Request for Proposal W91ZLK-13-R-0005
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until 04:00 PM local time 07 Dec 2012
X
A
X B
X C
D
EX
X
G
F 57 - 64
65 - 76
X H 77 - 86 david.a.macinty re.civ@mail.mil
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA
FAR (48 CFR) 53.214(c)
03 1 86
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
W91ZLK 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 6 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and
ACC-APG, MD
conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
DAVE A. MACINTYRE 410-278-4693
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 3
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
4 - 13 J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 16 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 17 - 22 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIO NS AND INSTRUCTIO NS
PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS
23 - 47
PART II - CO NTRACT CLAUSES
ACC APG, AICD - W91ZLK
ABERDEEN INSTALLATION CONTRACTING DIV.
4118 SUSQUEHANNA AVENUE
ABERDEEN PROVING GROUND MD 21005-3013
FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
48 - 56
6. REQUISITION/PURCHASE NO.
W23SR30166ME21
5. DATE ISSUED
25 Oct 2012
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
W91ZLK-13-R-0005
Section B - Supplies or Services and Prices
AGGREGATE MAXIMUM AMOUNT
The Government intends to award six (6) indefinte quantity/indefinite delivery (ID/IQ) contracts, including three (3) awards to small businesses. Each contract awarded will have a five (5) year ordering period. The Government reserves the right to issue up to an additional six (6) month extension in accordance with FAR 52.217-8. the total AGGREGATE maximum amount to be awarded against all Task Orders on all awarded Contracts is $48,000,000 (including the potential
6-month extention).
MINIMUM GUARANTEE
Each contract awarded under this multiple award IDIQ shall provide for a MINIMUM
GUARANTEE OF $400,000.00. This minimum guarantee may be satisfied by obligating funds and/or issuing a task order (or task orders) against the base contract.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
ANALYTICAL SERVICES (CPFF)
CPFF
Performance of analytical services associated with target descriptions, vulnerability, survivability, weapons effectiveness studies, and support to current operations. See Performance Work Statement (PWS) at Section C; specific services to be specified at the task order level. This CLIN shall be used for Cost
Plus Fixed Fee (CPFF) efforts.
FOB: Destination
PURCHASE REQUEST NUMBER: W23SR30166ME21
ESTIMATED COST
FIXED FEE
TOTAL EST COST + FEE
ANALYTICAL SERVICES (FFP)
FFP
Performance of analytical services associated with target descriptions, vulnerability, survivability, weapons effectiveness studies, and support to current operations. See Performance Work Statement (PWS) at Section C; specific services to be specified at the task order level. This CLIN shall be used for Firm
Fixed Price (FFP) efforts.
NET AMT
CONTRACTOR MANHOUR REPORTING
Cost for Providing Accounting for Contract Services – RDECOM CC 001-10, Accounting for Contract Services Requirement, has been added to the statement of work, and contractor is required to provide data on contractor manpower (including subcontractor manpower) for performance of this contract.
Instructions, including the Contractor and Subcontractor User Guides, are available at the CMRA (Contractor Manpower Reporting Application) website at:
https://cmra.army.mil. For further assistance, email the CMRA Help Desk at contractormanpower@hqda.army.mil.
NET AMT
Section C - Descriptions and Specifications
PERFORMANCE WORK STATMENT
SECTION C: DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
“Performance of Analytical Services Associated with Target Descriptions, Vulnerability, Survivability, Weapons Effectiveness Studies, and Support to Current Operations “
C.1. SCOPE.
C.1.1. Background. The Joint Technical Coordinating Group for Munitions Effectiveness
(JTCG/ME) is a joint service group whose mission is to provide the Services effectiveness data for fielded non-nuclear munitions. The U.S. Army Materiel Systems Analysis Activity
(AMSAA) supports the Army and the JTCG/ME with studies on the effectiveness of both fielded and developmental munitions. The JTCG/ME prepares and continuously updates Joint Munitions
Effectiveness Manuals (JMEM) for air-to-surface, surface-to-surface, antiair and other non-nuclear munitions systems (to include Non-lethal, Direct Energy and Information
Operations) including management of joint service efforts for associated data bases in target vulnerability, weapon characteristics and delivery accuracy. JTCG/ME is charged with establishing standardized procedures for important test factors such, as kill criteria, weapon lethalities, delivery accuracies, methodologies and data format for reporting new munitions effects into JMEM's. Weapon effectiveness calculations require a number of inputs such as weapon characteristics, weapon delivery accuracy and target vulnerability to specific damage mechanisms.
C.1.2. The contract is concerned with 1) the description and vulnerability of enemy targets to various damage mechanisms associated with conventional weapons such as fragments, blast, conical shaped charges, linear shaped charges, self-forging fragments, armor piercing projectiles, high explosive projectiles and others and 2) weapon system effectiveness analysis including:
methodology, computer simulation, data analyses, model verification and validation, documentation of models, systems effectiveness analyses and data base management systems. .
C.1.3. Objective. The objective of this contract is to obtain support in the areas of target descriptions, target vulnerability analysis, target survivability analysis, weapon system effectiveness and performance, data analysis, target disablement evaluation, component damage, warhead lethality, threat modeling, vulnerability/lethality methodology development and other areas.
C.2. APPLICABLE DOCUMENTS. Documents will be included in individual task orders as applicable.
C.2.1. Government Documents:
C.2.1.1. Army Regulation (AR) 25-2, Information Assurance, 23 March 2009.
(This document is available at: http://www.apd.army.mil/pdffiles/r25_2.pdf.)
C.2.1.2. AR 190-13, The Army Physical Security Program, 30 September 1993.
(This document is available at: http://www.fas.org/irp/doddir/army/ar190-13.pdf.)
C.2.1.3. AR 380-10, Foreign Disclosure and Contacts with Foreign Representatives, 22 June
2005 (available at: http://www.fas.org/irp/doddir/army/ar380-10.pdf).
C.2.1.4. Aberdeen Proving Ground Regulation (APGR) 190-4 (Change 2); Military Police, Movement Control within the Installation. (This document will be provided to the contractor when required by an individual task order.)
C.3 REQUIREMENTS.
C.3.1. Tasks. The Contractor, as an independent contractor and not as an agent of the
Government, shall provide the necessary resources (except those furnished by the Government) to accomplish tasks of the type set forth below:
C.3.1.1. Vulnerability Analysis and Assessments. The contractor shall:
C.3.1.1.1 Develop and provide drawings, target description, and computer models for a wide variety of vulnerability analyses, including details on all interior and exterior components and surfaces.
C.3.1.1.2. Provide detailed vulnerable area and kill probability data on selected targets using
Government-approved methodologies when considering a variety of damage mechanisms, with the analyses including a realistic treatment of multiple hits as well as single-hit considerations.
C.3.1.1.3. Provide vulnerability assessments for selected surface and air targets using approved methodologies when matched against a variety of damage mechanisms.
C.3.1.1.4. Update existing target descriptions and models to incorporate new or revised target information, changing threat potentials, and any known advances in weapon technology.
C.3.1.1.5. Develop hypothetical, physically-plausible models of generic target classes that permit rapid perusal of the target class. The target classes considered include both armored and "soft" targets ashore, afloat, and aloft.
C.3.1.1.6. Develop recommendations for reduction of ballistic threat vulnerability of domestic military equipment.
C.3.1.1.7. Apply vulnerability methodology and technology to enhance the survivability of domestic targets and weapons systems when exposed to various threats and damage mechanisms.
C.3.1.1.8. Conduct analyses of live-fire testing against simulated and actual targets to determine the penetration and behind armor debris characteristics produced by production, development, and conceptual weapons.
http://www.fas.org/irp/doddir/army/ar380-10.pdf
C.3.1.1.9. Develop vulnerability methodology (i.e., algorithms from test data, etc.) that can be applied to existing and developmental vulnerability assessment codes or tools.
C.3.1.2. Effectiveness Analysis and Performance Assessments. The contractor shall:
C.3.1.2.1. Conduct sensitivity studies in order to evaluate the impact of parameters such as target descriptions, warhead characteristics, component contribution, and methodology on estimates of target vulnerability and weapons effectiveness. Weapons effectiveness estimation may also include estimation of collateral damage.
C.3.1.2.2. Continue analysis of actual combat data to produce both summary and system-specific estimates of combat effectiveness.
C.3.1.2.3. Evaluate the psychological and psychophysical primary and secondary effects of various weapons, and estimate the contribution of these effects to system performance (i.e., to include collateral damage).
C.3.1.2.4. Conduct experiments and analyze data from firings against various target components and subcomponents and computerize these data for increased utility.
C.3.1.2.5. Characterize and develop simulations for the assessment of item/system performance
(including logistics) in a variety of standard and special scenarios to include the application of digitized terrain.
C.3.1.2.6. Develop capability to estimate reliability availability, maintainability and logistics support requirements under combat conditions on the basis of peacetime Proving Ground data and/or data from field or training exercises.
C.3.1.2.7. Develop methodology, test plans, data reduction procedures, data analysis and/or assess performance and effectiveness of US and foreign weapon systems and support systems
(e.g., aviation, air defense, armor, infantry, artillery, mines and barriers, command, control communication, intelligence, electronic warfare, non-lethal, directed energy, information operations, etc.). This could include countermeasure influence (and counter-countermeasure evaluations), evaluations of target acquisition, Chemical, Biological, Radiological, and Nuclear
(CBRN) evaluations, and delivery accuracy evaluations.
C.3.1.3. Test and Experiment Conduct and Support. The contractor shall:
C.3.1.3.1. Plan and conduct specialized weapons effects tests to verify computer-generated estimates of weapon outputs and/or target response.
C.3.1.3.2. Conduct detailed experimental investigations of various detonation processes, employing high-speed photographic techniques, including laser photography and digital instrumentation.
C.3.1.3.3. Conduct combined theoretical/experimental studies of various mechanical, electromechanical, and explosive components to arrive at component probability of kill given a hit (PK/H) and estimates of the performance capabilities of damaged components.
C.3.1.3.4. Prepare detailed plans for testing weapon systems.
C.3.1.3.5. Provide analysis and general support to testing programs.
C.3.1.3.6. Assess test-induced damage to targets and document in a standardized format.
C.3.1.3.7. Conduct and support vulnerability tests at remote locations.
C.3.1.3.8. Construct surrogate targets or components based on intelligence information or specifications.
C.3.1.3.9. Construct specialized test stands for munitions firing supporting of targets during tests.
C.3.1.3.10. In the event the contractor proposes use of Government test facilities, the contractor shall provide, in individual task orders, a commitment from the range and identify mechanisms that authorize use. Capabilities required at the experimental facilities may include, but are not limited to:
C.3.1.3.10.1. Dynamic firing of rounds of caliber up to 40 millimeters.
C.3.1.3.10.2. Static detonation of shaped charges up to 120 millimeters.
C.3.1.3.10.3. Bare charge high-energy explosive weights up to 500 pounds.
C.3.1.3.10.4. Launch of fragment simulators (i.e., 0 to 10,000 grains at velocities of 0 to 14,000 feet per second).
C.3.1.3.10.5. Diagnostics including velocity screens, orthogonal x-rays (at least four channels), and behind plate catch and recovery media.
C.3.1.4. Support to Current Operations, Publications, Databases, and Reporting. The contractor shall:
C.3.1.4.1. Identify data, materiel and/or capability gaps and deficiencies for current operations through all available sources. Identify and perform analytical efforts directed at potential solutions. Provide recommendations to expedite solutions to the Warfighter.
C.3.1.4.2. Prepare and edit documents and reports encompassing both technical and target descriptions of specified targets, as well as discussion and results of the particular vulnerability analyses conducted against these targets.
C.3.1.4.3. Develop and improve techniques for the testing and analysis of vulnerability/lethality of weapon systems.
C.3.1.4.4. Prepare test reports.
C.3.1.4.5. Prepare and present briefings on the overall programs and specific test results.
C.3.1.4.6. Analyze experimental data on behind armor effects of munitions or projectiles.
C.3.1.4.7. Develop automated databases and database management systems for item and system performance data for CD-ROM and/or web-based applications for both local area and/or wide area networks (LAN and/or WANs).
C.3.1.4.8. Develop and prepare for publication, on CD-ROM and other electronic media, comprehensive effectiveness information (text, figures, tables, drawings, photographs, data and computational tools) for collections of weapons systems against targets.
C.3.1.4.9. Perform review and modification of electronic publications of the JTCG/ME, to allow for their release to foreign countries under foreign military sales (FMS) and data exchange agreements (DEA).
C.3.1.4.10. Develop, update and standardize methodologies, translate them into computational tools, and accomplish their integration into generalized computational environments. Make recommendations to enhance such tools for various factors such as efficiency, speed and accuracy, and develop simplified approximation tools as are used, for example, in computational partitions of CD-ROM publications and/or web-based applications.
C.3.1.4.11. Conduct and document various activities in support of verification and validation of methodologies and data.
C.3.2. Meetings. The Contractor shall:
C.3.2.1. Participate in meetings when specified by the Government in individual task orders.
These meetings may take place at Aberdeen Proving Ground (APG), MD; Dahlgren, VA, Eglin
Air Force Base, FL or other locations specified by the Government in individual task orders.
C.3.2.2. Participate in technical meetings, including, as a minimum, project initiation meetings, design, test, or data reviews, meetings to discuss analytical requirements, meetings to support model verification and validation, meetings to present model or analysis results, and meetings with potential Government partners and customers.
C.3.2.3. Provide meeting support to include facilities, minutes, audiovisual and communications equipment as specified in an individual task order.
C.3.2.4. Participate in technical meetings in support of Government international cooperative research and development agreements. As directed by the Government, the Contractor may be required to prepare and present briefings to foreign nationals. The Contractor shall comply with
US export control laws and obtain any required Department of State or license(s) or exemption(s)
(either self-endorsed or certified by DoD).
C.3.3. Contractor‘s Working on a Government Site.
C.3.3.1. The Government will coordinate with the contractor‘s program manager for assignment of work tasks to on-site contractor personnel. The contractor support personnel working on-site shall:
C.3.3.3.1. Implicitly consent to Government searches, monitoring and surveillance, including audio and video recording of actions and conversations while entering and working on the
Government facility.
C.3.3.3.2. Wear a Common Access Card (CAC) or a DA Form 1602, Contractor Identification
Card, attached above the waist or on a lanyard around the neck at all times while in any controlled building or facility.
C.3.3.3.3. Label contractor workstations and offices with the employee‘s and company‘s name.
C.3.3.3.4. Identify themselves as a contractor when answering Government telephones.
C.3.3.3.5. Ensure all email has an auto-generated caveat in the name field that distinctly identifies the person as a contractor.
C.3.3.3.6. Not sign memoranda or other documents that in any way implies that they are making a decision on behalf of the Government.
C.3.3.3.7. Not attend meetings as the sole representative of AMSAA with the Department of the
Army (DA), Department of Defense (DOD), or other agencies.
C.3.3.3.8. Identify themselves as a contractor employee at the start of all meetings.
C.3.4. Security Requirements. Requirements contained in paragraphs C.3.4.1, C.3.4.2 and
C3.4.3 apply to this contract. All other requirements are specific to task orders performed at
AMSAA. Additional security and OPSEC requirements specific to other Government agencies may be issued by the COR, Alternate COR or Government Technical POC.
C.3.4.1. Facility Clearance. The contractor shall possess or be capable of obtaining a TOP
SECRET facility clearance as prescribed by DD Form 254, Contract Security Classification
Specification. Contractor performance may be at the contractor facility or the User Agency requiring the support. The contractor may receive, generate, and safeguard classified information up to the SECRET level at their facility. Contractor personnel may access classified information at Government or Contractor facilities as specified by the COR, Alternate COR, or Government
POC. Contractor personnel shall access SCI only at a US government facility or other contractor facility designated by the contract monitor.
C.3.4.2. Personnel Security Clearances. Contractor personnel performing under certain task orders may require access to TOP SECRET and Sensitive Compartmented Information (SCI).
All other contractor personnel designated to perform on this contract will require access to classified material up to and including SECRET.
C.3.4.3. Visit Notification/Authorization Request. A notification or visit authorization request shall be prepared and submitted to the appropriate Security Office via either hard copy or through the Joint Personnel Adjudication System (JPAS).
C.3.4.4. Information Technology (IT) Access. The contractor shall designate IT positions for all personnel requiring access to AMSAA IT systems in accordance with (IAW) paragraph 4-14, AR
25-2. The contractor shall request the appropriate personnel security investigation based upon the IT position designation. Access to government IT systems will not be granted until the basic requirements of paragraph 4-14a, AR 25-2 are validated by AMSAA Security Office personnel.
C.3.4.5. Reports of Adverse Information. The contractor shall report to the AMSAA Security
Manager all adverse information on contractor personnel such as security violations, arrests, bankruptcy, and denial, suspension, or revocation of security clearances. Employees may be denied access into APG restricted areas by the AMSAA Security Manager based upon the adverse information.
C.3.4.6. Installation Access. Aberdeen Proving Ground (APG) is a closed post. All vehicles and personnel are subject to search and seizure of contraband and unauthorized Government property in accordance with AR 190-13. All contractor personnel shall comply with the requirements of
APGR 190-4 for entry, exit, and internal control of personnel, material, and vehicles on APG.
C.3.4.7. Unescorted Access into Restricted Areas. Unescorted access into the APG restricted areas shall be granted to contractor personnel who possess a security clearance or were the subject of a favorable adjudicated National Agency Check (NAC) or FBI Fingerprint Check.
Unescorted access shall be authorized provided no more than 24 months have lapsed since the date of the termination of the security clearance or break of service and there is no known adverse information. The AMSAA Security Manager will serve as the approval authority for contractors nominated by the Contracting Officer‘s Representative (COR) or Alternate COR to have unescorted access into the restricted areas of APG. Contractors granted unescorted access into the restricted areas shall ensure they access only those government facilities approved by the
COR or Alternate COR. Contractors violating AMSAA and APG policies regarding access into the restricted area may have their unescorted access approval withdrawn on a temporary or permanent basis upon request of the AMSAA Security Manager, COR, or Alternate COR.
C.3.4.8. FBI Requests. The Contractor shall have completed an SSB Form 1199, Application for
Civilian ID Card/Security Badge, and FD 258, Application Finger Print Card, for each employee requiring unescorted access and not meeting one of the requirements in paragraph C.3.4.7. Upon contract award, the contractor shall obtain required forms from the COR and return the completed forms to the COR within ten (10) working days. Until a favorably adjudicated FBI
Fingerprint Check is obtained, Contractor personnel shall be continually escorted, into, out of, and within the restricted areas by other contractor personnel who possess a photographic security identification badge. Processing time for the FBI Fingerprint Check is approximately 45-60 days. The Contractor shall advise employees that the FBI Fingerprint Check shall be used to review criminal history records and that adverse information may result in an employee being denied access into the restricted areas.
C.3.4.9. Photographic Security Badges. Photographic security badges will only be issued to contractor personnel IAW APGR 190-4. Photographic security badges shall be approved and issued by AMSAA Security personnel to contractor personnel upon request from the COR and after the investigation or security clearance has been verified. Contractor personnel shall wear the photographic security badge at all times when in the restricted areas of APG. Contractors shall only escort visitors into the restricted area that have been approved by the COR or the
Alternate COR. Contractors violating AMSAA and APG policies regarding escorting requirements may have their photographic security badge confiscated on a temporary or permanent basis upon request of the AMSAA Security Manager, COR, or Alternate COR.
C.3.4.10. Common Access Cards. Common Access Cards (CAC) will be issued to contractor personnel nominated by the COR or Alternate COR for secure access to government information systems and networks. The contractor shall coordinate with the COR or Alternate COR to request and obtain a CAC via the automated Contractor Verification System (CVS).
C.3.4.11. Foreign Nationals and Immigrant Aliens. Foreign nationals or immigrant aliens cannot be granted access to classified or unclassified limited distribution information as identified by the
COR, and shall not be scheduled to perform work on Paragraph 3 tasks. When foreign nationals or immigrant aliens are visiting AMSAA, the contractor shall comply with AR 380-10.
C.3.4.12. Safeguarding Government Information and Property. The contractor shall be responsible for safeguarding all Government information and property provided for contractor use. The contractor shall safeguard information and material designated as classified, unclassified sensitive, For Official Use Only (FOUO), Operations Security (OPSEC) sensitive, and Privacy Act Information in accordance with applicable directives.
C.3.4.13. Loss or Possible Compromise of Classified Information. The contractor shall immediately report the loss or possible compromise of classified information or material to the
AMSAA Security Manager.
C.3.4.14. Security Training. The contractor shall develop and implement a security education program to ensure contractor personnel understand and are familiar with security requirements.
The contractor shall conduct security indoctrination training for all new employees within thirty
(30) days after their arrival, and refresher sessions annually thereafter. This training shall include general security education, Operations Security awareness, Information Assurance, Antiterrorism and training on Threat Awareness and Reporting Program (TARP). Contractor personnel shall complete Antiterrorism training IAW AR 525-13. Contractor personnel shall comply with threat awareness and reporting requirements IAW paragraph 1-14, AR 381-12.
C.3.4.15. Operations Security (OPSEC) Reviews. All material produced by the contractor which shall be disseminated outside of AMSAA shall be subject to an OPSEC and Security review to be performed by the AMSAA OPSEC Officer prior to release. This includes all written
(hardcopy) and electronic materials produced, such as organizational press releases and marketing material. The contractor shall submit to the AMSAA Security Manager any material proposed for public dissemination at least 10 days prior to its release. Only the material which has undergone an OPSEC and security review and has been approved by the AMSAA Security
Manager/OPSEC Officer shall be released in to the public domain.
C.3.4.16. Departing Employees. The contractor shall ensure all contractor employees process through the AMSAA Security Office to return issued security photographic badges, Common
Access Cards, keys, etc. to the Government at the completion of their employment. Contractor personnel may also be required to execute specific debriefing statements. In addition, the contractor shall notify the AMSAA Information Assurance Security Officer of their termination of employment to AMSAA/AKO accounts are deleted.
C.3.5. Reporting. The Contractor shall prepare and submit the following reports during the performance of this effort. Additional data requirements shall be in accordance with individual task orders.
C.3.5.1. Status Reports. The Contractor shall submit status reports IAW Exhibit Line Item
Number (ELIN) A001 of the Contract Data Requirements List, DD Form 1423. These reports shall summarize for the overall contract as well as individual task orders, all work performed during the designated month, work in progress, technical issues, and work scheduled for completion during the following month.
C.3.5.2. Technical Reports. The Contractor shall document all technical work performed for each task order and submit IAW ELIN A002. The Contractor shall submit a final report at the conclusion of the contract effort IAW ELIN A003.
C.3.5.3. Plan of Action and Milestone Schedule. The contractor shall develop a project milestone report that describes the plan of action and tracks key events for each task order.
C.3.6. Quality Control Plan.
C.3.6.1. The contractor shall be responsible for management and quality control actions necessary to meet the quality standards for the products and services set forth by the contract and individual task orders issued. The contractor shall implement and maintain the Quality Control
Plan (QCP) submitted with its proposal and IAW ELIN A005 to ensure services are performed in accordance with this Performance Work Statement (PWS). The contractor‘s quality control program shall verify and validate that the product development process is complete, is in compliance with contract requirements, and meets customer expectations. The contractor shall obtain Government approval prior to any proposed changes to its quality control program.
C.3.7. Performance Outcomes. The outcomes to be satisfied under this contract include high quality, cost effective analytical, engineering, technical, and management support services with adherence to schedule requirements. The Government will use the Quality Assurance
Surveillance Plan provided at Appendix A to Section C as the basis for assessing the contractor‘s performance.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
0002 Destination Government Destination Government
0003 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-4 Inspection Of Services--Fixed Price AUG 1996
52.246-5 Inspection Of Services Cost-Reimbursement APR 1984
Section F - Deliveries or Performance
TERM OF CONTRACT
The ordering period will commence on the specified effective date of the contract and continue for five (5) years. Individual task orders which are awarded during the ordering period may have a period of performance extending beyond the end of the ordering period, but will not exceed twelve (12) months in duration.
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 POP 01-APR-2013 TO
31-MAR-2018
N/A ABERDEEN PROVING GROUND
ABERDEEN PROVING GROUND
392 HOPKINS ROAD
ABERDEEN PROVING GROUND MD 21005
W23SR3
0002 POP 01-APR-2013 TO
N/A ABERDEEN PROVING GROUND
ABERDEEN PROVING GROUND
392 HOPKINS RD.
ABERDEEN PROVING GROUND MD 21005
0003 POP 01-APR-2013 TO
N/A (SAME AS PREVIOUS LOCATION)
52.242-15 Stop-Work Order AUG 1989
52.242-15 Alt I Stop-Work Order (Aug 1989) - Alternate I APR 1984
252.232-7006 Wide Area WorkFlow Payment Instructions JUN 2012
Section G - Contract Administration Data
PAYMENT OFFICES
The payment office will be determined and identified on a task order basis.
AMC-LEVEL PROTEST
If you have complaints about this procurement, it is preferable that you first attempt to resolve those concerns with the responsible contracting officer. However, you can also protest to
Headquarters, AMC. The HQ, AMC-Level Protest Program is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forum, rather than filing a protest with the Government Accountability Office or other external forum. Contract award or performance is suspended during the protest to the same extent, and within the same time periods, as if filed at the GAO. The AMC protest decision goal is to resolve protests within 20 working days from filing. To be timely, protests must be filed within the periods specified in FAR 33.103. If you want to file a protest under the AMC-Level Protest
Program, the protest must request resolution under that program and be sent to the address below. All other agency-level protests should be sent to the contracting officer for resolution.
Headquarters U.S. Army Materiel Command
Office of Command Counsel-Deputy Command Counsel
4400 Martin Road
Rm: A6SE040.001
Redstone Arsenal, AL 35898-5000
Fax: (256) 450-8840 or e-mail: amcprotests@conus.army.mil
The AMC-level protest procedures are located on the Internet. If Internet access is not available, contact the contracting officer or HQ, AMC to obtain the AMC-level protest procedures.
http://www.amc.army.mil//amc/commandcounsel.html mailto:amcprotests@conus.army.mil http://www.amc.army.mil/amc/commandcounsel.html
Section H - Special Contract Requirements
TASK ORDER CONTRACT TYPE
Task Orders may be written as either:
Firm-fixed price (FFP), or
Cost plus fixed fee (CPFF)
PREPARATION OF COST PROPOSAL
For CPFF task orders, the contractor shall submit a written cost proposal, based upon the tasks to be performed, providing the following as appropriate:
Number of hours by category of labor
Hourly rate of each labor category
List of materials/equipment with copy of supplier quotes
Travel requirements (including number & locations of trips, mode of transport, per diem, etc.
TASK ORDER PROCEDURES
Task orders can be categorized into four (4) groupings, as listed below. The determination of which grouping any individual task order falls within is a business decision based upon the requirements of the individual task order (i.e., nature, scope, complexity and other factors as deemed appropriate for the action) made at the Governmen‘s discretion. This determination is the Contracting Officer‘s decision, and will not be subject to the Disputes clause.
―Vulnerability Analysis and Assessments‖
―Effectiveness Analysis and Performance Assessments‖
―Test and Experiment Conduct and Support‖
―Support to Current Operations, Publications, Databases, and Reporting‖
Task orders under the ―Vulnerability Analysis and Assessments‖ grouping will be set-aside for small businesses IAW FAR 9.502-2(b) when applicable.
Task orders under the other three groupings will be competed among all ID/IQ holders on an
―unrestricted‖ basis.
The procedure for establishing task orders will be as follows:
a. After making the determination described above, the Contracting Officer will forward a
Request for Task Order Competition (RTOC). The RTOC will provide each contractor in the competition the Performance Work Statement (PWS) describing the requirements and objectives of the task, whether the task is firm fixed price (FFP) or cost plus fixed fee
(CPFF), and all other applicable documents (Wage Rates, DD Form 254, appropriate reference materials, Government Furnished Material, etc). The RTOC will set forth a task accomplishment schedule, describe any report requirements, and set forth other information and data as necessary for task accomplishment. Additionally, the RTOC will provide all evaluation factors, their importance and any considerations under cost technical trade determination, best value definition (low cost/technically acceptable or tradeoff), establish a closing date for the completion of the Task Order and any other pertinent information required for the fair competition of the requirement.
b. The Contractor shall furnish a Task Order Execution Proposal (TOEP) to the Contracting
Officer within the timeframe specified within the RTOC. The TOEP shall include the contractor‘s proposed approach and understanding of the work required; a description of the work to be accomplished; the proposed schedule and required deliverables (if applicable), and a clear explanation of any constraints which would impact the successful completion of the order. The TOEP will provide a proposed price (for FFP task orders) or cost (for CPFF task orders), and may require submittal of Other Than Certified Cost and Pricing Data IAW FAR 15.403-3.
c. Assignment of Task Orders:
1) Upon receipt of the plan, the TOEP will be reviewed and evaluated by the Task Order
Technical Evaluation Board to ensure acceptability to the Government. The Contracting
Officer may enter into discussions with the contractors if necessary.
2) A task order will be awarded to the Contractor with the best proposal and price in accordance with the evaluation factors and cost technical trade off language in the RTOC
(or lowest priced/technically acceptable offer, if applicable).
FAIR OPPORTUNITY
Pursuant to DFARS 216.505-70(b), task orders exceeding $150,000.00 shall be placed on a competitive basis unless an allowable exception to the fair opportunity process applies and is determined to be in the Government‘s best interest. The allowable exceptions set forth in FAR
16.505(b)(2) and DFARS 216.505-70(b)(2) are synopsized below:
Urgency
Sole source due to unique or specialized nature of the requirement and only one awardee is capable of providing support at the required level of quality
Sole source based on the interest of economy and efficiency, i.e., a logical follow-on to an order already placed under the requirement
Required to satisfy a minimum guarantee
Expressly authorized by statute for award to a specified source
APPLICABLE WAGE DETERMINATION
Applicable Wage Determinations shall be provided with all Task Orders that are subject to the
Service Contract Act (SCA).
The Contractor shall comply with the Service Contract Act and related clauses when task order requirements are covered by the SCA.
CLAUSES INCORPORATED BY FULL TEXT
INSURANCE REQUIREMENTS (NOV 2006)
The following insurance is required as a minimum in accordance with the Federal Acquisition Regulations and the appropriate clause in Section I:
a. Legally Required Insurance: Where certain laws apply, such as state laws governing workman‘s compensation and employer‘s liability coverage, etc., the contractor, prior to commencement of work, shall furnish the Contracting Officer a written statement that such laws have been complied with and that compliance will continue throughout the period of contract performance. Minimum coverage of $100,000 is required.
b. Comprehensive General Liability and Automobile Liability:
Per Property
Each Person Occurrence Damage
Comprehensive None $500,000 None
General Liability
Automobile Liability $200,000 $500,000 $20,000
GOVERNMENT-CONTRACTOR RELATIONSHIPS (NOV 2006)
a. The Government and the contractor understand and agree that the services to be delivered under this contract by the contractor to the Government are non-personal services and the parties recognize and agree that no employer-employee or master-servant relationships exist or will exist under the contract between the Government and the contractor and/or between the Government and the contractor‘s employees. It is therefore, in the best interest of the Government to afford the parties a full and complete understanding of their respective obligations.
b. Contractor personnel under this contract shall not:
(1) be placed in a position where they are appointed or employed by a Federal Officer, or are under the supervision, direction, or evaluation of a Federal Officer, Military or Civilian.
(2) be placed in a staff or policymaking position.
(3) be placed in a position of command, supervision, administration or control over DA Military or
Civilian Personnel, or personnel of other contractors, or become a part of the Government organization.
(4) be used for the purpose of avoiding manpower ceilings or other personnel rules and regulations of
DA or the Civil Service Commission.
(5) be used in administration or supervision of military procurement activities.
c. Employee Relationship:
(1) The services to be performed under this contract do not require the contractor or its employees to exercise personal judgment and discretion on behalf of the Government, but rather the contractor‘s employees will act and exercise personal judgment and discretion on behalf of the contractor.
(2) Rules, regulations, directions, and requirements that are issued by command authorities under their responsibility for good order, administration, and security are applicable to all personnel who enter the installation, or who travel on Government transportation. This is not to be construed or interpreted to establish any degree of
Government control that is inconsistent with a non-personal services contract.
U.S. GOVERNMENT-FURNISHED SPACE AND UTILITIES PROVIDED TO
CONTRACTORS (AUG 1999)
a. The Government shall not be obligated in any way for the connect or disconnect of contractor trailers to
Government utilities (water, sewage and electric service).
b. The Contractor shall, at contractor‘s expense, install, maintain and operate all new facilities required for obtaining service, including suitable metering and regulation equipment and service connections to the Government‘s utility system.
c. Plans for all such facilities shall be subject to the approval of the Chief, Engineering Plans and Services division (EPSD), Directorate of Public Works (DPW). The installation of such facilities shall be subject to the approval of the Chief, Buildings, Grounds and Utilities Division, DPW.
d. The Contractor shall reimburse the Army for the utility service at local prevailing rates.
e. The meter(s) will be read by the Aberdeen Area or Edgewood Area Maintenance Branch, BG&U
Division, DPW and bills will be rendered monthly to the Contractor by the Government. All such bills shall be due and payable 15 days after receipt thereof by the Contractor.
H5. CONTRACTOR‘S ORGANIZATION AND KEY PERSONNEL
a. The contractor's organization shall be established with authority to effectively accomplish the objectives of the Statement of Work. This organization shall become effective upon award of the contract and its integrity shall be maintained for the duration of the contract effort.
b. The key personnel listed in paragraph c below are considered to be critical to the successful performance of this contract. Prior to replacing these key personnel, the contractor shall obtain the written consent of the contracting officer. In order to obtain such consent, the contractor shall provide advance notice of the proposed changes and shall demonstrate that the qualifications of the proposed substitute personnel are generally equivalent to or better than the qualifications of the personnel being replaced.
c. Key Personnel List
NAME POSITION
d. Prior to permanently reassigning any of the specified individuals to other contracts, the contractor shall provide the Contracting Officer not less than thirty (30) days advance notice and shall submit justification (including proposed substitutions) in sufficient detail to permit evaluation of the impact on the program. No reassignment shall be made by the Contractor without written consent of the Contracting Officer. The "Key Personnel" list may be amended from time to time during the course of the contract to either add or delete personnel, as appropriate.
H6. ORGANIZATIONAL CONFLICT OF INTEREST
a. Due to the nature of this contract, OCI implications will be reviewed on an individual Task Order basis, prior to the issuance of each Task Order. Each situation will be examined on the basis of its particular facts and the nature of the proposed support/services/deliverables. The exercise of common sense, good judgment and sound discretion will be employed in determining whether a significant potential conflict exists and, if it does, the development of an appropriate means for resolving it. The two underlying principles are-
- preventing the existence of conflicting roles that might bias a contractor‘s judgment
- preventing an unfair competitive advantage
b. Perspective offerors are invited to review Federal Acquisition Regulation Subpart 9.5 ―Organizational and Consultant Conflicts of Interest.‖ Particular attention is directed to FAR 9.505, 9.505-1, 9.505-2, 9.505-3 and
9.505-4.
c. The effort to be performed under this contract may require the contractor to support the development of system requirements/specifications, provide system engineering and technical direction, and/or recommend products/capabilities. As such, the contractor may not (1) be awarded a contract to supply the system, product, capability or components, or (2) be a subcontractor or consultant to a supplier of the system or any major component on which provides support hereunder. However, the contractor may participate (i) on a noncompetitive basis under a prime contract with the Government or (ii) with the written approval of the Contracting Officer. This restriction shall be effective through a period ending one (1) year following completion of performance under the specific task order where the potential conflict has been identified.
d. The effort to be performed under this contract may require access to the proprietary information from other companies and consequently creates a potential significant conflict of interest. It is the intention of the
Government to prevent creation of an unfair competitive advantage as a result of knowledge gained through access to proprietary information. Consequently, when access to proprietary information of other companies is required, the contractor shall (1) enter into a written agreement with the other company(ies) to protect their proprietary information from unauthorized use or disclosure for as long as it remains proprietary; and (2) refrain from using such proprietary information for any purpose other than providing advisory and assistance service to the Government under this contract. In addition, the contractor shall (1) inculcate upon its employees, through appropriate means, such formal training and promulgation of company policies and procedures, the principles of FAR Subpart 9.5, so that employees will refrain from using or disclosing proprietary information except as provided herein; and (2) obtain from each of its employees whose responsibility in connection with the work under this contract may be reasonably expected to involve access to such proprietary information, a written agreement, which in substance shall provide that such employee will not, during his employment by the contractor or thereafter, disclose to other than the contractor's employees or sponsor, or use for the employee's own benefit or the future benefit of any other individual, corporation, or organization any such proprietary information to which the employee had access in connection with the work under the contract. An executed copy of all proprietary information agreements shall be furnished to the
Contracting Officer within fifteen (15) calendar days of execution. The contractor shall hold the Government harmless and indemnify the Government as to any cost/loss resulting from the unauthorized use or disclosure of third party proprietary information by the contractor, its employees, subcontractors, or agents.
e. For breach of any of the above restrictions or disclosure or misrepresentation of any relevant facts required to be disclosed concerning this contract, the Government may terminate this contract for default, disqualify the contractor for subsequent related contractual efforts, and pursue such other remedies as may be permitted by law or this contract. If, however, in compliance with this clause, the contractor discovers and promptly reports an organizational conflict of interest (or potential thereof) subsequent to contract award, the Contracting Officer may terminate this contract for convenience if such termination is deemed in the best interest of the Government.
f. The contractor shall include a clause which includes paragraphs a. in all subcontracts. Likewise, a clause which includes paragraph b. and c. shall be included in all subcontracts which may require access to proprietary information of other firms. When the above paragraphs are included in a subcontract, the term "Contracting Officer" shall represent the head of Contracts Office of the prime contractor.
Section I - Contract Clauses
MULTIPLE TASK ORDER CONTRACT
MULTIPLE AWARD TASK ORDER CONTRACT AND DELIVERY ORDER CONTRACT
OMBUDSMAN (MAR 2009)
a. In accordance with FAR 16.505(b)(5), the following individual has been appointed as ombudsman for multiple award task order and delivery order contracts issued by this organization:
Mr. Dennis Longo
Army Contracting Command - APG
4118 Susquehanna Avenue
Aberdeen Proving Ground, MD 21005-3013
Telephone: (443) 861-5087 dennis.p.longo.civ@mail.mil
b. The ombudsman has the authority to review contractor complaints that they have not been afforded fair opportunity to be considered for award of a particular task order or delivery order under a multiple award contract.
c. A contractor who…