W91ZRU19R0012_A2_Constr_QA_Insp_Svcs_19Sep19.pdf

PDF 215 KB Posted

Attached to
CONSTRUCTION QUALITY ASSURANCE INSPECTION SERVICES
Solicitation number
W91ZRU19R0012
Issued by

About this file

W91ZRU19R0012_A2_Constr_QA_Insp_Svcs_19Sep19

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

a. Incorporate FAR 52.228-5 Insurance -- Work on a Government Installation

b. PWS R1 19 Sep 19 incorporates subsection 1.4.7.1 Insurance

c. Incorporate Questions and Answ ers dated 19 Sep 19

d. All other terms and conditions remain unchanged

1. CONTRACT ID CODE PAGE OF PAGES

1 18

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-Sep-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91ZRU19R0012

X 9B. DATED (SEE ITEM 11)

16-Sep-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Sep-2019

CODE

W91ZRU USPFO FOR ALASKA

KO FOR AKNG

PO BOX B, CAMP DENALI

FT RICHARDSON AK 99505-2610

W91ZRU 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W91ZRU19R0012

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

The following have been added by full text:

PWS R1 19 SEP 19

PERFORMANCE WORK STATEMENT (PWS)

FOR

Construction Quality Assurance Inspection Services R1 19 September 2019

1.0 General:

1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform Construction Quality Assurance Inspection Services, as defined in this PWS.

1.2 Background: The Alaska Army National Guard (AKARNG) requires daily on-site Construction Quality Assurance (QA) Inspection Services for the duration of the construction project to ensure compliance with contract documents. The AKARNG needs to bridge the gap between the Type C services provided under an existing Supervision, Inspection and Overhead (SIOH) contract and Daily QA Inspection Services. An on-site Quality Assurance Inspector for the duration of the construction project will ensure adequate project oversight and that proper construction techniques are being followed by the construction contractor.

1.3 Period of Performance (PoP): The Period of Performance shall be 18 months.

1.4 General Information:

1.4.1 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary (PRS). A final QCP shall be submitted to the Contracting Officer Representative (COR) NLT 10 days after contract award. After acceptance of the QCP, the contractor shall obtain the Contracting Officer’s (KO’s) acceptance in writing of any proposed changes to its QCP.

1.4.2 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).

1.4.3 Recognized Holidays: The following are recognized United States (US) holidays. The contractor may be required to perform services on these days to coincide with construction contractor’s schedule if necessary to maintain the critical path:

1.4.3.1 New Year’s Day: January 1st

1.4.3.2 Martin Luther King, Jr.’s Birthday

1.4.3.3 President’s Day

1.4.3.4 Memorial Day

1.4.3.5 Independence Day: July 4th

1.4.3.6 Labor Day

1.4.3.7 Columbus Day

1.4.3.8 Veteran’s Day: November 11th

1.4.3.9 Thanksgiving Day

1.4.3.10 Christmas Day: December 25th

1.4.4 Place and Performance of Services: The contractor shall normally provide services between the hours of 0700-1700 on Monday through Friday unless otherwise required to maintain the critical path, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings.

Performance shall be at the AKARNG USPFO construction site, Camp Denali, JBER-Richardson, Alaska, 99505, the Construction Facility Management Office (CFMO) located on Camp Carroll, Building 57024, JBER-Richardson, Alaska 99505, and at the USPFO Purchasing and Contracting Office, Building 49140, Camp Denali, JBER-Richardson, Alaska 99505. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential. Teleworking is not authorized.

1.4.4.1 Reserved

1.4.4.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented.

Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.4.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times, and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation which may affect performance. The Government reserves the right to direct the removal of an employee for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.

1.4.5 Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the COR. The contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by Department of Defense (DoD), Headquarters Department of Army (HQDA) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1.4.5.1 For contractors requiring Common Access Card (CAC): The CAC is the DoD Federal Personal Identity Verification (PIV) credential. CAC issuance requirements are as follows:

In accordance with Department of Defense Manual (DoDM) 1000.13-M-V1, DoD Identification (ID) Cards, January 23, 2014, initial issuance of a CAC requires, at a minimum, the completion of an Federal Bureau of Investigation (FBI) fingerprint check with favorable results and submission of a National Agency Check with Inquiries (NACI) (or investigation approved in Federal Investigative Standards) to the Under Secretary of Defense for Intelligence (USD(I)) approved investigative service provider. The issuance of a CAC will be based on four criteria: (a) eligibility for a CAC; (b) verification of DoD affiliation from an authoritative data source; (c) completion of background vetting requirements according to the Federal Information Processing Standards Publication 201-2, Personal Identity Verification (PIV) of Federal Employees and Contractors, August 2013, and DoD Manual 5200.02, Procedures for the DoD Personnel Security Program (PSP), April 3, 2017, and (d) verification of a claimed identity. Sponsorship and enrollment information about each applicant must be registered in the Defense Enrollment Eligibility Reporting System (DEERS) through either the Real-Time Automated Personnel ID System (RAPIDS) using the DD Form 1172-2, or the Trusted Associate Sponsorship System (TASS).

1.4.5.1.1 HSPD-12 Background Investigation Requirements: The contractor shall ensure that all contractor and subcontractor personnel whose duties require CAC card issuance obtain them, and shall process all CAC card applications. The contractor shall ensure that all employees requiring an initial background investigation complete a Personnel Security Investigation Portal (PSIP) form at Attachment A, at the earliest possible date and that this form is forwarded to the COR immediately. The COR will review the form for completeness and accuracy and forward it to the National Guard Bureau (NGB) Personnel Security manager who will initiate the investigation process via the PSIP. Contractor personnel will then receive two e-mail messages; the first will confirm that the investigative service provider has received the request, and the second will provide instructions for the completion of the appropriate form via the Electronic Questionnaires for Investigations Processing (e-QIP) system. Upon completion of the e- QIP questionnaire and submittal of all required documents, including fingerprint card to the security manager, the background investigation (BI) will be initiated. The contractor shall ensure immediate compliance with all instructions regarding background investigation processing, including those provided verbally, by e-mail or via a Government system. The contractor is cautioned that the entire process from submittal of the PSIP form to return of the FBI fingerprint check may routinely take from two to six weeks and shall factor this lead time into its hiring/placement process. The contractor shall make all reasonable efforts to ensure that contractor employees meet CAC eligibility standards upon assignment to the contract and shall be held responsible for delays, failure to meet performance requirements or decreases in efficiency in accordance with the applicable inspection clause.

1.4.5.1.2 Trusted Associate Sponsorship System (TASS): The contractor shall process CAC applications through the TASS, the procedures for which are described below. Although there is no requirement for the contractor to designate a “Corporate Facility Security Officer" (FSO) to serve as its single point of contact for the BI, the TASS application process and other CAC and security-related matters, such designation facilitates these processes. If an FSO is not established, all contractor employees requiring a CAC will be required to process their own applications. The submission process for CAC applications is as follows:

1. The contractor's FSO or contractor employee shall submit requests for a CAC via email to the designated TASS Trusted Agent (TA). The TASS TA for this requirement will be: “TBD.”

2. The Government will establish a TASS application account for each CAC Request and will provide each contractor employee a USER ID and password, via email, to the FSO. The FSO or contractor employee shall access the TASS account and complete the CAC application (entering/editing contractor information as applicable) at: https://www.dmdc.osd.mil/tass/. The FSO or contractor employee shall follow up to ensure that the TA is processing the request.

3. The Government will inform the contractor's applicant, via email, of one of the following:

a. Approval.* Upon approval, the information is transferred to the DEERS database and an email notification is sent to the contractor with instructions on obtaining their CAC. The contractor proceeds to a RAPIDS station (RAPIDS Site Locator: http://www.dmdc.osd.mil/rsl/).

b. Rejection.* The Government, in separate correspondence, will provide reason(s) for rejection.

c. Return. Additional information or correction to the application required by the contractor employee.

*The contractor shall maintain records of all approved and rejected applications.

1.4.5.1.3 At the RAPIDS station, the RAPIDS Verification Officer will verify the contractor employee by SSN and two forms of identification. Identity source documents must come from the list of acceptable documents included in Form I-9, OMB No. 1615-0047, "Employment Eligibility Verification." Consistent with applicable law, at least one document from the Form I-9 list shall be a valid (unexpired) State or Federal Government-issued picture ID. The Identity documents will be inspected for authenticity and scanned and stored in the DEERS upon issuance of an ID. The photo ID requirement cannot be waived, consistent with applicable statutory requirements. The Verification Officer will capture primary and alternate fingerprints, picture, and updates to DEERS, and will then issue a CAC. Issued CACs will be valid for no longer than three years, or until the individual's contract end date (inclusive of any options), whichever is earlier.

1.4.5.1.4 The contractor shall return issued CACs to the DEERS office upon departure or dismissal of each contractor employee, and shall obtain a receipt for each card and provide it to the TA/COR.

1.4.5.1.5 The contractor shall manage requests for new or renewal CAC cards in sufficient time to ensure that all contractor employees have them when needed to perform work under this contract. The contractor shall provide at least 10 calendar days advance notice to the TA, unless there are extenuating circumstances approved by the COR or KO/KS.

1.4.5.1.6 The contractor shall obtain an Army Knowledge Online (AKO) email address for each applicant, including subcontractors, who may be deployed or require logical access to a government computer network. This can be done by going to: http://www.us.army.mil and registering as an "Army Guest," with the sponsor being the COR or a COR- designated individual if the COR is ineligible to Serve as an AKO Sponsor. Note: If employees of a contractor lose the privilege to access AKO, they lose the ability to renew their CAC. Therefore, it is critical that contractor employees maintain their AKO accounts.

1.4.5.2 Reserved

1.4.5.3 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information.

The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.

1.4.5.4 Use of Government Information Systems (IS) and access to Government networks is a revocable privilege, not a right. Users are the foundation of the DoD strategy and their actions affect the most vulnerable portion of the Army Enterprise Infostructure (AEI). Contractor employees shall have a favorable background investigation or hold a security clearance and access approvals commensurate with the level of information processed or available on the system. Contractor employees shall:

1.4.5.4.1 Comply with the command's Acceptable Use Policy (AUP) for Government owned IS and sign an AUP prior to or upon account activation.

1.4.5.4.2 Complete initial and/or annual Information Assurance (IA) training as defined in the IA Best Business Practices (BBP) training (https://informationassurance.us.army.mil).

1.4.5.4.3 Mark and safeguard files, output products, and storage media per classification level and disseminate them only to individuals authorized to receive them with a valid need to know.

1.4.5.4.4 Protect IS and IS peripherals located in their respective areas in accordance with physical security and data protection requirements.

1.4.5.4.5 Practice safe network and Internet operating principles and take no actions that threaten the integrity of the system or network.

1.4.5.5 Protection of Personally Identifiable Information (PII). The contractor shall protect all PII encountered in the performance of services in accordance with Defense Federal Acquisition Regulation Supplement (DFARS) 224.103 Personally Identifiable Information and Department of Defense Directive (DoDD) 5400.11, Department of Defense Privacy Program, and DoD 5400.11-R. If a PII breach results from the contractor’s violation of the aforementioned policies, the contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals whose PII has been compromised.

1.4.5.6 AT Level 1 Awareness Training (AT): All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete Level 1 AT within 30 calendar days after contract start date and within 30 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the ACO within 15 calendar days after completion of training. Level 1 AT is available at http://jko.jten.mil/courses/atl1/launch.html .

1.4.5.7 Information Assurance (IA)/Information Technology (IT) Training: All contractor employees and associated subcontractor employees shall complete the DoD IA Awareness Training before issuance of network access and annually thereafter. All contractor employees performing services involving IA/IT functions shall comply with DoD and Army workforce training requirements in DoDD 8140.01, DoD 8570.01-M and AR 25-2 within six months of the start of contract performance. In accordance with DoD 8570.01-M, DFARS 252.239.7001 and AR 25-2, contractor employees performing Information Assurance Technical (IAT) functions shall be appropriately certified upon contract award. The baseline certification as stipulated in DoD 8570.01-M shall be completed upon contract award.

1.4.5.8 Information Awareness: All contractor employees with access to a government information system shall be registered in the Army Training Certification Tracking System (ATCTS) (https://atc.us.army.mil/iastar/index.php) at commencement of services, and shall successfully complete the DoD Information Assurance awareness training prior to access to the IS and then annually thereafter.

(https://ia.signal.army.mil/DoDIAA/).

1.4.5.9 iWATCH Training: The contractor and all associated subcontractors with an area of performance within an Army-controlled installation, facilities or area shall brief all employees on the local iWATCH program. This local developed training shall be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or the ACO. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance. The contractor shall report completion for each contractor employee and subcontractor employee to the ACO within 15 calendar days after completion of training.

1.4.5.10 OPSEC Training: In accordance with AR 530-1, Operations Security, new contractor employees shall complete Level I OPSEC training within 30 calendar days of their reporting for duty and annually thereafter. The contractor shall submit certificates of completion for each contractor employee to the ACO within 15 calendar days after completion of training. Level 1 OPSEC training is available at http://cdsetrain.dtic.mil/opsec/.

1.4.5.11 Reserved

1.4.5.12 Reserved

1.4.5.13 Reserved

1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.4.6.1 Key Control. NOTE: All references to keys include key cards. The contractor shall establish and implement methods of ensuring that no keys/key cards issued by the Government are lost or misplaced or are used by unauthorized persons. No keys issued by the Government shall be duplicated. The contractor shall include procedures covering key control in the QCP. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The contractor shall immediately report any occurrences of lost or duplicated keys/key cards to the COR.

1.4.6.1.1 In the event keys, other than master keys, are lost or duplicated, the contractor shall, upon direction by the KO/KS, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the Government replaces or re-keys the locks, the Government will deduct the total cost of lock replacement or re-keying from the monthly payment due the contractor. In the event a master key is lost or duplicated, the Government will replace all locks and keys for that system, and will deduct the total cost from the monthly payment due the contractor.

1.4.6.1.2 The contactor shall prohibit the use of the Government issued keys/key cards by any persons other than the contractor’s employees. The contractor shall prohibit the opening of locked areas by contractor employees to permit entrance of persons other than contactor employees engaged in the performance of services in those areas, or personnel authorized entrance by the KO.

1.4.6.2 Lock Combinations: The contractor shall establish and implement methods of ensuring that no lock combinations are revealed to unauthorized persons. The contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations. These procedures shall be included in the contractor’s QCP.

1.4.7 Special Qualifications: The Contractor shall ensure that any personnel performing under the contract are fully trained, licensed in the State of Alaska (as applicable), certified and qualified to provide services in accordance with the requirements of the PWS.

1.4.7.1 Insurance: Contractors working on a Government Installation shall comply with minimum requirements in accordance with FAR 28.307-2 – Liability pursuant to applicable (a) Federal and State Workers’ compensation and employer’s liability; (b) General liability; and (c) Automobile liability.

1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO/KS in accordance with FAR Subpart 42.5. The KO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO/KS will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO/KS. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the ACO, to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO/KS. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.10 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non- Government entities. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed.

The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO/KS within 14 days of an employee’s departure.

1.4.11 Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.

1.4.12 Contractor Travel N/A

1.4.13 Data Rights N/A

1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO/KS immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO/KS to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.15 Phase In / Phase Out Periods: N/A

2.0 Definitions and Acronyms:

2.1 Definitions:

2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2 Contracting Officer (KO): A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3 Contracting Officer Representative (COR): An employee of the U.S. Government designated by the KO to monitor contractor performance. Such appointment will be in writing and will state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4 Contract Specialist (KS): A person with responsibility for daily contract administration and management on behalf of the government.

2.1.5 Defective Service: A service output that does not meet the standard of performance associated with the PWS.

2.1.6 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.7 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.8 Physical Security: Actions that prevent the loss or damage of Government property.

2.1.9 Quality Assurance: The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.10 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.11 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.

2.1.12 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.2 Acronyms:

ACO Administrative Contracting Officer AEI Army Enterprise Infostructure AKARNG Alaska Army National Guard AKST Alaska Standard Time AR Army Regulation AT/OPSEC Antiterrorism/Operational Security BI Background Investigation CFMO Construction Facility Management Office CFR Code of Federal Regulations CM Contract Manager

CMRA Contractor Manpower Reporting Application COMSEC Communications security CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative CQC Contractor Quality Control DA Department of the Army DD254 Department of Defense Contract Security Classification Specification DFARS Defense Federal Acquisition Regulation Supplement DoD Department of Defense FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services HQDA Headquarters, Department of the Army HSPD Homeland Security Presidential Directive IA Information Assurance IS Information System(s) Jacobs Jacobs Engineering Group JBER Joint Base Elmendorf-Richardson KO Contracting Officer KS Contract Specialist NGB National Guard Bureau OCI Organizational Conflict of Interest PII Personally Identifiable Information PIV Personal Identity Verification PIPO Phase In/Phase Out POC Point of Contact PoP Period of Performance PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SIOH Supervision, Inspection and Overhead SSN Social Security Number TE Technical Exhibit USD(I) Under Secretary of Defense for Intelligence USPFO United States Property and Fiscal Office

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:

3.1 Property: The Government will furnish the necessary workspace for the contractor to perform services outlined in this PWS to include desk space, telephones, computers and other items necessary to maintain an office environment.

3.2 Materials: The Government will furnish the supply items necessary to maintain an office environment.

3.3 Equipment: The Government will furnish the necessary mobile and desk telephones, computers, printers and lighting necessary to maintain an office environment.

3.4 Services: The Government will furnish the necessary telephone and computer support services necessary to maintain an office environment.

3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):

4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.

4.2 Secret Facility Clearance: N/A

5.0 Requirements: The contractor shall:

5.1 General Tasks. The Contractor shall act as the quality assurance (QA) inspector for the duration of the construction contract. Primary responsibilities shall include daily oversight and documentation of construction activities in coordination with the Contracting Officer Representative (COR), Jacobs, Contract Specialist (KS), and Contracting Officer (KO). Contractor shall perform daily quality assurance inspections and is responsible for providing oversight and independent inspection and verification of construction contractor(s) quality control processes, and documentation of all construction activities.

Contractor shall monitor and inspect construction activities and advise the COR on quality control and quality assurance issues, such as non-compliance with standards, or potential problems (e.g., technical, legal, or political) that may impact schedule, scope, cost, or safety. Contractor shall conduct field reviews and inspections of ongoing and completed work to verify competency and accuracy with respect to approved construction methods and applications and in accordance with contract specifications and plans.

5.1.1 Quality Assurance Inspection Tasks.

5.1.1.1 Will review the contractor’s quality control plan looking for clarity and completeness to ensure it meets the contract requirements.

5.1.1.2 The contractor shall be onsite for all required inspections, tests and reports made by the contractor, subcontractors, specially trained technicians, equipment manufacturers and others as required.

5.1.1.3 Contractor will be present for the weekly, monthly meetings and conferences at the project site unless otherwise approved by the KO/KS in advance. Contractor will review the meeting minutes and will report to the COR any discrepancies or points of concern impacting quality assurance, construction schedule, critical work sequencing, long-lead items, procedures for processing field changes, change orders, procedures for testing and inspecting, submittal procedures, sustainable design requirements, preparation of record documents, work restrictions, working hours, or safety concerns.

5.1.1.4 The contractor will review the construction contractors daily Contractor Quality Control (CQC) report, and will monitor and report to the COR and KO/KS any occurrence of adverse weather and the resultant impact to normally scheduled work. Documentation will be used to determine the basis for granting additional days should the construction contractor make such a request for actual adverse weather delay days.

5.1.1.5 The contractor shall review construction contractor coordination drawings to confirm that the work is being coordinated, but not for the details of the coordination, which are the construction contractor's responsibility. If contractor determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, contractor will report findings to the COR and KO/KS for the purpose of informing the construction contractor, who shall make changes as directed and resubmit.

5.1.2 Project Web Site

5.1.2.1 The contractor shall review and make recommendations to the government pertaining to submittals, RFIs and other contractor provided documentation within the Project Web site for purposes of managing project communication and documentation through final completion. All project documentation shall be maintained in the Project Web site.

5.1.3 Reports.

5.1.3.1 The contractor shall prepare daily construction logs documenting construction activity and report immediately any areas of concern to the COR and KO/KS. Construction logs shall be provided to the COR daily.

5.1.3.2 The contractor shall review the Daily Construction Report submitted by the construction contractor ensuring there are no impacts to quality assurance.

5.1.3.3 The contractor shall review material location reports at weekly intervals to ensure the construction contractor is keeping track of all material stored prior to previous report and remaining in storage. Material stored prior to previous report and since removed from storage and installed. Material stored following previous report and remaining in storage. Any discrepancies that could impact quality assurance will be reported to the COR.

5.1.3.4 The contractor shall review site condition reports prepared by the construction contractor and will report any discrepancies that could impact quality assurance will be reported to the COR.

5.1.3.5 The contractor shall review special reports and will take note of an event of an unusual and significant nature which occurs at the project site, whether or not related directly to the work that impacts quality or safety on the project. The contractor will prepare and submit a special report to the COR explaining issues related to the special event that need to be addressed with the construction contractor.

5.1.4 Review of Construction Photographs

5.1.4.1 Contractor shall review construction contractor’s photographs to ensure properly documented in accordance with specifications for specified and periodic requirements.

5.1.4.2 The contractor shall review construction photographs as they may pertain to the construction contractor’s quality control plan and shall report any concerns with the construction photographs to the

COR.

5.1.5 Monthly Reports

5.1.5.1 Contractor shall prepare monthly reports in coordination with COR as specified in the contract documents covering the period from the notice to proceed through the final inspection.

5.1.5.2 Contractor shall review construction contractor’s monthly reports to verify the percentages of progress are in agreement with the government. If agreement cannot be made, a joint report shall be prepared and submitted to the KO/KS.

5.1.5.3 Contractor, KO, KS, COR, and/or other Government personnel, will meet monthly with the construction contractor to review the contractors performance.

5.2 Contractor Manpower Reporting Application (CMRA):

5.2.1 The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Alaska Army National Guard Bureau via a secure data collection site.

5.2.2 The contractor shall completely fill in all required data fields using the following web address:

http://www.ecmra.mil/. Reporting inputs shall be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2019. Contractors may direct questions to the help desk at http://www.ecmra.mil.

6.0 Applicable Publications: Publications applicable to this PWS are listed below:

Publication (Chapter/Page)

Date of Publication

Mandatory or Advisory

Website

Federal Acquisition Regulation Advisory https://www.acquisition.gov/?q=browsefar or http://farsite.hill.af.mil/

Defense Federal Acquisition Regulation Supplement

Advisory http://www.acq.osd.mil/dpap/dars/dfarspgi/current /index.html or http://farsite.hill.af.mil/

DoDM 1000.13-M-V1 DoD Identification (ID) Cards (Enclosure 2, paragraph 3.b)

01/23/2014 Advisory http://www.esd.whs.mil/Directives/issuances/dod m/

Federal Information Processing Standards (FIPS) Publication 201-2 Personal Identity Verification (PIV) of Federal Employees and Contractors

(paragraph 9)

August 2013 Advisory http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.2 01-2.pdf

Army Directive 2014-05 Policy and Implementation

Procedures for Common Access Card Credentialing and Installation Access for Uncleared Contractors

03/07/2014 Advisory http://www.apd.army.mil/ProductMaps/PubForm/ ArmyDir.aspx

AR 190-13

The Army Physical Security Program

02/25/2011 Advisory http://www.apd.army.mil/ProductMaps/PubForm/ AR.aspx

Homeland Security Presidential Directive (HSPD)-12

Policy for a Common Identification Standard for Federal Employees and

Contractors

08/27/2004 Advisory https://www.dhs.gov/homeland-security-presidential-directive-12

DoDD 5400.11 Department of Defense Privacy

Program

10/29/2014 Advisory http://www.dtic.mil/whs/directives/corres/dir.html#

DoD 5400.11-R Department of Defense Privacy

Program

05/14/2007 Advisory http://www.dtic.mil/whs/directives/corres/pub1.htm l

DoDD 8140.01 Cyberspace Workforce Management

08/11/2015 Advisory http://www.dtic.mil/whs/directives/corres/dir.html

DoD 8570.01-M Information Assurance Workforce

Improvement Program

12/19/2005 (Change 4:

11/10/2015)

Mandatory http://www.dtic.mil/whs/directives/corres/pub1.htm l

AR 25-2

Information Assurance

10/24/2007 Advisory http://armypubs.army.mil/ProductMaps/PubForm/ AR.aspx

AR 530-1

Operations Security

09/26/2014 Mandatory http://armypubs.army.mil/ProductMaps/PubForm/ AR.aspx

DA PAM 415-28 Guide to Real Property Category Codes 13 July 2013 Mandatory

10 July 2013 Advisory http://armypubs.army.mil/ProductMaps/PubForm/ AR.aspx

National Guard Pamphlet 415-12 Construction

25 January

Advisory https://www.ngbpdc.ngb.army.mil/Portals/27/Publi cations/ngr/ngpam%20415-12.pdf?ver=2018-09-

07-082536-893

Army Regulation 405-70 Utilization of Real Property

12 May 2006 Advisory https://armypubs.army.mil/epubs/DR_pubs/DR_a/ pdf/web/r405_70.pdf

NG PAM 415-5

Army National Guard Military

Construction Program Execution

31 July 2003 Mandatory https://www.ngbpdc.ngb.army.mil/Portals/27/Publi cations/ngr/ngpam%20415-5.pdf?ver=2018-09-

07-082536-783

TECHNICAL EXHIBIT 1

Performance Requirements Summary (PRS)

This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).

Performance

Objective Performance Standard Acceptable Quality

Levels (AQL) Surveillance Method / By

Whom

5.1.1.2 On-site for all required inspections, tests and reports by contractor / subcontractors, etc.

Contractor shall be on-site for all inspections, tests and reports unless otherwise authorized by the COR 2 weeks in advance.

Does not meet the standard no more than two occurrences during a 12 month period.

Random / COR

5.1.1.3 Will be present for the weekly, monthly meetings and conferences at the project site

Contractor shall be present for all weekly, monthly meetings and conferences unless otherwise authorized by the COR 2 weeks in advance.

Does not meet the standard no more than two occurrences during a 12 month period.

Periodic / COR

5.1.1.4 Review the construction contractor’s daily CQC report, and monitor any occurrence of adverse weather and the resultant impact to normally scheduled work.

Contractor shall report to the COR any occurrence which could result in an impact to normal operations within 2 hours of identification.

Does not meet the standard no more than two occurrences during a 12 month period.

Random / COR

5.1.1.5 Review coordination drawings to confirm work is being coordinated.

Contractor shall report to the COR any occurrence which could result in an impact to normal operations within 2 hours of identification.

Does not meet the standard no more than two occurrences during a 12 month period.

5.1.2.1 Review and maintain project documentation in the Project Web site

Contractor shall maintain all project documentation in the Project Web site.

Failure to meet standard 100% of the time.

5.1.3.1 Prepare daily construction logs.

Contractor shall prepare and provide construction logs to the COR daily.

Failure to provide reports daily no more than 2 occurrences in a 12 month period.

Continuous / COR

5.1.3.2 Review construction contractor’s daily reports.

Contractor shall review construction contractor’s daily reports and report concerns to the COR immediately.

Does not meet standard no more than 2 occurrences in

5.1.3.3 Review material storage reports.

Contractor shall review Material location reports and report findings to the COR weekly.

Does not meet than 2 occurrences in

5.1.3.4 Review site condition reports reporting any discrepancies impact QA.

Contractor shall submit daily site conditions report to the

COR.

Does not meet than 2 occurrences in a 12 month period.

Continuous / COR

5.1.3.5 Prepare and submit to the COR special reports explaining issues related to special events occurring at the project site.

Contractor shall prepare and submit a special report to the COR within 2 hours explaining issues related to any special event that needs to be addressed with the construction contractor.

Failure to prepare report and provide within 2 hours of identifying an issue related to any special event no more than 2 occurrences in a 12 month period.

Periodic / COR

5.1.4 Review Construction Photographs as they pertain to overall quality assurance.

Contractor shall report to the COR any concerns within 1 hour.

Failure to report quality assurance concerns within 1 hour 100% of the time.

TECHNICAL EXHIBIT 2

Deliverables Schedule

PWS Reference / Deliverable Title

Frequency Number of Copies

Medium/Format Submit To

1.4.1. Quality

Control Plan

10 days after contract award

N/A Electronic Submission

ACO/COR

1.4.5.6 AT Level 1

Awareness Training

Certificates

Provide within 15 calendar days after employee completes training.

N/A Electronic Submission

ACO/COR

1.4.5.9 iWatch Training Certificates

Provide within 15 calendar days after employee completes training.

N/A Electronic Submission

ACO/COR

1.4.5.10 OPSEC

Training Certificates

Provide within 15 calendar days after employee completes training.

N/A Electronic Submission

ACO/COR

1.4.10 Identification

Media

Return within 14 days of employee’s departure from contract performance.

Original(s) Hard Copy ACO/COR

1.4.11 Combating

Trafficking in

Persons

Prior to contractor performance, than annually thereafter

N/A Electric Submission

ACO/COR

52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION (JAN 1997)

(a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts…