Wage Rates Summary

This is a Wage Decision Approval document issued by the New Mexico Department of Workforce Solutions Labor Relations Division for the Leyendecker Office Renovation project at New Mexico State University. The project involves the demolition and construction of a new office building at 7200 Plant Science Circle in Las Cruces, Dona Ana County, with an estimated total project cost of $3,600,000.00 and an estimated contract award date of January 25, 2027. The Leyendecker Agricultural Science Center Office will serve as dedicated office and meeting space for faculty, staff, students, and visitors to conduct research on sustainable agriculture, crop production, livestock management, natural resource management, environmental ecosystems, irrigation, plant science, and conservation practices. The project scope includes interior and exterior building demolition with utility disconnection and capping, new building construction with concrete foundations, structural metal framing, building envelope systems, and four office spaces with a conference room and reception area, as well as mechanical, electrical, plumbing systems, and site improvements. The approved Wage Decision Number is DA-26-3801-B with an expiration date of March 10, 2027.

The prevailing wage rates for this Type "B" General Building classification project, effective January 1, 2026, establish minimum compensation requirements for all classified trades including carpenters, electricians, plumbers, cement masons, roofers, drywall finishers, painters, laborers, and equipment operators. The document specifies that no federal funds are involved in this project. All contractors and subcontractors, regardless of contract amount and excluding professional services, must register with the Public Works and Apprenticeship Application website, pay prevailing wages, contribute to approved apprenticeship programs or the Public Works Apprentice and Training Fund, display wage rate posters at the jobsite, and submit required documentation including Statements of Intent to Pay Prevailing Wages and Affidavits of Wages Paid. The contracting agency contact is Yvonne Tellez at New Mexico State University, (575) 646-5001 Ext. 4, and additional inquiries should be directed to the Labor Relations Division at (505) 841-4400 or public.works@dws.nm.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Wage Decision Approval Summary

1) Project Title: Leyendecker Office Renovation Requested Date: 11/09/2026 Approved Date: 11/10/2026 Approved Wage Decision Number: DA-26-3801-B

Wage Decision Expiration Date: 03/10/2027

2) Physical Location of Jobsite for Project:

Job Site Address: 7200 Plant Science Circle Job Site City: Las Cruces Job Site County: Dona Ana

3) Contracting Agency Name (Department or Bureau): New Mexico State University Contracting Agency Contact's Name: Yvonne Tellez Contracting Agency Contact's Phone: (575) 646-5001 Ext.

4) Estimated Contract Award Date: 01/25/2027

5) Estimated total project cost: $3,600,000.00

a. Are any federal funds involved?: No

b. Does this project involve a building?: Yes - The Leyendecker Ag. Science Center Office is an office and meeting space for faculty, staff, students, and visitors.

c. Is this part of a larger plan for construction on or appurtenant to the property that is subject to this project?: No

d. Are there any other Public Works Wage Decisions related to this project?: No

e. What is the ultimate purpose or functional use of the construction once it is completed?: The Leyendecker Ag. Science Center Offices is a dedicated for faculty, staff, and students to conduct research on the sustainable agriculture, crop production, livestock, management of natural resources, environmental ecosystems, irrigation, plant science, sustainable farming practices, and conservation.

6) Classifications of Construction:

Classification Type and Cost Total

Description

General Building (B) Cost: $3,600,000.00

Demltion work includes disconnection and capping of existing utilities interior and exterior building demolition removal of existing foundations and concrete slabs as required hauling and disposal of demolition debris and site clearing and preparation for new construction New building construction includes concrete foundations and slabongrade structural metal framing steel joists and associated structural supports Building envelope construction includes exterior wall assemblies roofing systems insulation exterior doors and windows and associated weatherproofing To office building will include four 4 office spaces a conference room receptionlobby area and miscellaneous support spaces Interior construction includes metal stud partitions drywall installation and finishing ceilings flooring painting doors hardware and millwork The project includes mechanical electrical and plumbing MEP systems

LABOR RELATIONS DIVISION WWW.DWS.STATE.NM.US

401 Broadway NE Albuquerque, NM 87102 Phone: 505-841-4400 Fax: 505-841-4424

226 South Alameda Blvd Las Cruces, NM 88005 Phone: 575-524-6195 Fax: 575-524-6194

An Equal Opportunity Employer Page 1 of 2 including HVAC equipment electrical services lighting power plumbing fixtures domestic eater and sanitary waste piping and associated equipment and controls Site construction includes clearing and grubbing excavation earthwork fill and compaction site grading stormwater management drainage improvements and installation or modification of required site utilities Additional site improvements include concrete walks and flatwork access areas site restoration and other miscellaneous site work necessary to complete the project The following classification may be required Laborers operators carpenters electricians plumbers cement masons concrete finishers form setters ironworks structural steel erectors roofers sheet metal workers drywall installers tapers glaziers painters electricians plumbers pipefitters pipe layers and HVAC Technicians

An Equal Opportunity Employer Page 2 of 2

LABOR RELATIONS DIVISION WWW.DWS.NM.GOV

401 Broadway Blvd. NE

Albuquerque, NM 87102

505-841-4400

An Equal Opportunity Employer

PUBLIC WORKS PROJECT REQUIREMENTS

As a participant in a Public Works project valued at more than $60,000 in the State of New Mexico, the following list addresses many of the responsibilities that are defined by statute or regulation to each project stakeholder.

Contracting Agency

• Ensure that all contractors wishing to work on a Public Works project when the project is

$60,000 or more are actively registered with the Public Works and Apprenticeship Application

(PWAA) website: http://www.dws.nm.gov/pwaa (Contractor Registration).

• Please submit Notice of Contractor Designation (NOCD) and Subcontractor List(s) to the PWAA website promptly.

• Please update the Subcontractor List(s) on the PWAA website whenever changes occur.

• All sub-contractors and tiers (excluding professional services) regardless of contract amount must be listed on the Subcontractor List and must adhere to the Public Works Minimum Wage

Act.

• Ninety days after project completion please go into the PWAA system and close the project.

Only contracting agencies are allowed to close the project. Agents or contractors are not allowed to close projects.

General Contractor

• Provide a complete Subcontractor List and Statements of Intent (SOI) to Pay Prevailing Wages for all contractors, regardless of amount of work, to the contracting agency within 3 (three) days.

• Ensure that all subcontractors wishing to work on a Public Works project have an active

Contractor Registration with the Public Works and Apprenticeship Application (PWAA) website:

http://www.dws.nm.gov/pwaa.

• Make certain the Public Works Apprentice and Training Act contributions are paid either to an approved Apprenticeship Program or to the Public Works Apprentice and Training Fund.

• Confirm the Wage Rate poster, provided in PWAA, is displayed at the job site in an easily accessible place.

• When the project has been completed, make sure the Affidavits of Wages Paid (AWP) are sent to the contracting agency.

• All subcontractors and tiers (excluding professional services) regardless of contract amount must pay prevailing wages, be listed on the Subcontractor List, and adhere to the Public Works

Minimum Wage Act.

Subcontractor http://www.dws.nm.gov/pwaa

LABOR RELATIONS DIVISION WWW.DWS.NM.GOV

401 Broadway Blvd. NE

Albuquerque, NM 87102

505-841-4400

An Equal Opportunity Employer

• Ensure that all subcontractors wishing to work on a Public Works project have an active

Contractor Registration with the Public Works and Apprenticeship Application (PWAA) website:

http://www.dws.nm.gov/pwaa.

• Make certain the Public Works Apprentice and Training Act contributions are paid either to an approved Apprenticeship Program or to the Public Works Apprentice and Training Fund.

• All subcontractors and tiers (excluding professional services) regardless of contract amount must pay prevailing wages, be listed on the Subcontractor List, and adhere to the Public Works

Minimum Wage Act.

Additional Information

Reference material and forms may be found in the New Mexico Department of Workforce Solutions Public Works web pages at: https://www.dws.nm.gov/Labor-Relations/Labor-Information/Public- Works .

CONTACT INFORMATION

Contact the Labor Relations Division for any questions relating to Public Works projects by email at public.works@dws.nm.gov or call (505) 841-4400.

https://www.dws.nm.gov/Labor-Relations/Labor-Information/Public-Works https://www.dws.nm.gov/Labor-Relations/Labor-Information/Public-Works mailto:public.works@dws.nm.gov%20

Page | 1

Trade Classification

Base Rate

Fringe Rate

Apprenticeship

Cement Mason 26.26 11.61 0.60

Millwright/pile driver 51.77 22.13 0.60

Plasterer 27.16 9.59 0.60

Plumber/Pipefitter 39.92 16.85 0.60

Sprinkler Fitter 39.94 28.08 0.60

Asbestos Workers/Heat and Frost Insulators

Asbestos Workers/Heat and Frost insulators

39.23 12.16 0.60

Asbestos Workers/Heat and Frost insulators: Los Alamos County

41.36 12.16 0.60

Boilermaker/Blacksmith

Boilermaker/blacksmith 35.88 32.28 0.60

Boilermaker/blacksmith: San Juan County

36.83 31.88 0.60

Bricklayer/Block Layer/Stonemason

Bricklayer/Block layer/Stonemason 33.41 12.04 0.60

Bricklayer/Block layer/Stonemason Curry, DeBaca, Quay and Roosevelt counties

23.10 8.98 0.60

Bricklayer/Block layer/Stonemason Dona Ana, Otero, Eddie and Lea counties

26.42 8.98 0.60

Carpenter

Carpenter/Lather 32.12 14.28 0.60

Carpenter: Los Alamos County 38.56 14.70 0.60

Electricians-Outside Classifications: Zone 1

Ground man 28.54 13.36 0.60

Equipment Operator 40.94 17.73 0.60

TYPE “B” –

GENERAL BUILDING

Effective January 1, 2026

Page | 2

TYPE “B” - GENERAL BUILDING Effective January 1, 2026

Lineman or technician 51.71 21.43 0.60

Cable Splicer 52.98 21.75 0.60

Electricians-Outside Classification: Zone 2

Ground man 28.54 13.36 0.60

Equipment Operator 40.94 17.73 0.60

Lineman or technician 51.71 21.43 0.60

Cable Splicer 52.98 21.75 0.60

Electricians-Outside Classifications: Los Alamos County

Ground man 29.35 13.38 0.60

Equipment Operator 42.12 17.76 0.60

Lineman 53.07 21.77 0.60

Journeyman Technician 49.55 20.89 0.60

Cable Splicer 58.28 23.07 0.60

Electricians-Inside Classifications: Zone 1

Wireman/low voltage technician 42.30 13.42 0.60

Cable Splicer 46.53 13.55 0.60

Electricians-Inside Classification: Zone 2

Wireman/low voltage technician 46.11 13.53 0.60

Cable Splicer 50.34 13.67 0.60

Electricians-Inside Classification: Zone 3

Wireman/low voltage technician 48.65 13.60 0.60

Cable Splicer 52.88 13.74 0.60

Electricians-Inside Classification: Zone 4

Wireman/low voltage technician 53.30 13.75 0.60

Cable Splicer 57.53 13.87 0.60

Page | 3

Electricians-Inside Classification: Doña Ana, Hidalgo, Luna and Otero Counties

Wireman/low voltage technician 40.00 9.92 0.60

Cable splicer 40.00 9.92 0.60

Electricians-Inside Classification: Los Alamos County

Wireman/low voltage technician 48.65 16.04 0.60

Cable Splicer 52.88 16.38 0.60

Elevator Constructor

Elevator Constructor 53.27 40.89 0.60

Elevator Constructor Helper 37.30 40.89 0.60

Glazier

Glazier/Fabricator 22.75 7.70 0.60

Glazier: Los Alamos County 22.75 7.70 0.60

Ironworker

Ironworker Journeyman 29.45 19.51 0.60

Probationary Ironworker 23.56 19.51 0.60

Painter

Painter 21.00 5.75 0.60

Painter: Los Alamos County 35.85 12.82 0.60

Paper Hanger

Paper Hanger 21.00 5.75 0.60

Paper Hanger: Los Alamos County 36.85 12.82 0.60

Drywall Finisher/Taper 31.60 9.58 0.60

Drywall Finisher/Taper: Los Alamos County

35.85 12.82 0.60

Page | 4

Roofer

Roofer Journeyman 31.20 9.36 0.60

Roofer Helper 18.72 9.36 0.60

Sheet Metal Worker

Zone 1 40.74 19.29 0.60

Zone 2 – Industrial 41.74 19.29 0.60

Zone 3 – Los Alamos County 42.74 19.29 0.60

Soft Floor Layer

Soft Floor Layer 21.52 9.40 0.60

Soft Floor Layer: Los Alamos County 35.87 12.92 0.60

Tile Setter

Tile Setter 24.46 8.81 0.60

Tile Setter Finisher 16.53 8.81 0.60

Laborers

Group I- Unskilled 22.37 8.48 0.60

Group II – Semi-skilled 23.37 8.48 0.60

Group III- Skilled 23.37 8.48 0.60

Group IV - Specialty 25.62 8.48 0.60

Operators

Group I 26.61 8.22 0.60

Group II 29.07 8.22 0.60

Group III 29.61 8.22 0.60

Group IV 30.11 8.22 0.60

Page | 5

Group V 30.33 8.22 0.60

Group VI 30.57 8.22 0.60

Group VII 30.68 8.22 0.60

Group VIII 34.14 8.22 0.60

Group IX 36.89 8.22 0.60

Group X 40.77 8.22 0.60

Truck Drivers

Group I-VII 16.65 8.27 0.60

Group VIII 16.71 8.27 0.60

Group IX 18.65 8.27 0.60

NOTE: All contractors are required to pay SUBSISTENCE, ZONE, AND INCENTIVE PAY according to the particular trade. More information available at https://www.dws.state.nm.us/public-works.

For more information about the Subsistence, Zone, and Incentive Pay rates, or to file a wage claim, contact the New Mexico Department of Workforce Solutions Labor Relations Division at

(505) 841-4400 or visit us online at www.dws.state.nm.us.

https://www.dws.state.nm.us/public-works http://www.dws.state.nm.us/

Wage Decision Approval Summary.pdf
Project Requirements.pdf
Wage Rate Poster B.pdf

File details come from the government source that posted it. Updated .