subcontracts ---------------------------------------------------------- 31 8
Time For Completion ----------------------------------------------------------------------------- 31 9
Liquidated Damages ------------------------------------------------------------------------------ 31 10
MEASUREMENT AND PAYMENT --------------------------------------------------------------- 31 11
Weighing Equipment ----------------------------------------------------------------------------- 31 12
General Requirements for Weighing Equipment ------------------------------------------- 31 13
Electronic Delivery Management System (E-Ticketing) ---------------------------------- 31 14
Payment --------------------------------------------------------------------------------------------- 32 15
Payments-------------------------------------------------------------------------------------------- 32 16
Retainage ------------------------------------------------------------------------------------------- 32 17
DIVISION 2 18
TEMPORARY FEATURES 19
Public Convenience and Safety ---------------------------------------------------------------- 33 20
Construction Requirements --------------------------------------------------------------------- 33 21
Construction Under Traffic ---------------------------------------------------------------------- 33 22
Temporary Traffic Control ------------------------------------------------------------------------ 35 23
Materials --------------------------------------------------------------------------------------------- 35 24
Automated Flagger Assistance Devices ----------------------------------------------------- 35 25
Construction Requirements --------------------------------------------------------------------- 36 26
Traffic Control Management -------------------------------------------------------------------- 36 27
Traffic Control Devices --------------------------------------------------------------------------- 37 28
Automated Flagger Assistance Devices ----------------------------------------------------- 37 29
Temporary Portable Transverse Rumble Strips -------------------------------------------- 38 30
Payment --------------------------------------------------------------------------------------------- 38 31
Item Bids With Lump Sum for Incidentals --------------------------------------------------- 38 32
PAGE
26Y016 C
DIVISION 3 1
EARTHWORK 2
Removal of Structures and Obstructions ---------------------------------------------------- 39 3
Construction Requirements --------------------------------------------------------------------- 39 4
Removal and Disposal of Asbestos Material ------------------------------------------------ 39 5
DIVISION 5 6
SURFACE TREATMENTS AND PAVEMENTS 7
HOT MIX ASPHALT --------------------------------------------------------------------------------- 40 8
Materials --------------------------------------------------------------------------------------------- 40 9
Mix Design – Obtaining Project Approval ---------------------------------------------------- 40 10
ESAL's -------------------------------------------------------------------------------------------------- 40 11
HMA Tolerances, Specification Limits and Adjustments ------------------------------------ 40 12
Construction Requirements --------------------------------------------------------------------- 40 13
Equipment ------------------------------------------------------------------------------------------- 40 14
Payment --------------------------------------------------------------------------------------------- 40 15
Asphalt Cost Price Adjustment ----------------------------------------------------------------- 40 16
DIVISION 8 17
MISCELLANEOUS CONSTRUCTION 18
EROSION CONTROL AND WATER POLLUTION CONTROL --------------------------- 42 19
Construction Requirements --------------------------------------------------------------------- 42 20
General ---------------------------------------------------------------------------------------------- 42 21
DIVISION 9 22
MATERIALS 23
APPENDICES ---------------------------------------------------------------------------------------- 42 24
STANDARD PLANS --------------------------------------------------------------------------------- 42 25
PAVEMENT REPAIRS
26Y016 1
INTRODUCTION 1
This Contract shall be constructed in accordance with the 2027 Standard Specifications for 3 Road, Bridge, and Municipal Construction. 4
SPECIAL PROVISIONS 6
Several types of Special Provisions are included in this contract; General, Region, and Project 8 Specific. Special Provisions types are differentiated as follows: 9
(date) General Special Provision 11 (Region1 date) Region Special Provision 12 (******) Project Specific Special Provision 13
General Special Provisions are designated with the date they were last updated and include 15 standardized language that is used on applicable projects within Washington State. The only 16 difference since the specified date from one project to another is the inclusion of variable 17 project data, inserted as a “fill-in”. 18 Region Special Provisions are designated with the Region or Division abbreviation followed 20 by the date they were last updated and include standardized language that is used on 21 applicable projects within the designated Region or Division. The only difference since the 22 date specified from one project to another is the inclusion of variable project data, inserted as 23 a “fill-in”. Region and Division designations are as follows: 24
Region1 26 ER Eastern Region 27 NCR North Central Region 28 NWR Northwest Region 29 OR Olympic Region 30 SCR South Central Region 31 SWR Southwest Region 32 WSF Washington State Ferries Division 33
Project Specific Special Provisions are designated with six asterisks instead of a date. 35 These are provisions that normally appear only in the contract for which they were developed. 36
Division 1 38
General Requirements 39
DESCRIPTION OF WORK 41
(March 13, 1995) 43 This Contract provides for the improvement of *** US 12 MP 357.00 to MP 357.60 and MP 44
358.70 to MP 366.50, in Walla Walla and Columbia Counties. The work will consist of crack 45 sealing, HMA pavement repair at select locations, traffic control *** and other work, all in 46 accordance with the attached Contract Plans, these Contract Provisions, and the Standard 47 Specifications. 48
PAVEMENT REPAIRS
26Y016 2
Bid Procedures and Conditions 1 Examination of Plans, Specifications and Site of Work 3
General 5
Section 1-02.4(1) is supplemented with the following: 7
(September 3, 2019) 9 The Reference Information for this project is available for review by the bidder at the 10 following location: 11
*** ftp.wsdot.wa.gov - /contracts/ *** 13
The Reference Information includes the following: 15
*** 26Y016 Electronic Design Files are available by request*** 17
Preparation of Proposal 19 (November 20, 2023) 21 The fourth and fifth paragraphs of Section 1-02.6 are deleted. 22 Section 1-02.6 is supplemented with the following: 24
(October 5, 2026) 26
Bidder Questionnaire 27 The Bidder shall submit with their Bid a Bidder Questionnaire form (WSDOT Form #272-28 022). This shall be filled out for each firm who submitted a bid or quote in attempt to 29 participate in the project whether they were successful or not and include the following 30 information: 31
1. Firm name; 33
2. Firm address including ZIP code; 35
3. Firm’s status as a DBE or non-DBE; 37
4. NAICS code applicable to each scope of work the firm sought to perform in its 39 bid; 40
5. Age of the firm; and 42
6. The annual gross receipts of the firm. The Bidder may obtain this information by 44 asking each firm to indicate into what gross receipts bracket they fit (less than 45 $1 million; $1-3 million; $3-6 million; $6-10 million; $10-20 million; $20-30.72 46 million; or greater than $30.72 million) rather than requesting an exact figure 47 from the firm. 48
This form shall be received at the same location and no later than the time required for 50 the delivery of the Proposal. This form is meant to provide the Contracting Agency with 51 the above information so reasonable care shall be taken to complete the form as 52
PAVEMENT REPAIRS
26Y016 3 accurately as possible, and the questionnaire shall be corrected by the Bidder if requested 1 by the Contracting Agency. 2
Bid Deposit 4 The last sentence of the first paragraph of Section 1-02.7 is revised to read: 6
(October 5, 2026) 8 The Surety shall: (1) be registered with the Washington State Insurance Commissioner, 9 and (2) be listed as an active company under the “Surety” coverage type within the 10 database published by the Office of the Insurance Commissioner at 11 https://fortress.wa.gov/oic/consumertoolkit/Search.aspx. 12
Public Opening of Proposals 14 Section 1-02.12 is supplemented with the following: 16
(August 3, 2015) 18
Date of Opening Bids 19 The bid opening date for this project is *** December 9, 2026 ***. Bids received will be 20 publicly opened and read after 11:00:59 A. M. Pacific Time on this date. 21
Irregular Proposals 23 (October 5, 2026) 25 Item n, under Item 1 in Section 1-02.13, is deleted. 26 Scope of the Work 28 Coordination of Contract Documents, Plans, Special Provisions, 30
Specifications, and Addenda 31 Section 1-04.2 is supplemented with the following: 33
(November 20, 2023) 35
Document Control 36 This specification applies to project documentation and correspondence that occurs after 37 execution of the Contract. The Contractor shall submit all project documentation and 38 correspondence for this Contract in electronic format utilizing the WSDOT Unifier system. 39 Documents that are received by means other than the WSDOT Unifier system will be 40 rejected, except as allowed by this special provision or specifically approved by the 41 Engineer. 42 The Engineer may reject documents that are deemed unsuitable. This includes 44 documents that are illegible, unreadable, locked, etc. Forms that require further 45 information from WSDOT must be unlocked. 46 The Contractor shall submit to the Contracting Agency a Unifier Access Request Form 48 (WSDOT Form 134-092) to WSDOT e-Construction Support (e-49 ConstructionSupport@wsdot.wa.gov) designating all individuals requiring access to 50 WSDOT Unifier no later than 5 days following Contract Award. Training for WSDOT 51
PAVEMENT REPAIRS
26Y016 4
Unifier will be provided by WSDOT at no cost to the Contractor. Throughout the life of the 1 Project, all changes to the Contractor’s personnel who require access to the WSDOT 2 Unifier system shall be submitted on a Unifier Access Request Form. 3 All signed documents shall be in PDF format and will require an electronic signature. An 5 electronic signature is defined as a symbol, or process attached to or logically associated 6 with a record and executed or adopted by a person with the intent to sign the record. All 7 signed documents shall be in PDF format. 8 WSDOT has provided an application to be used to apply electronic signatures to the 10 following documents: 11
Change Orders that are not Minor Change Orders 13 421-009 Release – Retained Percentage (Except Landscaping) 14 134-146 Final Contract Voucher Certificate 15
When the Contract specifies that documentation is to be submitted through other web-17 based systems, such as the Diversity Management and Compliance System, or email 18 addresses, the Contractor shall utilize those systems and email addresses accordingly. 19 Before a Completion Date will be established by the Contracting Agency, all contractor 21 active tasks in Unifier shall be closed out or acknowledged. 22 All costs for submitting project documentation electronically shall be included in the 24 Contract prices for the Bid items of Work involved. 25
Procedure, Protest, and Dispute by the Contractor 27 Section 1-04.5 is supplemented with the following: 29
(March 9, 2026) 31
Project Partnering 32 The Engineer and the Contractor’s Project Manager (PM) will plan and host a Project 33 Partnering workshop as soon as practical after Contract execution. The objective of this 34 Partnering workshop is to promote open lines of communication and teamwork between 35 the Contracting Agency and Contractor staff for the effective completion of the work, and 36 to the standard of quality that will be a source of pride to both the Contracting Agency and 37 the Contractor. Commitments made by both parties shall be memorialized in a Project 38 Partnering Agreement at the conclusion of the Partnering workshop. The Partnering 39 agreement will not affect the terms of the Contract. It is intended only to establish an 40 environment of cooperation and mutual understanding between the parties. 41 The planning and execution of the Partnering process is intended to be a collaborative 43 effort between the Engineer and the PM. The length of the partnering workshop should 44 be commensurate with the size and complexity of the project, and familiarity of the parties. 45 For simple projects an expanded pre-construction meeting may suffice. The partnering 46 workshop may be facilitated by the Engineer, the Engineer and PM, or a mutually 47 agreeable Partnering Facilitator (PF). Selection of a PF, dates and location of the 48 workshops, materials needed for the workshop, frequency and location for follow up 49 meetings, and estimated cost associated with this effort should be discussed and agreed 50 to prior to moving forward with the Partnering process. 51
PAVEMENT REPAIRS
26Y016 5
An initial 1 day (or half day) facilitated Project Partnering workshop is recommended to 1 initiate the partnering agreement. 2 The cost to retain the services of a Partnering Facilitator (if mutually selected as the PF), 4 locate and rent a neutral location to hold the workshop (if held offsite), and any additional 5 materials needed to host the workshop, will be paid by the Contractor. The Partnering 6 Field Guide is available as a resource to the Engineer and PM to assist in the planning of 7 the Partnering session(s) at the following link: 8 https://wsdot.wa.gov/publications/fulltext/construction/WSDOTProjects-Partnering-10 FieldGuide.pdf 11
The Contracting Agency will reimburse invoice cost for the Contractor provided Partnering 13 Facilitator, facilities and materials at a rate of 50% under the Bid item, “Project Partnering”. 14 After the initial Partnering workshop, quarterly follow-up meetings on projects with over 16 120 working days shall be scheduled to evaluate how the Partnering process is working, 17 acknowledge successes and opportunities for improvement. 18 When the Project Engineer and Contractor’s Project Manager have determined 20 recognition is warranted, the cost for meals and awards for recognition of project 21 partnering success shall be borne by each party. Expenses shall be divided such that 22 each party pays for their pro rata share of the expenses based on the number of people 23 receiving the meal or award. Reimbursement for expenses initially paid by one party will 24 be made to the other party under the Bid item, “Project Partnering”. 25
Payment 27 “Project Partnering”, by calculation. 28 “Project Partnering” will be calculated and paid for as described above. 29
Control of Work 31 Final Acceptance 33 The second paragraph of Section 1-05.12 is revised to read: 35
(October 5, 2026) 37 The Contractor agrees that neither Completion nor final acceptance shall relieve the 38 Contractor of the responsibility to indemnify, defend, and protect the Contracting Agency 39 against all claims or losses (i) which may fall within the obligations of Section 1-07.14 40 herein, or (ii) resulting from the failure of the Contractor or subcontractors to pay all 41 laborers, mechanics, subcontractors, material persons, or others who provides labor, 42 supplies, or provisions for carrying out the Work or for payments required for 43 unemployment compensation under Title 50 RCW or for industrial insurance and medical 44 aid required under Title 51 RCW. To the extent applicable, the Contractor shall also 45 continue to satisfy any and all requirements of Section 1-07.18 which involve obligations 46 beyond final acceptance. 47
PAVEMENT REPAIRS
26Y016 6
Cooperation with Other Contractors 1 Section 1-05.14 is supplemented with the following: 3
(March 20, 2025) 5
Speed Safety Camera System Vendor 6 Coordination with a vendor managed by the Contracting Agency to provide portable 7 Speed Safety Camera Systems (SSCS) when workers are present within the work zone 8 may be required. If a SSCS is used on this Contract, the SSCS vendor’s field personnel 9 will need to enter the temporary traffic control zone to place and remove required signage 10 and equipment to implement the automated speed enforcement. The SSCS vendor may 11 document the work zone traffic control setup provided by the Contractor to confirm 12 workers are present prior to commencing operations with the SSCS. 13 The Engineer will set up a coordination meeting between the Contractor’s designated 15 traffic control manager, traffic control supervisor, the Contracting Agency, and the SSCS 16 vendor’s field personnel a minimum of 5 working days prior to the first anticipated 17 implementation date of the SSCS. At a minimum, coordination will include the following: 18
1. The anticipated date and time the SSCS vendor will be on site. 20
2. The expected work area location and temporary traffic control or staged traffic 22 plan that will be in place when the vendor will be on site, including the location(s) 23 of any Contractor-provided Radar Speed Display Sign (RSDS) if included in the 24 project. 25
3. Location for the SSCS vendor’s enforcement unit, photo enforcement sign, and 27
RSDS (may be vendor-provided if one is not provided by the Contractor). 28
4. Provide contact information between Contractor’s traffic control manager, traffic 30 control supervisor, Contracting Agency staff, and SSCS vendor. 31
Control of Material 33 Section 1-06 is supplemented with the following: 35 Buy America Requirements 37
(October 5, 2026) 39
General Requirements 40 In accordance with Buy America requirements contained in 23 CFR 635.410 and 2 CFR 41 184, the following materials must be produced in the United States: 42
1. All Iron or Steel Products used in the project. This means all manufacturing 44 processes, from the initial melting stage through the application of coatings, 45 occurred in the United States. 46
2. All Manufactured Products used in the project. This means the Manufactured 48
Product meets both the “final assembly requirement” and the “55 percent 49 requirement”. To meet the “final assembly requirement” the Manufactured 50 Product must have been manufactured in the United States. To meet the “55 51 percent requirement” all of the components of the Manufactured Product that 52
PAVEMENT REPAIRS
26Y016 7 are mined, produced, or manufactured in the United States must be greater than 1 55 percent of the total cost of all components of the Manufactured Product. 2
3. All Construction Materials used in the project. This means that all manufacturing 4 processes for the Construction Material occurred in the United States. 5
An article, material, or supply will be classified in one of four categories: 1) Iron or Steel 7 Product, 2) Manufactured Product, 3) Construction Material, or 4) Excluded Material. Only 8 a single category will apply to an item except as follows: 9
1. With respect to precast concrete products that are classified as Manufactured 11 Products, the components of precast concrete products that consist wholly or 12 predominantly of iron, steel, or combination of both shall meet the requirements 13 for and be tracked as an Iron or Steel Product. The item shall also meet the 14 requirements for and be tracked as a Manufactured Product. 15
2. With respect to intelligent transportation systems and other electronic hardware 17 systems that are classified as Manufactured Products, the cabinets or other 18 enclosures of such systems that consist wholly or predominantly of iron, steel, 19 or a combination of both, shall meet the requirements for and be tracked as an 20 Iron or Steel Product. The item shall also meet the requirements for and be 21 tracked as a Manufactured Product. 22
Some Contract items are composed of multiple parts that may fall into different categories. 24 Individual components will be categorized as a Construction Material, a Manufactured 25 Product, an Iron or Steel Product, or an Excluded Material based on their composition 26 when they arrive at the staging area or work site. 27 Definitions 29
1. Construction Material: Defined as any article, material, or supply brought to the 30 construction site for incorporation into the final product. Construction Materials 31 include an article, material, or supply that is or consists primarily of: 32
a. Non-ferrous metals including all manufacturing processes, from initial smelting 34 or melting through final shaping, coating, and assembly; 35
b. Plastic and polymer-based products including all manufacturing processes, from 37 initial combination of constituent plastic or polymer-based inputs, or, where 38 applicable, constituent composite materials, until the item is in its final form); 39
c. Glass including all manufacturing processes, from initial batching and melting of 41 raw materials through annealing, cooling, and cutting); 42
d. Fiber optic cable (includes drop cable) including all manufacturing processes, 44 from initial ribboning (if applicable), through buffering, fiber stranding and 45 jacketing, (fiber optic cable also includes the standards for glass and optical 46 fiber); 47
e. Optical fiber including all manufacturing processes, from the initial preform 49 fabrication stage, though the completion of the draw; 50
PAVEMENT REPAIRS
26Y016 8
f. Lumber including all manufacturing processes, from initial debarking through 1 treatment and planing; 2
g. Drywall including all manufacturing processes, from initial blending of mined or 4 synthetic gypsum plaster and additives through cutting and drying of 5 sandwiched panels; or 6
h. Engineered wood including all manufacturing processes from the initial 8 combination of constituent materials until the wood product is in its final form. 9 If a Construction Material is not manufactured in the United States it shall be 11 considered a Foreign Construction Material. 12
2. Excluded Material: A material where Buy America requirements do not apply. This 14 includes the following: 15
a. Materials excluded by Section 70917(c) of the Buy America, Build America Act 17 with respect to aggregates this includes cement and cementitious materials, 18 aggregates such as stone, sand, or gravel or aggregate binding agents or 19 additives. These materials shall be classified as Excluded Materials based on 20 the composition when brought to the work site. It also includes combinations of 21 these excluded materials when mixtures of Excluded Materials are delivered to 22 the work site without final form for incorporation into the project (i.e. wet concrete 23 and HMA). If they are formed prior to delivery, they are a Manufactured Product 24 and not an Excluded Material. 25
b. Temporary materials that are not being permanently incorporated into the 27 project. 28
c. Raw or minimal processed materials where the article, material, or supply does 30 not fall into any of the categories, as it is not a Manufactured Product, an Iron or 31 Steel Product, or a Construction Material and when these materials are 32 delivered to the work site without final form for incorporation into the product (i.e. 33 seed mix and topsoil). If they are formed prior to delivery, and are not an Iron or 34 Steel Product or a Construction Material, they are a Manufactured Product and 35 not an Excluded Material. 36
3. Iron or Steel Product: An article, material, or supply that consist of wholly or 38 predominantly of iron or steel or a combination of both. To be considered 39 predominantly of iron or steel or a combination of both means that the cost of the iron 40 and steel content exceeds 50 percent of the total cost of all its components. The 41 cost of iron and steel is based on a good faith estimate of the cost of the iron or steel 42 components. 43
4. Manufactured Product: A Manufactured Product includes any item produced as a 45 result of the manufacturing process. Items that should be treated as a manufactured 46 product (rather than a Construction Material) are: 1) items that consist of two or more 47 of the listed Construction Materials that have been combined together through a 48 manufacturing process, and 2) items that include at least one of the listed 49 Construction Materials as defined above, combined with a material that is not listed 50 through a manufacturing process. 51
PAVEMENT REPAIRS
26Y016 9
If a product is not an Iron or Steel Product, a Construction Material, or an Excluded 1 Material, it is a Manufactured Product. 2
If a manufactured material is not manufactured in the United States, it shall be 4 considered a Foreign Manufactured Product. 5
5. United States: To further define the coverage, a domestic product is a material that 7 was produced in one of the 50 states, the District of Columbia, Puerto Rico, or in the 8 territories and possessions of the United States. 9
Iron or Steel Product Requirements 11 Iron or Steel Products that are permanently incorporated into the project shall consist of 12 American-made materials only. Buy America requirements do not apply to temporary steel 13 or iron items, e.g., temporary sheet piling, temporary bridges, steel scaffolding and 14 falsework. 15 Minor amounts of foreign steel and iron may be utilized in this project provided the cost 17 of the foreign material used does not exceed one-tenth of one percent of the total Contract 18 cost or $2,500.00, whichever is greater. The total Contract cost is the final Contract cost, 19 including any modifications due to change orders, at the end of the project. 20 American-made material is defined as material having all manufacturing processes 22 occurring domestically. 23 If domestically produced steel billets or iron ingots are exported outside of the United 25 States, as defined above, for any manufacturing process then the resulting product does 26 not conform to the Buy America requirements. Additionally, products manufactured 27 domestically from foreign source steel billets or iron ingots do not conform to the Buy 28 America requirements because the initial melting and mixing of alloys to create the 29 material occurred in a foreign country. 30 Manufacturing begins with the initial melting and mixing and continues through the coating 32 stage. Any process which modifies the chemical content, the physical size or shape, or 33 the final finish is considered a manufacturing process. The processes include rolling, 34 extruding, machining, bending, grinding, drilling, welding, and coating. The action of 35 applying a coating to steel or iron is deemed a manufacturing process. Coating includes 36 epoxy coating, galvanizing, aluminizing, painting, and any other coating that protects or 37 enhances the value of steel or iron. Any process from the original reduction from ore to 38 the finished product constitutes a manufacturing process for iron. 39 Due to a nationwide waiver, Buy America requirements do not apply to raw materials (iron 41 ore and alloys), scrap (recycled steel or iron), and pig iron ore processed, pelletized, and 42 reduced iron ore. 43 The following are considered to be steel manufacturing processes: 45
1. Production of steel by any of the following processes: 47
a. Open hearth furnace. 49
b. Basic oxygen. 51
PAVEMENT REPAIRS
26Y016 10
c. Electric furnace. 1
d. Direct reduction. 3
2. Rolling, heat treating, and any other similar processing. 5
3. Fabrication of the products: 7
a. Spinning wire into cable or strand. 9
b. Corrugating and rolling into culverts. 11
c. Shop fabrication. 13
A certification of materials origin will be required for all Iron or Steel Products prior to such 15 items being incorporated into the permanent Work. The Contractor will not receive 16 payment until the certification is received by the Engineer. The certification shall be on 17 WSDOT Form 350-109 provided by the Engineer, or such other form approved by the 18 Contracting Agency, provided it contains the same information as WSDOT Form 350-109. 19 Manufactured Products and Construction Material Requirements 21 A Contractor provided certification of materials origin will be required before each 22 progress estimate or payment. The Contractor will not receive payment until the 23 certification is received by the Engineer. The Contractor shall certify that all Manufactured 24 Products and all Construction Materials installed during the current progress estimate 25 period meet the Buy America requirements. The certification shall be on WSDOT Form 26 350-107 provided by the Engineer, or such other form approved by the Contracting 27 Agency, provided it contains the same information as WSDOT Form 350-107. 28
Iron or Steel Products in a Manufactured Product 30 In addition to providing the certification of materials origin for the Manufactured 31 Product, the Iron or Steel Products in a Manufactured Product are subject to the Buy 32 America requirements as follows: 33
1. When a precast concrete product is classified as a Manufactured Product, 35 the components that are an Iron or Steel Product shall follow the “Iron or 36 Steel Requirements” of this Specification. 37
2. When an electronic hardware system such as an intelligent transportation 39 system is classified as a Manufactured Product, the cabinets and the other 40 enclosures of such systems that are an Iron or Steel Product shall follow 41 the “Iron or Steel Requirements” of this Specification. 42
Waiver for De Minimis Costs 44 Minor amounts of Foreign Construction Materials and Foreign Manufactured Products 45 may be utilized in this project, provided that the total cost of the Foreign Construction 46 Materials and Foreign Manufactured Products does not exceed $1,000,000 and does not 47 exceed 5 percent of the total applicable material costs calculated as follows: 48
< 0.05 50
PAVEMENT REPAIRS
26Y016 11
The total applicable material costs shall be the sum of the costs of all Construction 1 Materials, all Iron or Steel Products, and all Manufactured Products. Total applicable 2 material costs does not include Excluded Materials. 3
Legal Relations and Responsibilities to the Public 5 Laws to be Observed 7 Section 1-07.1 is supplemented with the following: 9
(March 9, 2026) 11
Unmanned Aircraft Systems (UAS) 12 The procurement and/or use of any drone (UAS) on this Contract shall comply with the 13 following directives: 14
• National Defense Authorization Act (NDAA) – American Security Drone Act of 16 2023 (ASDA, Pub. L. No. 118-31). 17
• Office of Management and Budget Memorandum M-26-02 – Restrictions on 19 using federal funds to purchase or operate prohibited foreign UAS. 20 Contractors, subcontractors, and lower-tier subcontractors shall not procure, operate, 22 maintain, or process data from prohibited UAS manufactured or assembled by “covered 23 foreign entities” as defined in the Federal Acquisition Security Council (FASC) in the 24 performance of this Contract. 25
Environmental Regulations 27
Air Quality 29
Asbestos Containing Material 31
Section 1-07.5(4)C is supplemented with the following: 33
(October 4, 2021) 35 Asbestos Good Faith Investigation 36 An asbestos Good Faith Investigation (GFI) has been conducted for this project 37 and it has been determined to a reasonable certainty that no known Asbestos 38 Containing Material (ACM) will be disturbed by the work on this project. The 39 asbestos GFI has been provided as Appendix *** A ***. 40
Load Limits 42 Section 1-07.7 is supplemented with the following: 44
(March 13, 1995) 46 If the sources of materials provided by the Contractor necessitates hauling over roads 47 other than State Highways, the Contractor shall, at the Contractor's expense, make all 48 arrangements for the use of the haul routes. 49
PAVEMENT REPAIRS
26Y016 12
Wages 1
General 3
Section 1-07.9(1) is supplemented with the following: 5
(January 6, 2026) 7 The Federal wage rates incorporated in this contract have been established by the 8 Secretary of Labor under United States Department of Labor General Decision No. 9
WA20260001. 10
The State rates incorporated in this contract are applicable to all construction 12 activities associated with this contract. 13
Requirements for Nondiscrimination 15 Section 1-07.11 is supplemented with the following: 17
(May 5, 2025) 19 Requirement for Affirmative Action to Ensure Equal Employment Opportunity 20 In accordance with 41 CFR § 60-4.2, the clauses contained in 1-4 below are required to 22 be included in this Contract. Nothing in this contract alters the Contractor’s responsibility 23 to comply with all applicable Federal regulations, including but not limited to 41 CFR part 24 60 as currently existing or later amended. 25
1. The Contractor's attention is called to the “Equal Opportunity Clause and the 27
Standard Federal Equal Employment Opportunity Construction Contract 28 Specifications” set forth herein. 29
2. The goals and timetables for minority and female participation set by the Office of 31
Federal Contract Compliance Programs, expressed in percentage terms for the 32 Contractor's aggregate work force in each construction craft and in each trade on all 33 construction work in the covered area, are as follows: 34
Women - Statewide 36
Timetable Goal 38
Until further notice 6.9% 40 Minorities - by Standard Metropolitan Statistical Area (SMSA) 41 Spokane, WA: 43
SMSA Counties: 44 Spokane, WA 2.8 45
WA Spokane. 46 Non-SMSA Counties 3.0 47
WA Adams; WA Asotin; WA Columbia; WA Ferry; WA Garfield; WA 48 Lincoln, WA Pend Oreille; WA Stevens; WA Whitman. 49
PAVEMENT REPAIRS
26Y016 13
Richland, WA 1 SMSA Counties: 2
Richland Kennewick, WA 5.4 3 WA Benton; WA Franklin. 4
Non-SMSA Counties 3.6 5 WA Walla Walla. 6
Yakima, WA: 8
SMSA Counties: 9 Yakima, WA 9.7 10
WA Yakima. 11 Non-SMSA Counties 7.2 12
WA Chelan; WA Douglas; WA Grant; WA Kittitas; WA Okanogan. 13 Seattle, WA: 15
SMSA Counties: 16 Seattle Everett, WA 7.2 17
WA King; WA Snohomish. 18 Tacoma, WA 6.2 19
WA Pierce. 20 Non-SMSA Counties 6.1 21
WA Clallam; WA Grays Harbor; WA Island; WA Jefferson; WA Kitsap; 22 WA Lewis; WA Mason; WA Pacific; WA San Juan; WA Skagit; WA 23 Thurston; WA Whatcom. 24
Portland, OR: 26
SMSA Counties: 27 Portland, OR-WA 4.5 28
WA Clark. 29 Non-SMSA Counties 3.8 30
WA Cowlitz; WA Klickitat; WA Skamania; WA Wahkiakum. 31 These goals are applicable to each nonexempt Contractor’s total on-site construction 33 workforce, regardless of whether or not part of that workforce is performing work on 34 a Federal, or federally assisted project, contract, or subcontract until further notice. 35 Compliance with these goals and timetables is enforced by the Office of Federal 36 Contract compliance Programs. 37 The Contractor's compliance with the Executive Order and the regulations in 41 CFR 39 Part 60-4 shall be based on its implementation of the Equal Opportunity Clause, 40 specific affirmative action obligations required by the specifications set forth in 41 41 CFR 60-4.3(a), and its efforts to meet the goals. The hours of minority and female 42 employment and training must be substantially uniform throughout the length of the 43 contract, in each construction craft and in each trade, and the Contractor shall make 44 a good faith effort to employ minorities and women evenly on each of its projects. 45 The transfer of minority or female employees or trainees from Contractor to 46 Contractor or from project to project for the sole purpose of meeting the Contractor's 47 goals shall be a violation of the contract, the Executive Order and the regulations in 48 41 CFR Part 60-4. Compliance with the goals will be measured against the total work 49 hours performed. 50
PAVEMENT REPAIRS
26Y016 14
3. The Contractor shall provide written notification to the Office of Federal Contract 1 Compliance Programs (OFCCP) within 10 working days of award of any construction 2 subcontract in excess of $10,000 or more that are Federally funded, at any tier for 3 construction work under the contract resulting from this solicitation. The notification 4 shall list the name, address and telephone number of the subcontractor; employer 5 identification number of the subcontractor; estimated dollar amount of the 6 subcontract; estimated starting and completion dates of the subcontract; and the 7 geographical area in which the contract is to be performed. The notification shall be 8 sent to: 9
U.S. Department of Labor 11 Office of Federal Contract Compliance Programs Pacific Region 12 Attn: Regional Director 13 San Francisco Federal Building 14 90 – 7th Street, Suite 18-300 15 San Francisco, CA 94103 16
(415) 625-7800 Phone 17
(415) 625-7799 Fax 18
4. As used in this Notice, and in the contract resulting from this solicitation, the Covered 20
Area is as designated herein. 21 In accordance with 41 CFR § 60-4.3, the clauses contained in 1-15 below are required to 23 be included in this Contract. Nothing in this Contract alters the Contractor’s responsibility 24 to comply with all applicable Federal regulations, including but not limited to 41 CFR part 25 60 as currently existing or later amended. 26 Standard Federal Equal Employment Opportunity Construction Contract Specifications 28
1. As used in these specifications: 30
a. “Covered Area” means the geographical area described in the solicitation from 32 which this contract resulted; 33
b. “Director” means Director, Office of Federal Contract Compliance Programs, 35
United States Department of Labor, or any person to whom the Director 36 delegates authority; 37
c. “Employer Identification Number” means the Federal Social Security number 39 used on the Employer's Quarterly Federal Tax Return, U.S. Treasury 40 Department Form 941; 41
d. “Minority” includes: 43
(1) Black (all persons having origins in any of the Black African racial groups 45 not of Hispanic origin); 46
(2) Hispanic (all persons of Mexican, Puerto Rican, Cuban, Central American, 48
South American, or other Spanish culture or origin, regardless of race); 49
PAVEMENT REPAIRS
26Y016 15
(3) Asian and Pacific Islander (all persons having origins in any of the original 1 peoples of the Far East, Southeast Asia, the Indian Subcontinent, or the 2 Pacific Islands); and 3
(4) American Indian or Alaskan Native (all persons having origins in any of the 5 original peoples of North America and maintaining identifiable tribal 6 affiliations through membership and participation or community 7 identification.) 8
2. Whenever the Contractor, or any subcontractor at any tier, subcontracts a portion of 10 the work involving any construction trade, it shall physically include in each 11 subcontract in excess of $10,000 the provisions of these specifications and the 12 Notice which contains the applicable goals for minority and female participation and 13 which is set forth in the solicitations from which this contract resulted. 14
3. If the Contractor is participating (pursuant to 41 CFR 60-4.5) in a Hometown Plan 16 approved by the U.S. Department of Labor in the covered area either individually or 17 through an association, its affirmative action obligations on all work in the Plan area 18 (including goals and timetables) shall be in accordance with that Plan for those trades 19 which have unions participating in the Plan. Contractors must be able to demonstrate 20 their participation in and compliance with the provisions of any such Hometown Plan. 21 Each Contractor or subcontractor participating in an approved Plan is individually 22 required to comply with its obligations under the EEO clause, and to make a good 23 faith effort to achieve each goal under the Plan in each trade in which it has 24 employees. The overall good faith performance by other Contractors or 25 subcontractors toward a goal in an approved Plan does not excuse any covered 26 Contractor's or subcontractor's failure to take good faith efforts to achieve the Plan 27 goals and timetables. 28
4. The Contractor shall implement the specific affirmative action standards provided in 30 paragraphs 7a through 7p of this Special Provision. The goals set forth in the 31 solicitation from which this contract resulted are expressed as percentages of the 32 total hours of employment and training of minority and female utilization the 33 Contractor should reasonably be able to achieve in each construction trade in which 34 it has employees in the covered area. Covered construction contractors performing 35 construction work in geographical areas where they do not have a Federal or 36 federally assisted construction contract shall apply the minority and female goals 37 established for the geographical area where the work is being performed. The 38 Contractor is expected to make substantially uniform progress in meeting its goals in 39 each craft during the period specified. 40
5. Neither the provisions of any collective bargaining agreement, nor the failure by a 42 union with whom the Contractor has a collective bargaining agreement, to refer either 43 minorities or women shall excuse the Contractor's obligations under these 44 specifications, Executive Order 11246, or the regulations promulgated pursuant 45 thereto. 46
6. In order for the nonworking training hours of apprentices and trainees to be counted 48 in meeting the goals, such apprentices and trainees must be employed by the 49 Contractor during the training period, and the Contractor must have made a 50 commitment to employ the apprentices and trainees at the completion of their 51
PAVEMENT REPAIRS
26Y016 16 training, subject to the availability of employment opportunities. Trainees must be 1 trained pursuant to training programs approved by the U.S. Department of Labor. 2
7. The Contractor shall take specific affirmative actions to ensure equal employment 4 opportunity. The evaluation of the Contractor's compliance with these specifications 5 shall be based upon its effort to achieve maximum results from its actions. The 6 Contractor shall document these efforts fully, and shall implement affirmative action 7 steps at least as extensive as the following: 8
a. Ensure and maintain a working environment free of harassment, 10 intimidation, and coercion at all sites, and in all facilities at which the 11 Contractor's employees are assigned to work. The Contractor, where 12 possible, will assign two or more women to each construction project. The 13 Contractor shall specifically ensure that all foremen, superintendents, and 14 other on-site supervisory personnel are aware of and carry out the 15 Contractor's obligation to maintain such a working environment, with 16 specific attention to minority or female individuals working at such sites or 17 in such facilities. 18
b. Establish and maintain a current list of minority and female recruitment 20 sources, provide written notification to minority and female recruitment 21 sources and to community organizations when the Contractor or its unions 22 have employment opportunities available, and maintain a record of the 23 organizations' responses. 24
c. Maintain a current file of the names, addresses and telephone numbers of 26 each minority and female off-the-street applicant and minority or female 27 referral from a union, a recruitment source or community organization and 28 of what action was taken with respect to each such individual. If such 29 individual was sent to the union hiring hall for referral and was not referred 30 back to the Contractor by the union or, if referred, not employed by the 31 Contractor, this shall be documented in the file with the reason therefor, 32 along with whatever additional actions the Contractor may have taken. 33
d. Provide immediate written notification to the Director when the union or 35 unions with which the Contractor has a collective bargaining agreement has 36 not referred to the Contractor a minority person or woman sent by the 37 Contractor, or when the Contractor has other information that the union 38 referral process has impeded the Contractor's efforts to meet its obligations. 39
e. Develop on-the-job training opportunity and/or participate in training 41 programs for the area which expressly include minorities and women, 42 including upgrading programs and apprenticeship and trainee programs 43 relevant to the Contractor's employment needs, especially those programs 44 funded or approved by the U.S. Department of Labor. The Contractor shall 45 provide notice of these programs to the sources compiled under 7b above. 46
f. Disseminate the Contractor's EEO policy by providing notice of the policy 48 to unions and training programs and requesting their cooperation in 49 assisting the Contractor in meeting its EEO obligations; by including it in 50 any policy manual and collective bargaining agreement; by publicizing it in 51 the company newspaper, annual report, etc.; by specific review of the policy 52
PAVEMENT REPAIRS
26Y016 17 with all management personnel and with all minority and female employees 1 at least once a year; and by posting the company EEO policy on bulletin 2 boards accessible to all employees at each location where construction 3 work is performed. 4
g. Review, at least annually, the company's EEO policy and affirmative action 6 obligations under these specifications with all employees having any 7 responsibility for hiring, assignment, layoff, termination or other 8 employment decisions including specific review of these items with on-site 9 supervisory personnel such as Superintendents, General Foremen, etc., 10 prior to the initiation of construction work at any job site. A written record 11 shall be made and maintained identifying the time and place of these 12 meetings, persons attending, subject matter discussed, and disposition of 13 the subject matter. 14
h. Disseminate the Contractor's EEO policy externally by including it in any 16 advertising in the news media, specifically including minority and female 17 news media, and providing written notification to and discussing the 18 Contractor's EEO policy with…