GENERAL NOTE

A. REPAIR/MAINTENANCE (K-WORK)

QTYITEM D E S C R I P T I O N

KIM, SM

MECHANICAL

NTS

SYMBOL BY

DESIGNED BY

ENERGY MANAGER

SUBMITTED BY

USING AGENCY

APPROVED BY

PROJECT NO. DRAWING NO. REF NO.

SCALE :

ZONE DATE APVD.

UTILITIES

SHEET OF

REVIEWED BY

DESCRIPTION

BLDGS & GROUNDS

CHIEF, ENGR'G DIV

DES

CHK'D

REVISIONS

IMCOM

FIRE & EMERGENCY SVC

SAFETY

ENVIRONMENT

UNIT #15333, APO AP 96205-5333

ENGINEERING DIVISON, DPW, USAG-YONGSAN

HEADQUARTERS, UNITED STATES ARMY GARRISON, YONGSAN

US ARMY INSTALLATION MANAGEMENT COMMAND

DEPARTMENT OF THE ARMY

A

B C D

E F G H

& EQUIPMENT SCHEDULES

GENERAL NOTES, SCOPE OF WORKS

SUBMERSIBLE PUMP

SP

NOTE :

203473

21 M-1

SCOPE OF WORK (MECHANICAL & ELECTRICAL)

E Q U I P M E N T S C H E D U L E

REPAIR STORM DRAINAGE SYSTEM, K16

FY19

MOTOR

DISCHARGE SIZE

CAPACITY

: 1,150 RPM

: 60 HP (6P), 460V, 3Ph, 60Hz.

: 400 mm

: 5,548 GPM @23 FT TDH.

MODEL NO. SHINHAN, SH-14-450E OR APPROVED EQUAL.

SAFETIES & OPERATING ACCESSORIES.

DETECTOR), CONTROL PANEL AND ALL COMPONENTS, STATIONARY CRANE, AND ALL NECESSARY

CHAIN, LEVEL SENSOR, MONITORING UNIT (MOTOR TEMPERATURE SENSING DEVICE & LEAKAGE

MOTOR, EQUIPPED WITH MECHANICAL SEAL, AUTOMATIC DESORPTION DEVICE, STS304 LIFTING

STS410 STAINLESS STEEL ONE PIECE MOTOR SHAFT, STS304 BOLTS & NUTS, NON OVERLOADING

VERTICAL MOUNTED SUBMERSIBLE PUMP, NON-CLOG TYPE IMPELLER, SSC13 CASING & IMPELLER, CONDUITS, AND ALL ASSOCIATED ACCESSORIES AS SHOWN ON DRAWINGS.

WITH NEW 500 KVA TRANSFORMER AND INSTALLING NEW 600A ENCLOSURES CIRCUIT BREAKER, WIRES,

2. REPAIR DETERIORATED EXISTING ELECTRICAL POWER SYSTEM BY REPLACING EXISTING TRANSFORMER

CONC. PADS, AND ALL ASSOCIATED ACCESSORIES AS SHOWN ON DRAWINGS.

PANEL AND ALL COMPONENTS, CRANE, GUIDE RAIL, PIPES, VALVES, WIRES, CONDUITS, CONTROLS, PUMPS (2 SET), AUTOMATIC DESORPTION DEVICE, LEVEL SENSORS, MONITORING UNIT, CONTROL

1. REPAIR EXISTING STORM DRAINAGE SYSTEM BY INSTALLING NEW 60HP VOLUTE TYPE SUBMERSIBLE

10. SALVAGEABLE MATERIALS SHALL BE RETURNED TO DPW.

KEEP THE ROOMS CLEAN DURING CONSTRUCTION.

9. THE CONTRACTOR SHALL PROVIDE, INSTALL, AND REMOVE CONSTRUCTION BARRICADES AND/OR PROTECTION TO

AND THE LIKE SHALL BE DONE BY THE CONTRACTOR AT NO ADDITIONAL COST TO THE U.S. GOVERNMENT.

8. DISPOSAL OF CONSTRUCTION DEBRIS, WASTE MATERIALS, MATERIALS RESULTING FROM DEMOLITION ACTIVITIES, CEILING, ROOF, PIPE, DUCT, EQUIPMENT AND ELECTRICAL ITEMS.

ADDITIONAL COST TO THE GOVERNMENT, INCLUDING, BUT NOT NECESSARILY LIMITED TO ITEMS SUCH AS WALLS, NECESSARY TO ALLOW FOR INSTALLATION AND REPLACEMENT OF MECHANICAL AND FIRE ALARM SYSTEM AT NO

7. THE CONTRACTOR SHALL BE RESPONSIBLE FOR REMOVAL AND REINSTALLATION OF ALL OBSTRUCTIONS AS

BY THE CONTRACT SPECIFICATIONS.

WHICH MAY DEVIATE FROM THAT SHOWN ON CONTRACT DRAWINGS SHALL BE SUBMITTED FOR APPROVAL AS REQUIRED

ALL FUNCTIONAL REQUIREMENTS SHOWN ON DRAWING. SHOP DRAWINGS OF THE ACTUAL PROPOSED CONTROL SYSTEM

6. THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING A COMPLETE AND WORKABLE CONTROL SYSTEM TO SATISFY

SPECIFICATIONS FOR MISCELLANEOUS PROJECTS, KOREA.

ACCORDANCE WITH APPLICABLE SECTIONS OF DIVISION 22 & 23 - MECHANICAL. O & MA STANDARD TECHNICAL

5. ALL MECHANICAL SYSTEMS SHALL BE TESTED, ADJUSTED AND BALANCED BY THE CONTRACTOR IN STRICT

TO THE U.S. GOVERNMENT.

THE DETAILS WILL BE UTILIZED WHILE PERFORMING THE MECHANICAL SCOPE OF WORK AT NO ADDITIONAL COST

4. FOR O & MA PROJECTS, KOREA, OCTOBER 1, 2003 DEPARTMENT OF THE ARMY FORM AS A PART OF THIS PROJECT.

SUBMITTED TO THE CONTRACTING OFFICER FOR APPROAL.

SHALL BE PREPARED IN THE FIELD BY THE CONTRACTOR ACCORDING TO ACTUAL FIELD CONDITIONS AND

3. SOME DETAILS SHOWN ON THIS CONTRACT DRAWINGS MAY NOT MATCH EXACT FIELD CONDITIONS. SUCH DETAILS

BY THIS PROJECT AND TO MATCH CONDITION TO ADJACENT AREAS AS DIRECTED BY THE CONTRACTING OFFICER.

2. THE CONTRACTOR SHALL BE RESPONSIBLE TO CONSTRUCT OR REPAIR ALL DAMAGES TO EXISTING AREAS CAUSED

EQUIPMENT & SERVICE CLEARANCE, EQUIPMENT PAD SIZE, INSTALLATION LOCATIONS, AND ADDITIONAL ITEMS.

1. THE CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING ALL EXISTING CONDITIONS FOR NEW WORK SUCH AS

WITH MECHANICAL EQUIPMENT MANUFACTURER'S RECOMMENDATIONS.

6. EXACT RATINGS AND SETTINGS OF ELECTRICAL EQUIPMENT AND DEVICES SHALL BE IN ACCORDANCE

CRITERIA & CONTRACT SPECIFICATIONS.

ELECTRICAL CODE, NATIONAL ELECTRICAL SAFETY CODE, LIFE SAFETY CODE, UNIFIED FACILITIES

5. ALL ELECTRICAL WORK SHOULD BE DONE IN ACCORDANCE WITH THE CURRENT EDITIONS OF NATIONAL

AND ALL NECESSARY ACCESSORIES FOR CONTROL WORK.

4. THE CONTROLS CONTRACTOR SHALL PROVIDE ALL THE WIRINGS, RELAYS, CONTROLLERS, CONDUITS

BY GOVERNMENT.

3. CONTRACTOR SHALL SUBMIT PUMP & CONTROL PANEL INSTALLATION SHOP DRAWINGS FOR APPROVAL

COMPLIANCE WITH MANUFACTURER'S SPECIFICATION BY A LICENSED OR CERTIFIED INSTALLER.

2. INSTALLATION OF THE SUBMERSIBLE PUMP SYSTEM INCLUDING CONTROL PANEL SHALL BE IN

SERVICE CLEARANCE, EQUIPMENT PAD SIZE, INSTALLATION LOCATIONS, AND ADDITIONAL ITEMS.

1. THE CONTRACTOR SHALL VERIFY EXISTING CONDITIONS FOR NEW WORK SUCH AS EQUIPMENT &

KEY PLAN

N

W A

L

W

F E

N C

E

W A

F E

N C

E

WALL W/FENCE

RETAINING WALL

RETAINING WALL

W

H 147' LINE

WALL W/FENCE

RETAINING WALL

508 505

UNK1 UNK2 UNK3 UNK4 UNK5 UNK6 UNK7 UNK8 UNK9 UNK10 UNK11 UNK12

UNK13

UNK14

U N

K

UNK16

UNK17

UNK18

UNK19

UNK20

127128

212213214

W A

F E

N C

E

WALL W/FENCE

RETAINING WALL

RETAINING WALL

W

H 147' LINE

WALL W/FENCE

RETAINING WALL

W A

F E

N C

E

SEWAGE

LIFT

STATION

W A

F E

N C

E

WALL W/FENCE

RETAINING WALL

RETAINING WALL

SEWAGE

TREATMENT

PLANT

W

H 147' LINE

WALL W/FENCE

RETAINING WALL

W A

F E

N C

E

SCALE: 1:100

0 2000 4000

GRAPHIC SCALE

KIM, SM

MECHANICAL

SYMBOL BY

DESIGNED BY

ENERGY MANAGER

SUBMITTED BY

USING AGENCY

APPROVED BY

PROJECT NO. DRAWING NO. REF NO.

SCALE :

ZONE DATE APVD.

UTILITIES

SHEET OF

REVIEWED BY

DESCRIPTION

BLDGS & GROUNDS

CHIEF, ENGR'G DIV

DES

CHK'D

REVISIONS

IMCOM

FIRE & EMERGENCY SVC

SAFETY

ENVIRONMENT

UNIT #15333, APO AP 96205-5333

ENGINEERING DIVISON, DPW, USAG-YONGSAN

HEADQUARTERS, UNITED STATES ARMY GARRISON, YONGSAN

US ARMY INSTALLATION MANAGEMENT COMMAND

DEPARTMENT OF THE ARMY

A

B C D

E F G H

203473

21 M-2

REPAIR STORM DRAINAGE SYSTEM, K16

FY19

1 STORM WATER PUMP STATION PLAN

SACLE = 1:100

N

3PH, 500KVA

TYPE TRANSFORMER

NEW PAD MOUNTED

DTR

S -5

T -5

S -5

.4

M W C

O N

C D

IT

C H W

S T

E E

L G

R A

T

IN

G S

S -5

C O

N T

A

IN

E R B

O X

B O

X

C O

N T

A

IN

E R

B O

X

C O

N T

A

IN

E R

TO REMAIN

SAFETY SWITCH

TRANSFORMER &

EXISTING DRY TYPE

PVC CONDUIT

8#3/0 IN 78dia

NEW U/G SEC LINE

NEMA 3R, 600A

CIRCUIT BREAKER

NEW ENCLOSURES

M2

- M3

SEE

FOR ENLARGED PLAN

M3

STORM WATER PUMP STATION PLAN

1:100

W/ CONC. PAD

SUBMERSIBLE PUMPS

(NEMA 4X) FOR

NEW CONTROL PANEL

SP

KIM, SM

MECHANICAL

203473

21 M-3

REPAIR STORM DRAINAGE SYSTEM, K16

FY19

3,000450 300

10,900

300 3,000 4501,0002,400

,9

,0

N

M3 SACLE = 1:50

SPLASH BLOCK

CONCRETE

1,200x2,400x200

(TYP OF 2)

CHECK VALVE

STORM WATER PIPE

M3-

(TYP OF 2)

FLEXIBLE JOINT

(TYP OF 2)

SUBMERSIBLE PUMP

DEVICE (TYP OF 2)

AUTOMATIC DESORPTION

STORM WATER TANK

450 450

4,900

4,000

GL. APP.+18.20

- M3 SACLE = 1:50

STORM WATER PUMP STATION ENLARGED PLAN

STORM WATER PUMP STATION ENLARGED SECTION

SCALE: 1:50

0 1000 2000

GRAPHIC SCALE

ENLARGED PLAN & SECTION

STORM WATER PUMP STATION

1:50

SPLASH BLOCK

CONCRETE

1,200x2,400x200

STORM WATER PIPE

LEVEL SENSOR (TYP.)

GUIDE PIPE

80MM SST

SP

(TYP OF 2)

SUBMERSIBLE PUMP

DEVICE (TYP OF 2)

AUTOMATIC DESORPTION

(5,000mmH x 3,000L)

SUBMERSIBLE PUMPS

CRANE FOR LIFTING

(5,000mmH x 3,000L)

SUBMERSIBLE PUMPS

CRANE FOR LIFTING

(TYP OF 2)

CHECK VALVE

(TYP OF 2)

FLEXIBLE JOINT

WITH FENCE

RETAINING WALL

EXISTING

COORDINATION WITH DPW CIVIL ENGINEER.

ACCORDANCE WITH TEST OPERATION AND

INSTALLATION SHALL BE DETERMINED IN

NOTE : THE LOCATION & QUANTITY OF LEVEL SENSOR

SYMBOL BY

DESIGNED BY

ENERGY MANAGER

SUBMITTED BY

USING AGENCY

APPROVED BY

PROJECT NO. DRAWING NO. REF NO.

SCALE :

ZONE DATE APVD.

UTILITIES

SHEET OF

REVIEWED BY

DESCRIPTION

BLDGS & GROUNDS

CHIEF, ENGR'G DIV

DES

CHK'D

REVISIONS

IMCOM

FIRE & EMERGENCY SVC

SAFETY

ENVIRONMENT

UNIT #15333, APO AP 96205-5333

ENGINEERING DIVISON, DPW, USAG-YONGSAN

HEADQUARTERS, UNITED STATES ARMY GARRISON, YONGSAN

US ARMY INSTALLATION MANAGEMENT COMMAND

DEPARTMENT OF THE ARMY

A

B C D

E F G H

KIM, SM

MECHANICAL

NTS

SYMBOL BY

DESIGNED BY

ENERGY MANAGER

SUBMITTED BY

USING AGENCY

APPROVED BY

PROJECT NO. DRAWING NO. REF NO.

SCALE :

ZONE DATE APVD.

UTILITIES

SHEET OF

REVIEWED BY

DESCRIPTION

BLDGS & GROUNDS

CHIEF, ENGR'G DIV

DES

CHK'D

REVISIONS

IMCOM

FIRE & EMERGENCY SVC

SAFETY

ENVIRONMENT

UNIT #15333, APO AP 96205-5333

ENGINEERING DIVISON, DPW, USAG-YONGSAN

HEADQUARTERS, UNITED STATES ARMY GARRISON, YONGSAN

US ARMY INSTALLATION MANAGEMENT COMMAND

DEPARTMENT OF THE ARMY

A

B C D

E F G H

203473

21 M-4

REPAIR STORM DRAINAGE SYSTEM, K16

FY19

1 PUMP MATERIAL DETAIL

NOT TO SCALE

- NOT TO SCALE

CONTROL PANEL MATERIAL DETAIL & DIMENSION

FRONT VIEW SIDE VIEW

NO Q'TY

1EA

TERMINAL

SOFT START

3EA

3EA

3EA

3EA

7 3EA

8 1EA

2EA

1EA

3EA

2EA

1EA

2EA

1EA

1EA

1EA

12EA

1EA

1EA

1EA

INNER FRONT VIEW

FAN

50x50x6T

ANGLE

50x50x6T

ANGLE

1 2

8 9 10 11 18

13 1521

12 17 14 19

16 20 24

DESCRIPTION SPECIFICATION REMARK

UL-LISTED 1EA

1EA

1EA

2EA

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

UL-LISTED

1EA

120mm

AC 110V/25mm

MCCB-HANDLE

POWER LAMP

HOUR METER

S/SW

PBL

PBL

PBL

MAIN MCCB

MOTOR CIRCUIT BREAKER

FOR CONTROL

460V/55KW

80W

FOR POWER

11v/4ab

10 POINT

2P/20A

0-60C

DMIN-WH61

25L2-11

25WML1CR11(R)

25WML1CR11(G)

25WML1CR11(Y)

3P-225A

3P-100A

2P-15MOTOR CIRCUIT BREAKER

CIRCUIT BREAKER

3POLE CONTACTOR

3POLE CONTACTOR

MONITORING UNIT

VOLTAGE RELAY

TRANSFORMER

LEVEL CONTROLLER

TIC CONTROLLER

OUTLET

GROUND

RELAY

TERMINAL

HEATER

5P

200V/110V/150VA

2PH/200V

153-MPU

LC1-D15

LC1-D25

1P/2A

200 200 200 200 200 200

900 500 900

3. TYPE : OUTDOOR 4. Q'TY : 1 SET

1. MATERIAL : STS 304 2. NEMA 4X

NOTE;

DIMENSION

6312ZZ

MOTOR FRAME

PUMP CASING

SUCTION COVER

BEARING COVER

BEARING HOUSING

MOTOR SHAFT

OIL SEAL

IMPELLER

STS410

N.B.R

CAB TYRE CABLE

NAME OF PARTS

STUFFING BOX

UPPER BEARING

MOTOR BRACKET

NO

STB2

MATERIAL

8M

Q'TY

1EA

STS304EYE BOLT M20

SSC13

PNCTx16SQx7C

1EA

1EASSC13

SSC13 1EA

1EA

SSC137 1EA

8 1EASSC13

10 70x 90x11 1EA

1EASSC13

1EASSC13

1EASSC13

N.B.R15 1EAPROTECTED

4EA16

SIC : SILICON CARBIDE

N.B.R : NITRILE-BUTADIENE RUBBER

ABBREVIATIONS;

DIMENSIONNAME OF PARTSNO MATERIAL Q'TY

S-60

SIC/SIC

TURBINE OIL

STS304(80A)

OIL BOLT

GUIDE PIPE

GUIDE SUPPORT

DUCK FOOT BEND

ROTOR

STATOR

PIPE FLANGE

MECHANICAL SEAL

LOWER BEARING

OIL

STB2

M12x30L

6315, 7315ZZ

H-60

#T-46

LIFTING CHAIN

1EA17

S-60 1EA

2EA

1EA

1EA

1EA

STS304 400A

SSC13

STS304

SSC13 1EA

SSC13 1EAGUIDE HOOK

STS304 1EA

1EA

1EALEAK DETECTION SENSOR

MOTOR TEMP. SENSOR

M4

PANEL MATERIAL DETAIL & DIMENSION

PUMP MATERIAL DETAIL / CONTROL

COORDINATION WITH DPW CIVIL ENGINEER.

ACCORDANCE WITH TEST OPERATION AND

INSTALLATION SHALL BE DETERMINED IN

NOTE : THE LOCATION & QUANTITY OF LEVEL SENSOR

M4

File details come from the government source that posted it.