Section B - Supplies or Services and Prices

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Job

(K) REPLACE AC UNIT, B2301, YSN

FFP

Replace 16 ton A/C Unit and Air Handling Unit, B2301 Yongsan

FOB: Destination

PURCHASE REQUEST NUMBER: 0011138433

PSC CD: 5670

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

PWO
TITLE
LOCATION
155316
Replace 16 ton A/C Unit and Air Handling Unit, B2301
USAG YONGSAN

1. DESCRIPTION: Contractor shall provide all labor, tools, equipment, supplies, and any other resources necessary to accomplish the scope of work contained herein and as included in the drawings and specifications.

2. PERFORMANCE PERIOD: The contractor must complete this project within 180 days after NTP is issued.

3. PRINCIPAL FEATURES: This project includes, but will not be limited to, the following principal features:

1) Maintenance and Repair (K)

a) Building 2301, Yongsan

i. CIVIL

· NONE

ii. ARCHITECTURAL

· NONE

iii. STRUCTURAL

· NONE

iv. MECHANICAL

· Replace existing A/C unit (Outdoor), AHU (Indoor), steam trap, ducts, pipes (Steam & Cooling), duct smoke detector, motorized valve, valves, duct liner, fittings, control line associated with equipment replacement, pipe support, insulation, and all associated accessories, for HVAC system as shown on drawings.

· Perform duct air leakage test (DALT) after construction to verify if the HVAC system works properly.

· For this project, the project manager should be a first class building facilities engineer license and should meet other requirements as specified on Korea-wide general construction

(Including new construction work under $750k) multiple award indefinite delivery indefinite quantity (MA IDIQ) document.

Note

· The contractor shall verify existing conditions for new work such as equipment & service clearance, equipment pad size, installation locations, and additional items.

· If the contractor is going to construction during the cooling/heating season, the contractor shall provide the temporary cooling or heating system to the entire building.

v. ELECTRICAL

· Disconnect and reconnect power supply and control line for new A/C unit and Air Handling Unit.

Note

· All electrical work should be done in accordance with the current editions of national electrical code, national electrical safety code, life safety code, unified facilities criteria and contract specifications.

· Exact ratings and settings of electrical equipment and devices shall be in accordance with mechanical equipment manufacturer's recommendations.

1) Construction or New Work (L)

NONE

SPECIAL CONDITIONS

1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which form a part of the contract.

2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours, from 1 October through 30 April and from 0730 hours through 1930 hours from 1 May through 30 September, Mondays through Saturdays, except for Korean Legal Holidays: Any proposed change in working hours should be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR).

3. WINTERIZATION: The contractor may be required to perform weather sensitive work during the winter season, which may cause additional costs to be incurred for the contractor. These additional costs are the contractor’s responsibility in the event you are required to work during the winter. Your responsibility regarding the preparation of the proposal is to reflect these additional costs in your proposal.

4. ESCORT PRIVILEGE: The contractor shall be responsible for requesting escorting privileges on base passes for Project Manager, Quality Control Manager, Safety Specialist and Foremen. The maximum number of escorted employee will be three persons and the number of escorted vehicle will be one. The contractor shall ensure that the escorting employee has full control of all escorted individuals at all times. Any individual found on the installation unescorted will be removed from the installation and the escort employee’s escorting privileges will be withdrawn. Any individual removed from this installation will not be authorized further access to this installation.

5. DISPOSAL OF CONSTRUCTION DEBRIS/WASTE MATERIALS: The Contractor shall be required to dispose all construction debris and waste materials in strict accordance with disposal requirements of Section 024100, Demolition and Deconstruction, and local laws and regulations at the Contractor’s responsibility and his own expense. The waste/unsalvageable materials shall be disposed at the location(s) approved and designated by the local authorities.

6. AT/FP TRAINING REQUIREMENTS OF CONTRACTOR:

a. AT Level 1 Training: All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 14 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 14 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.

b. Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

c. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

d. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 14 calendar days of contract award and within 14 calendar days of new employees commencing performance with the results reported to the COR NLT 14 calendar days after contract award.

e. OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.

7. SUBMITTALS: The Contractor shall process submittals in accordance with Section 013300 – SUBMITTAL PROCEDURES. Specific submittal requirements are shown on attached document entitled, “SUBMITTAL REGISTER”, Enclosure 1.

Section F - Deliveries or Performance

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 calendar days after notice to proceed (NTP) is issued. * The time stated for completion shall include final cleanup of the premises.

(End of clause)

Section J - List of Documents, Exhibits and Other Attachments

LIST OF APPLICABLE CONTRACT DRAWINGS

GENERAL: The work shall conform to the following contract drawings and OMA standard detail drawings, 2014 (dated 30 November 2015), located on the 411th CSB Web Page http://www.usfk.mil/Resources/ContractingwithUSFK.aspx, all of which form a part of the specifications.

PWO 155316

Ring No.
Sheet No.
Description
Date

GENERAL

1
G-001
TITLE SHEET
7 AUG 17
2
G-002
PROJECT LOCATION PLAN
7 AUG 17

MECHANICAL

M-001
GENERAL NOTE, SCOPE OF WORK AND EQUIPMENT SCHEDULES
7 AUG 17
MD101
EXIST/REMOVAL HVAC AND HVAC PIPING ENLARGED PLAN
7 AUG 17
5
MH101
EXIST/NEW HVAC AND HVAC PIPING ENLARGED PARTIAL PLAN & SITE PICTURES
7 AUG 17
6
M-501
MECHANICAL DETAILS & CONTROL
7 AUG 17

TECHNICAL DETAIL SPECIFICATIONS

GENERAL: The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea, Revision 1” (2014 OMA SPECS, REVISION 1), dated 20151030, located on the 411th CSB Web Page, http://www.usfk.mil/Resources/ContractingwithUSFK.aspx. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.

STANDARD TECHNICAL SPECIFICATIONS FOR O&MA

PROJECT TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

01 30 00

ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10

PROJECT SCHEDULE

01 33 00

SUBMITTAL PROCEDURES

01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.00 10

QUALITY CONTROL

01 50 00

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 58 00

PROJECT IDENTIFICATION

01 78 00

CLOSEOUT SUBMITTALS

01 78 23

OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00

DEMOLITION AND DECONSTRUCTION

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING

23 00 00

AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 03 00.00 20

BASIC MECHANICAL MATERIALS AND METHODS

23 05 93

TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00

THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 23 00

REFRIGERANT PIPING

23 82 02.00 10

UNITARY HEATING AND COOLING EQUIPMENT

DIVISION 26 – ELECTRICAL

26 00 00.00 20

BASIC ELECTRICAL MATERIALS AND METHODS

26 20 00

INTERIOR DISTRIBUTION SYSTEM

Section K - Representations, Certifications and Other Statements of Offerors

CLAUSES INCORPORATED BY FULL TEXT

52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)

(a) The offeror certifies that --

(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –

(i) Those prices,

(ii) The intention to submit an offer, or

(iii) The methods of factors used to calculate the prices offered:

(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and

(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.

(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --

(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or

(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);

(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and

(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.

(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.

(End of Provision)

252.209-7999 Representation by Corporations Regarding an Unpaid Delinquent Tax Liability or a Felony Conviction under any Federal Law

REPRESENTATION BY CORPORATIONS REGARDING AN UNPAID DELINQUENT TAX LIABILTIY OR A FELONY CONVICTION UNDER ANY FEDERAL LAW (DEVIATION 2012-00004) (JAN 2012)

(a) In accordance with sections 8124 and 8125 of Division A of the Consolidated Appropriations Act, 2012, (Pub. L. 112-74) none of the funds made available by that Act may be used to enter into a contract with any corporation that-

(1) Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless the agency has considered suspension or debarment of the corporation and made a determination that this further action is not necessary to protect the interests of the Government.

(2) Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where the awarding agency is aware of the conviction, unless the agency has considered suspension or debarment of the corporation and made a determination that this action is not necessary to protect the interests of the Government.

(b) The Offeror represents that –

(1) It is ( ) is not ( ) a corporation that has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with authority responsible for collecting the tax liability,

(2) It is ( ) is not ( ) a corporation that was convicted of a felony criminal violation under a federal law within the preceding 24 months.

(End of provision)

5152.204-4032 REPRESENTATIONS AND CERTIFICATIONS

(a) SUBCONTRACTING:

If the offeror contemplates subcontracting, it must obtain prior written approval of subcontractor from the PCO or ACO, and list below: (1) the names and addresses of the subcontractor(s), (2) the type of subcontracting, and (3) the estimated price for each subcontract.

(b) AFFILIATED OFFERORS:

(1) Business concerns are affiliates of each other when, either directly or indirectly, one concern controls or has the power to control the other, or a third party controls or has the power to control both.

(2) Each offeror shall furnish, below, the following information:

(i) Whether the offeror has any affiliates;

(ii) The names and addresses of all affiliates of the offeror; and

(iii) The names and addresses of all persons and concerns exercising control or ownership of the offeror and any or all of its affiliates, and whether they are common officers, directors, stockholders holding controlling interest, or otherwise.

AFFILIATED CONCERNS. : (Name, location and, in detail, controlling interest in each)

(c) PRINCIPAL OWNER(S) OR STOCKHOLDER(S):

Each offeror shall list below the name(s) and address(es) of the principal owner(s) or stockholder(s) of the company and percentage of ownership. If a major portion is publicly traded and/or otherwise widely distributed, state that, with the percentage so affected.

(d) STANDARDS OF CONDUCT CERTIFICATION:

This is to certify that, to the best of my knowledge and belief, except as described below, no representative of this firm who deals with US Government employees on any aspect of this procurement is a former US Government employee, to include former US military personnel. I understand that this certification is continuing in nature and places a duty on me and my firm to notify the Contracting Officer of any additional individual(s) who fit the above description prior to the individual's assuming duties.

(i) Name ______________________________________________

Former rank/grade ____________________________________

Last US Government position ___________________________

(ii) Name ______________________________________________

Former rank/grade ____________________________________

Last US Government position ___________________________

(iii) Name ______________________________________________

Former rank/grade ____________________________________

Last US Government position ___________________________

Firm ____________________________________________________

Name _____________________________________________________

Signature __________________________________________________

Title _____________________________________________________

Date of Execution ____________________________________________

(e) TAXES:

(1) References:

(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."

(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.

(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.

(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.

(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

This item will be imported specifically for this contract? Yes _____ No _____

(ii) Special Excise Tax:

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

Name of item manufacturer

(iii) Value Added Tax (VAT):

Input VAT on materials purchased for this contract. 10% _____

Input VAT on transportation leased/rented for this contract.10% _____

Input VAT on equipment leased/rented for this contract. 10% _____

Input VAT on services purchased for this contract. 10% _____

Output VAT on total contract amount. 10% _____

(iv) Special Excise (Petroleum) Tax:

No. of U/P

Liters w/o Tax Tax/Unit Total Tax Amount

Regular Gasoline ________ (L) ________ w________ w_____________

Premium Gasoline ________ (L) ________ w________ w_____________

Diesel ________ (L) ________ w________ w_____________

Other ________ (L) ________ w________ w_____________

(v) Education Tax.

(3) Name of the oil company from which POL products will be purchased:

Oil Company: _________________________________________ (Name only)

(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.

Signed (Chop)

(f) CERTIFICATIONS AND REPRESENTATIONS

By submitting an offer, each offeror agrees to be bound by all certifications and representations in this solicitation. The Government reserves the right to require any and all certifications and representations to be completed and signed in hard copy by the successful offeror prior to contract award. Failure of an offeror to complete the certifications and representations within the time directed by the Contracting Officer may result in a determination that the contractor is not a responsible offeror for this acquisition.

Section L - Instructions, Conditions and Notices to Bidders

INSTRUCTION TO OFFEROR

1. GENERAL INSTRUCTIONS FOR PREPARATION OF PROPOSAL:

a. Site Visit: Offerors who intend to propose on this solicitation are strongly encouraged to attend the site visit. See site visit Clause FAR 52.236-27. Offerors are required to have a valid Korean Identification card when attending the site visit orientation.

b. Offeror(s) are cautioned to follow the detailed instructions fully and carefully, as the Government reserves the right to make award based on initial offers received, without discussions of such offers.

c. Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted. For that purpose, if the Government conducts discussions with any offeror in the competitive range, the Government shall conduct discussions with all offeror(s) in the competitive range.

2. SUBMISSION OF PROPOSAL:

a. Offeror shall submit its proposal electronically by 1300 hours on the closing date of the solicitation through Federal Business Opportunities (FBO) https://www.fbo.gov/.

b. Offeror shall provide a Point of Contact (name, position title, email address, and phone number) who has knowledge of the proposal’s contractual and technical issues.

c. Proposal Document Submissions: Offeror shall provide the following documentation as part of their proposal:

i) Pricing Proposal: The pricing proposal shall include the following:

(1) Completed Pricing Schedule: the offeror shall complete the pricing information for the each contract line item identified in Section B.

ii) Offer Breakdown: Offerors shall submit an offer breakdown that identifies Materials, Labor, and Transportation and Equipment (T&E), and other resources upon which the offeror intends to rely to perform this contract in accordance with the Statement of Work. The offer breakdown must demonstrate that the offeror understands the requirement in the RFP by listing an appropriate amount of materials, labor, and transportation and equipment required to perform the contract in accordance with the Statement of Work and drawings. The Offeror’s proposal must contain all contractor’s costs including mobilization, demobilization, overhead, profit, insurance, design fee and all other costs including but not limited to compliance with environmental laws, tax laws, protection or moving of Government property, engineering services (to include survey work and drawings) and waste disposal inherent to accomplish the work request. No allowance will be made later for any other purpose whatsoever unless specifically allowed elsewhere in the contract. Offeror shall provide one (1) original offer breakdown with price and one (1) copy of the offer breakdown without price in accordance to the provided template below:

(a) Materials:

(I) Local Materials:

(A) Type of material with item description, capacity or model number;

(B) Quantity

(II) U.S. Origin Materials:

(A) Type of material with item description, capacity or model number;

(B) Quantity

(b) Labor:

(I) Category of labor;

(II) Quantity (man-days in each category);

(c) Transportation and Equipment:

(I) Description of all transportation and equipment (category and capacity);

(II) Quantity (per trip or equipment-day);

(d) Other Critical Resource(s): Must be fully described.

iii) Section K: Offerors shall fill out and submit all portions of the clauses included in Section K.

- FAR clause 52.203-2

- DFARS clause 252.209-7999

- AFARS clause 5152.204-4032

3. NO-OFFER LETTER: If MATOC Contractor is unable to submit a proposal in response to this RFP, the Contractor shall submit a ‘No-Offer Letter’ by date and time specified in this solicitation.

4. All questions shall be submitted via electronic mail to the Contracting Officer, Ms. Jessica Gaskins at jessica.d.gaskins.civ@mail.mil, and the Contract Specialist, Ms. Jessica Gaskins at yongsuk.kim5.ln@mail.mil, within 5 calendar days at 1700 hours (Korea Standard Time) from the date the solicitation is issued.

Failure to submit the above requirements may be grounds for determining the proposal to be non-responsive and not eligible to be considered for award.

CLAUSES INCORPORATED BY FULL TEXT

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Location: Bldg #2301 Date & Time: 2 Feb 2018 (Friday) & 1000 hrs POC: Mr. Kim, Hon Yong, COR/Const., DSN)724-7751 (End of provision)

5152.236-4011 CONSTRUCTION PRICE RANGE

Pursuant to FAR 36.204 the estimated price range is between $25,000 and $100,000.

Section M - Evaluation Factors for Award

BASIS OF AWARD

1. Award shall be made to the responsible offeror submitting the lowest priced, technically acceptable offer and completed Section K that satisfies all terms and conditions of this solicitation. The Government reserves the right to make a technical acceptability determination without any discussion with the offeror.

2. The Government will evaluate the Offeror Breakdown to determine technical acceptability. Offeror Breakdown must identify Materials, Labor, and Transportation and Equipment (T&E), and other resources upon which the offeror intends to rely to perform this contract in accordance with the Statement of Work and drawings. The offer breakdown must demonstrate that the offeror understands the requirement in the RFP by listing an appropriate amount of materials, labor, and transportation and equipment required to perform the contract in accordance with the Statement of Work and drawings. Proposals rated technically unacceptable will not be considered for award.

Technical Rating Method

Adjectival Rating
Description
Acceptable
Proposal meets the requirements of the solicitation.
Unacceptable
Proposal does not meet the requirements of the solicitation.

3. The Government will evaluate the offeror's responses to the applicable Section K Representations and Certifications listed in the Instructions to Offerors. Offeror's who fail to submit or complete the applicable Representations and Certifications may be removed from the competitive range and may not be considered for award.

Representations and Certifications Rating Method

Adjectival Rating
Description
Acceptable
All representations and certifications listed in the Instructions to Offerors are complete and no responses prohibit the contracting officer from making an award.
Unacceptable
Representations and certifications listed in the Instructions to Offerors are incomplete, missing, or include responses that prohibit the contracting officer from making an award.

4. The Offeror Breakdown and Section B will be evaluated in accordance with FAR 15.404 Proposal Analysis Techniques to determine if the price is fair and reasonable. Price for all line items will be added together to evaluate offeror's total price. Tax exemptions stated in Section K will be reviewed by the contracting officer for reasonableness and necessity to complete the Task Order. The contracting officer may reject a proposal if the offeror appears to have improperly overstated any proposed tax exemptions or submitted pricing and/or cost data that appear to be unreasonable.

5. A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.

Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.