Attachment 2 - Performance Work Statement Revised 120121.docx
DOCX document 23 KB Posted
- Attached to
- Epoxy Service
- Solicitation number
- W91ZLK-22-R-0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08 Combined SS Revised 120121.DOCX | DOCX document | |
| B08 Attachment 1 - Provisions and Clauses.docx | DOCX document | |
| B08 Combined SS 111521.DOCX | DOCX document | |
| B08 Attachment 2 - Performance Work Statement.docx | DOCX document | |
| B08 Attachment 3 - Quality Assurance Surveillance Plan.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SYNOPSIS/SOLICITATION
W91ZLK-22-R-0001
Attachment 2 – Performance Work Statement Revised 12/01/2021
PERFORMANCE WORK STATEMENT
REPAIR AND RECOAT FLOORS AND WALLS WITH CHEMICAL RESISTANT EPOXY
AT THE CHEMICAL TRANSFER FACILITY SUMP AREA AND CHEMICAL WASTE HOLDING TANK SECONDARY CONTAINMENT AREA AND SELECT LABORATORIES AND STORAGE ROOMS, BLDG E3832, ABERDEEN PROVING GROUND MD 21010
1. INTRODUCTION: The U.S. Army Combat Capabilities Development Command – Chemical Biological Center (CCDC-CBC) Chemical Transfer Facility (CTF) is a repository for research and development stock of toxic chemical agents. The facility includes a critical system of storage tanks and piping. Surfaces in portions of the CTF are coated with epoxy that is resistant to hazardous and aggressive chemicals.
1.1. BACKGROUND: The U.S. Army Combat Capabilities Development Command – Chemical Biological Center (CCDC-CBC) Chemical Transfer Facility (CTF) requires the repair and recoat of floors and walls with chemical resistant epoxy portions where the current coating is failing due to being greater than 10 years old.
1.2. OBJECTIVE: The objective of this contract is to repair and recoat the floor and walls of the CTF sump area, secondary holding tank area, and select laboratories and storage rooms to ensure containment of any hazardous or aggressive chemicals, should there ever be a leak in the system.
2.0. GENERAL: The Government will award a Firm Fixed-Price contract for repair and recoating of the floor and walls of the CTF sump area, secondary holding tank area, and select laboratories and storage rooms.
2.1. Period of Performance - The contractor shall provide services in the “Base” table below within three (3) months from the date of award. Should the option be exercised, the contractor shall provide services in the “Option” table below within three (3) months from the date of the option being exercised. The Government will be required to exercise the option(s) within twelve (12) months from the date of award.
2.2. Place of Performance - Chemical Transfer Facility (CTF) sump area and secondary holding tank area located in Building E3832 on the Edgewood Area of Aberdeen Proving Ground. The contractor shall be required to get a pass upon entering APG at the Visitor Center located at either Aberdeen North or Aberdeen South (Edgewood). Visitor Center information is available at www.home.army.mil/apg/index.php/about/visitor-information.
2.3. Business hours are 7:00AM – 5:00PM EST, Monday through Friday, excluding federal Holidays. Contractor is not required to perform services on the following Holidays:
| New Year’s Day | Labor Day | ||
| Martin Luther King Jr.’s Birthday | Columbus Day | ||
| President’s Day | Veteran’s Day | ||
| Memorial Day | Thanksgiving Day | ||
| Independence Day | Christmas Day |
3.0. TECHNICAL REQUIREMENT: The contractor, as an independent contractor and not as an agent of the government, shall provide sufficient personnel possessing the skills, knowledge, training, and experience to perform the required tasks. All training, education and certification will be accomplished outside of this contract.
3.1. The Contractor shall provide proof of a minimum of five (5) years’ experience repairing and recoating floors and walls with chemical resistant epoxy.
4.0. PERFORMANCE REQUIREMENTS. The U.S. Army Combat Capabilities Development Command, Chemical Biological Center (CCDC CBC) requires the floor and walls of the CTF sump area and secondary holding tank area, as well as the floors in select laboratories and storage rooms to be stripped of old epoxy surface and recoated with an epoxy that is resistant to hazardous and aggressive chemicals including organic solvents, strong acids (such as hydrochloric and sulfuric), strong bases (such as 20% sodium hydroxide solution), and oxidizing/bleach (such as 10% Sodium Hypochlorite solution). The new chemical-resistant epoxy coating shall be applied in two coats of at least 10 mils thick each. The coating shall be sufficiently resilient that it will be undamaged by the traffic of heavy rolling carts or forklifts up to 10,000lbs. The coating shall be sufficiently adhered to the concrete substrate that if a scratch, crack, or chip occurs, the coating will not further flake off in sheets or cracks spread. Coatings without solvents or VOCs are preferred. The contractor shall utilize a system to capture the dust generated during stripping and shall dispose of project waste and debris. The Chemical Transfer Facility is located in Building E3832 on the Edgewood Area of Aberdeen Proving Ground. Subject to the availability of Government escorts, the vendor may be able to work in more than one room at a time. In order to not disrupt operations in the CTF, the vendor cannot, however, strip and prepare all rooms at once prior to applying epoxy.
The CTF sump area has approximately 400 square foot of area needing to be repaired and recoated. The chemical waste holding tank area has approximately 2,000 square foot of area needing to be repaired and recoated. Additional Laboratories and Storage Rooms are approximately 400 1,500 square feet needing to be repaired and recoated. “Repair” refers to removal of old epoxy and preparation of concrete substrate for new epoxy adhesion (to include some filling of uneven surfaces). Note in particular that the CTF sump is below-grade and requires “Confined Space entry”.
Base Requirement
| Tank Farm |
| Approx. 2,000 sq. ft. |
| Room 27 Sump Pit & Tank |
| Approx. 400 sq. ft. |
Options
| Room 2 |
| Approx. 215 sq. ft. |
| Room 3 |
| Approx. 200 sq. ft. |
| Room 25 |
| Approx. 85 sq. ft. |
| Room 26 |
| Approx. 300 sq. ft. |
| Room 28 |
| Approx. 290 sq. ft. |
| Room 29 |
| Approx. 290 sq. ft. |
| Room 31 |
| Approx. 290 sq. ft. |
| Various |
| Up to 10 isolated epoxy repair locations within the CTF, with each site being less than 4 sq. ft. |
4.1. The contractor shall remove and dispose of all refuse/waste generated as a result of this project.
4.2. The contractor shall warranty their labor to be free from material defect for one (1) year or 12-months following completion of the contract.
4.3. The Government will provide access to electricity and restrooms. The Government certifies that the project area contains no lead paint or asbestos.
5.0. SECURITY: All personnel will have a valid Government-issued ID and may be subject to search of belongings upon entry and exit of facility. All personnel will sign in at the front office and receive a Safety and Security brief. All personnel are to remain in approved areas with a facility-assigned escort.
5.1. Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation, Director of Operations (DoO) or Protection Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
5.2. For contractors that do not require a CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractor employees shall comply with adjudication standards and processes using the National Crime Information Center Interstate Identification Index (NCIC- Ill) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/ facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
5.3. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity Antiterrorism Officer (ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
6.0. ENVIRONMENTAL
6.1. Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulations and policies. Contractor shall immediately report any conflicts between applicable Federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the Contracting Officer Representative (COR) as well as the Director of Engineering & Public Works.
6.2. Contractor shall immediately report any nonconformance and/or noncompliance with applicable Federal, State or Local environmental laws, Army and installation environmental regulations or policies to the COR and Director of Engineering & Public Works.
7.0. SAFETY AND HEALTH
7.1. Contractor personnel or any representative of the contractor shall abide by all federal and Department of the Army safety regulations while working on the Aberdeen Proving Grounds. The contractor will have a written Confined Space Entry Program. The contractors Confined Space Entry Program will be available for review tens (10) days prior to commencing work after award of contract.
7.2. Should contractor operational or confined space procedures indicate the requirement for respiratory protection, the contractor shall have and meet all requirements in a Respiratory Protection Program in accordance with (IAW) the current versions of 29 CFR 1910.134
7.3. Contractor personnel shall comply with all on-site safety requirements which may include, but not be limited to, sign in/out, daily building safety briefs and the use of personal protective equipment (PPE).
7.4. The contractor shall notify the Contracting Officer’s Representative (COR) of any accident or incident mishap related to, or incurring during the performance of, this contract immediately.
8.0. QUALITY ASSURANCE SURVEILLANCE PLAN (QASP): (See Attached)