411TH CSB, KOREA - HUMP CONTRACTING DIV

POC: MS. YIM, UN SONG

TEL: 0503-355-3370

UNSONG.YIM.LN@ARMY.MIL

APO AP 96271

UNITED STATES

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SEE NEXT PAGE.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Nov-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91QVN23R0011

X 9B. DATED (SEE ITEM 11)

08-Nov-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Nov-2022

CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

HUMPHREYS CONTRACTING DIVISION

UNIT 15289

APO AP 96271-5584

UNITED STATES

W91QVN 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W91QVN

FACILITY CODECODE

EMAIL:TEL:

W91QVN23R0011

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT #0001

1. The purpose of this amendment is to answer the questions received and post power point slides for construction materials.

QUESTION & ANSWER

No. QUESTION ANSWER 1 Item 1: Shipping Container, 20ft

a. Any register the container, if so, please provide information.

b. Any mark outside container like container #, maximum weight, the size limit of capability and more

c. Any other request

a. NO

b. No data plate specifically needed.

c. Prefer something that is airtight to reduce the elements from deteriorating or rusting the goods inside. Since it will be locked and stored.

2 Item 4: Barbed wire strand

What would be LENGTH & GAUGE?

Each role is usually 1,320 feet in Length.

4point 12 1/2 Gauge

3 Item 8: Picket pounder

Which one should choose -Two types available 28.7lb H23.6" ID 5.9” or 34lb H23.6 ID 6.14"?

34lb H23.6 ID 6.14”

4 Item 9: Mechanical Tanker Tool Bag Ordinance

Can we support Available 19”X6”X9” or must need 19”x6”x7”?

19”X6”X9” is fine

5 Item 11: Sleep Mat

Acceptable US Standard size 182 X 60 (72" x 24") Foam sleeping pad or must need 188 x 60 cm?

US Standard size 182 X 60 (72" x 24") Foam sleeping pad is acceptable.

6 Item 15: Concrete screw bolt/nut set w/ cap

What would be SCREW SIZE (length & diagram)

Diameter: 3/8” Length: 3”

7 Item 16: Rolled chain link fencing

Changed from EA to FOOT Total length = 2,100 ft

W91QVN23R0011

Is unit EA -> FOOT? This will be 9Gauge (Standard).

8ft h x 50 ft w 9 gauge, 2’ mesh

8 Item 23: Aluminum wire fence tie

9 gauge Aluminum has INDIVIDUAL TIE (What would be quantity, ONLY GALBANIZED Steel has a roll. What would be total length? (1500m?)

1,500M Galvanized Steel roll at 6-9 gauge

9 Can we purchase a few items in Korea or must all items purchase need in USA?

Yes, can purchase from ROK.

10 Item No. 15: Concrete screw bolt/nut set w/ cap

If a steel screw bolt/nut is set with a cap, please provide the size and material of the subject equipment.

See No 6. on this list

Material: Steel to secure base plates into concrete floor. see NO. 6 for same question.

11 Item No. 16: Rolled chain link fencing

Is it a mesh net?

No, this is metal chain link fencing 9 guage. Just like what goes around the airfield or in all the COF cages.

12 Item No. 17: Pole

If it is a pole when constructing a fence, should the plate be attached to the relevant pole? Is it galvanized or painted?

Galvanized with plate attached to pole

13 Item No. 19: Hinged Cage Door

Is it a locking device related to the fence, or is it a subsidiary material related to the fence construction?

It would be a locking door/gate that would close and can be locked from the outside of the cage/ fence to keep items secured inside the individual cages.

2. All other terms and conditions remain unchanged.

(End of Summary of Changes)