A21_Solicitation_W91QVN17R0108_Repave_8th_Army_Road.pdf
PDF 147 KB Posted
- Solicitation number
- W91QVN-17-R-0108
About this file
Solicitation W91QVN-17-R-0108 Repave 8th Army Road
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A21_Solicitation_W91QVN17R0108_A001_Drawings.pdf | ||
| A21_Solicitation_W91QVN17R0108_A003_Pricing_Sheet.XLS | XLS spreadsheet | |
| A21_Solicitation_W91QVN17R0108_A002_Submittal_Register.XLSX | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0011013226
PWO #163417
Title: Repave 8th Army Road from DHL to Fire Station, Yongsan
a. “THIS TASK ORDER RFP IS FOR MA IDIQ CONTRACTORS ONLY.”
Applicable Contract Numbers: W91QVN-12-D-0120, W91QVN-12-D-0121, and W91QVN-12-D-0123.
b. Site Visit: Offerors w ho intend to propose on this solicitation are strongly encouraged to attend site visit. See site visit clause FAR 52.236-27. Offerors are required to have a valid Korean Identif ication Card w hen attending the site visit orientation.
MS. GASKINS, JESSICA D. (02) 7914-3357
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
12-May-2017
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________90 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________23 May 2017 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All of fers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
RCC YONGSAN, UNIT #15289
APO AP 96205-5289
W91QVN
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
01:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W91QVN-17-R-0108 22
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specified below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
4001 1 Job Repave 8th Army Road, YS
FFP
Repave 8th Army Road between Dragon Hill Lodge and Fire Station, Yongsan FOB: Destination
PURCHASE REQUEST NUMBER: 0011013226
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Estimated War Hazard Losses
FFP
Estimated War Hazard Losses is Zero (0).
NET AMT
Section C - Descriptions and Specifications
STATEMENT OF WORK
TECHNICAL PROVISIONS - I
STATEMENT OF WORK 16 MAR 2017
PWO TITLE LOCATION
163417 Repair/replace pavement at 8TH Army Road
(Between DHL and Fire Station)
USAG YONGSAN
1. DESCRIPTION: Contractor shall provide all labor, tools, equipment, supplies, and any other resources necessary to accomplish the scope of work contained herein and as included in the drawings and specifications.
2. PERFORMANCE PERIOD: The contractor must complete this project within 90 days after NTP is issued.
3. PRINCIPAL FEATURES: This project includes, but will not be limited to, the following principal features:
a. PWO 163417
1) Maintenance and Repair (K)
a) LOCATION (USAG YONGSAN, 8TH Army Road)
i. Civil Work
Replace 100mm thick asphalt concrete (AC) pavement with 200mm base course and
350mm thick subbase course (9,106 SM).
Apply pavement marking (740 SM).
Raise existing concrete manhole (2 EA).
Replace divider reflective rubber cone with anchor (19 EA).
Remove and dispose asphalt pavement and construction debris (5,919 CM) to outside compound including asphalt concrete base course and subbase course.
Notes:
1. Existing utilities (speed hump & etc.) whether shown on the drawing or not which has been damaged as a result of the construction work, shall be restored immediately to its original condition or better condition and shall be paid by the contractor.
2. Paved roads shall have a crown in the middle with 2% grade in travel lanes, unless on a natural side slope or banked turn.
3. Height of manhole covers surface inlets, and valve boxes shall match the finished grade and pavement elevation to within 5 millimeters.
4. Contractor shall include the tack/prime coat application rate as O&MA standard specification (Section
32 12 10).
5. In case the contractor damage existing concrete curb or gutter during the construction, the contractor shall restore damaged concrete curb or gutter.
6. Contractor shall make proper phasing of the pavement work area for the smooth traffic flow. (Traffic Control Plan shall be approved by the Yongsan Directorate of Emergency Service (DES) thru Department of Public Works (DPW) Yongsan).
7. Contractor shall place flaggers from AM 07:00 to PM 06:00 during pavement work.
8. During work hours, contract workers shall be supervised by contract supervisor.
9. Contractor shall repaint all existing pavement markings at the completion of the paving work to include centerline, stop line, crosswalk, turn lane, driving instructions written on the road lanes, and cycling road markings.
10. When the contractor raises manholes, the contractor shall use a permanently constructed structure, not a brick or other unstable material, underneath the manhole.
11. Contractor shall make provisions for minimum of one lane of traffic to be open throughout the construction period.
TECHNICAL PROVISIONS - II
TECHNICAL DETAIL SPECIFICATIONS
GENERAL: The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea, Revision 1” (2014 OMA SPECS, REVISION 1), dated 20151030, located on the 411th CSB Web Page, http://www.usfk.mil/Resources/ContractingwithUSFK.aspx. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.
STANDARD TECHNICAL SPECIFICATIONS FOR O&MA
PROJECT TABLE OF CONTENTS
DIVISION 01 GENERAL REQUIREMENTS
01 30 00 Administrative Requirements 01 32 01.00 10 Project Schedule 01 33 00 Submittal Procedures 01 35 26 Governmental Safety Requirements 01 35 29.13 Health, Safety, and Emergency Response Procedure for Contaminated Sites 01 42 00 Sources for Reference Publications 01 45 00.00 10 Quality Control 01 50 00 Temporary Construction Facilities and Controls 01 57 20.00 10 Environmental Protection 01 58 00 Project Identification 01 78 00 Closeout Submittals 01 78 23 Operation and Maintenance Data
DIVISION 32 EXTERIOR IMPROVEMENTS
32 11 16 Base Course for Rigid and Subbases for Flexible Paving 32 11 24 Graded Crushed Aggregate Base Course for Pervious/Flexible Pavement 32 12 10 Bituminous Tack and Prime Coats 32 12 16 Hot-Mix Asphalt (HMA) for Roads 32 17 24.00 10 Pavement Markings
W91QVN-17-R-0108
TECHNICAL PROVISIONS - III
SPECIAL CONDITIONS
1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which form a part of the contract.
2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours, from 1 October through 30 April and from 0730 hours through 1930 hours from 1 May through 30 September, Mondays through Saturdays, except for Korean Legal Holidays: Any proposed change in working hours should be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR).
3. WINTERIZATION: The contractor may be required to perform weather sensitive work during the winter season, which may cause additional costs to be incurred for the contractor. These additional costs are the contractor’s responsibility in the event you are required to work during the winter. Your responsibility regarding the preparation of the proposal is to reflect these additional costs in your proposal.
4. ESCORT PRIVILEGE: The contractor shall be responsible for requesting escorting privileges on base passes for Project Manager, Quality Control Manager, Safety Specialist and Foremen. The maximum number of escorted employee will be three persons and the number of escorted vehicle will be one. The contractor shall ensure that the escorting employee has full control of all escorted individuals at all times. Any individual found on the installation unescorted will be removed from the installation and the escort employee’s escorting privileges will be withdrawn. Any individual removed from this installation will not be authorized further access to this installation.
5. DISPOSAL OF CONSTRUCTION DEBRIS/WASTE MATERIALS: The Contractor shall be required to dispose all construction debris and waste materials in strict accordance with disposal requirements of Section 024100, Demolition and Deconstruction, and local laws and regulations at the Contractor’s responsibility and his own expense. The waste/unsalvageable materials shall be disposed at the location(s) approved and designated by the local authorities.
6. AT/FP TRAINING REQUIREMENTS OF CONTRACTOR:
a. AT Level 1 Training: All contractor employees, to include subcontractor employees, requiring access
Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 14 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 14 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website:
http://jko.jten.mil.
b. Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
c. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
d. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 14 calendar days of contract award and within 14 calendar days of new employees commencing performance with the results reported to the COR NLT 14 calendar days after contract award.
e. OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I
OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.
7. SUBMITTALS: The Contractor shall process submittals in accordance with Section 013300 – SUBMITTAL PROCEDURES. Specific submittal requirements are shown on attached document entitled, “SUBMITTAL REGISTER”, Enclosure 1.
APPENDIX A
APPENDIX "A"
LIST OF APPLICABLE CONTRACT DRAWINGS
GENERAL: The work shall conform to the following contract drawings and OMA standard detail drawings, 2014 (dated 30 November 2015), located on the 411th CSB Web Page http://www.usfk.mil/Resources/ContractingwithUSFK.aspx, all of which form a part of the specifications.
PWO 163417
Ring No. Sheet No. Description Date
GENERAL
G-001
G-002
TITLE SHEET
LOCATION PLAN, GENERAL NOTES
16 MAR 17
CIVIL
CP101
CP301
C-501
SITE LAYOUT PLAN
PAVEMENT BOUDARY DETAIL
SITE LAYOUT PLAN
16 MAR 17
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
4001 Destination Government Destination Government 4002 Destination Government Destination Government
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC
4001 90 dys. ADC 1 W6B0 USA GARRISON YONGSAN
W6B0 USA GARRISON YONGSAN
DPW, UNIT 15333
APO AP 96205-0177
W582LG
4002 N/A N/A N/A N/A
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 calendar days after the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
Section G - Contract Administration Data
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984
Section J - List of Documents, Exhibits and Other Attachments
ATTACHMENTS
Attachment Title Date Pages A001 Drawings 22 MAR 2017 005 A002 Submittal Register 17 APR 2017 001 A003 Pricing Schedule 17 APR 2017 001
Section K - Representations, Certifications and Other Statements of Offerors
52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)
(a) The offeror certifies that --
(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –
(i) Those prices,
(ii) The intention to submit an offer, or
(iii) The methods of factors used to calculate the prices offered:
(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and
(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.
(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --
(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or
(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);
(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and
(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.
(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.
(End of Provision)
252.209-7999 REPRESENTATION BY CORPORATIONS REGARDING AN UNPAID DELINQUENT TAX
LIABILITY OR A FELONY CONVICTION UNDER ANY FEDERAL LAW (DEVIATION 2012-O0004) (JAN 2012)
(a) In accordance with sections 8124 and 8125 of Division A of the Consolidated Appropriations Act, 2012,(Pub. L.
112-74) none of the funds made available by that Act may be used to enter into a contract with any corporation that—
(1) Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless the agency has considered suspension or debarment of the corporation and made a determination that this further action is not necessary to protect the interests of the Government.
(2) Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where the awarding agency is aware of the conviction, unless the agency has considered suspension or debarment of the corporation and made a determination that this action is not necessary to protect the interests of the Government.
(b) The Offeror represents that—
(1) It is [ ___ ] is not [ ___ ] a corporation that has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability,
(2) It is [ ___ ] is not [ ___ ] a corporation that was convicted of a felony criminal violation under a Federal law within the preceding 24 months.
(End of provision)
5152.204-4032 REPRESENTATIONS AND CERTIFICATIONS
(a) SUBCONTRACTING:
If the offeror contemplates subcontracting, it must obtain prior written approval of subcontractor from the PCO or ACO, and list below: (1) the names and addresses of the subcontractor(s), (2) the type of subcontracting, and (3) the estimated price for each subcontract.
(b) AFFILIATED OFFERORS:
(1) Business concerns are affiliates of each other when, either directly or indirectly, one concern controls or has the power to control the other, or a third party controls or has the power to control both.
(2) Each offeror shall furnish, below, the following information:
(i) Whether the offeror has any affiliates;
(ii) The names and addresses of all affiliates of the offeror; and
(iii) The names and addresses of all persons and concerns exercising control or ownership of the offeror and any or all of its affiliates, and whether they are common officers, directors, stockholders holding controlling interest, or otherwise.
AFFILIATED CONCERNS. : (Name, location and, in detail, controlling interest in each)
(c) PRINCIPAL OWNER(S) OR STOCKHOLDER(S):
Each offeror shall list below the name(s) and address(es) of the principal owner(s) or stockholder(s) of the company and percentage of ownership. If a major portion is publicly traded and/or otherwise widely distributed, state that, with the percentage so affected.
(d) STANDARDS OF CONDUCT CERTIFICATION:
This is to certify that, to the best of my knowledge and belief, except as described below, no representative of this firm who deals with US Government employees on any aspect of this procurement is a former US Government employee, to include former US military personnel. I understand that this certification is continuing in nature and places a duty on me and my firm to notify the Contracting Officer of any additional individual(s) who fit the above description prior to the individual's assuming duties.
(i) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
(ii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
(iii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
Firm ____________________________________________________ Name _____________________________________________________ Signature __________________________________________________
Title _____________________________________________________ Date of Execution ____________________________________________
(e) TAXES:
(1) References:
(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."
(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.
(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.
(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.
(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
This item will be imported specifically for this contract? Yes _____ No _____
(ii) Special Excise Tax:
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
Name of item manufacturer
(iii) Value Added Tax (VAT):
Input VAT on materials purchased for this contract. 10% _____ Input VAT on transportation leased/rented for this contract.10% _____ Input VAT on equipment leased/rented for this contract. 10% _____ Input VAT on services purchased for this contract. 10% _____ Output VAT on total contract amount. 10% _____
(iv) Special Excise (Petroleum) Tax:
No. of U/P Liters w/o Tax Tax/Unit Total Tax Amount Regular Gasoline ________ (L) ________ w________ w_____________ Premium Gasoline ________ (L) ________ w________ w_____________ Diesel ________ (L) ________ w________ w_____________ Other ________ (L) ________ w________ w_____________
(v) Education Tax.
(3) Name of the oil company from which POL products will be purchased:
Oil Company: _________________________________________ (Name only)
(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.
Signed (Chop)
(f) CERTIFICATIONS AND REPRESENTATIONS
By submitting an offer, each offeror agrees to be bound by all certifications and representations in this solicitation.
The Government reserves the right to require any and all certifications and representations to be completed and signed in hard copy by the successful offeror prior to contract award. Failure of an offeror to complete the certifications and representations within the time directed by the Contracting Officer may result in a determination that the contractor is not a responsible offeror for this acquisition.
Section L - Instructions, Conditions and Notices to Bidders
52.211-6 BRAND NAME OR EQUAL (AUG 1999)
(a) If an item in this solicitation is identified as “brand name or equal,” the purchase description reflects the characteristics and level of quality that will satisfy the Government's needs. The salient physical, functional, or performance characteristics that “equal” products must meet are specified in the solicitation.
(b) To be considered for award, offers of “equal” products, including “equal” products of the brand name manufacturer, must--
(1) Meet the salient physical, functional, or performance characteristic specified in this solicitation;
(2) Clearly identify the item by--
(i) Brand name, if any; and
(ii) Make or model number;
(3) Include descriptive literature such as illustrations, drawings, or a clear reference to previously furnished descriptive data or information available to the Contracting Officer; and
(4) Clearly describe any modifications the offeror plans to make in a product to make it conform to the solicitation requirements. Mark any descriptive material to clearly show the modifications.
(c) The Contracting Officer will evaluate “equal” products on the basis of information furnished by the offeror or identified in the offer and reasonably available to the Contracting Officer. The Contracting Officer is not responsible for locating or obtaining any information not identified in the offer.
(d) Unless the offeror clearly indicates in its offer that the product being offered is an “equal” product, the offeror shall provide the brand name product referenced in the solicitation.
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for-- Date: May 16, 2017, 1330 hours Korean Standard Time
(c) Participants will meet at-- Near B4203, USAG Yongsan
(c) Point of Contact— Mr. Kim, Chong Pil Phone number: 0101-9876-4489; DSN: 314-724-4490 Email: chongpil.kim3.ln@mail.mil
Escort: Any Multiple Award (MA) Indefinite Delivery Indefinite Quantity (IDIQ) contractor who needs escort shall have a Korea Identification Card, passport, or driver’s license.
Offerors shall provide names of who will attend the site visit to the Point of Contact listed above no later than May 15, 2017, 1330 hours Korean Standard Time (1:30 pm).
(End of Provision)
5152.236-4011 CONSTRUCTION PRICE RANGE
Pursuant to FAR 36.204 the estimated price range is between $ 500,000 and $1,000,000.
INSTRUCTIONS TO OFFERORS
INSTRUCTIONS TO OFFERORS
1. GENERAL INSTRUCTIONS FOR PREPARATION OF PROPOSAL:
a. Site Visit: Offerors who intend to propose on this solicitation are strongly encouraged to attend the site visit. See site visit Clause FAR 52.236-27. Offerors are required to have a valid Korean Identification card when attending the site visit orientation.
b. Offeror(s) are cautioned to follow the detailed instructions fully and carefully, as the Government reserves the right to make award based on initial offers received, without discussions of such offers.
c. Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted. For that purpose, if the Government conducts discussions with any offeror in the competitive range, the Government shall conduct discussions with all offeror(s) in the competitive range.
2. SUBMISSION OF PROPOSAL:
a. Offeror shall submit its proposal electronically by 1300 hours on the closing date of the solicitation through Federal Business Opportunities (FBO) https://www.fbo.gov/.
b. Offeror shall provide a Point of Contact (name, position title, email address, and phone number) who has knowledge of the proposal’s contractual and technical issues.
c. Proposal Document Submissions: Offeror shall provide the following documentation as part of their proposal:
i) Pricing Proposal: The pricing proposal shall include the following:
(1) Completed Pricing Schedule: the offeror shall complete the pricing information for the each contract line item identified in Section B.
ii) Offer Breakdown: Offerors shall submit an offer breakdown that identifies Materials, Labor, and Transportation and Equipment (T&E), and other resources upon which the offeror intends to rely to perform this contract in accordance with the Statement of Work. The offer breakdown must demonstrate that the offeror understands the requirement in the RFP by listing an appropriate amount of materials, labor, and transportation and equipment required to perform the contract in accordance with the Statement of Work and drawings. The Offeror’s proposal must contain all contractor’s costs including mobilization, demobilization, overhead, profit, insurance, design fee and all other costs including but not limited to compliance with environmental laws, tax laws, protection or moving of Government property, engineering services (to include survey work and drawings) and waste disposal inherent to accomplish the work request. No allowance will be made later for any other purpose whatsoever unless specifically allowed elsewhere in the contract. Offeror shall provide one (1) original offer breakdown with price and one (1) copy of the offer breakdown without price in accordance to the provided template below:
(a) Materials:
(I) Local Materials:
(A) Type of material with item description, capacity or model number;
(B) Quantity (II) U.S. Origin Materials:
(A) Type of material with item description, capacity or model number;
(B) Quantity
(b) Labor:
(I) Category of labor;
(II) Quantity (man-days in each category);
(c) Transportation and Equipment:
(I) Description of all transportation and equipment (category and capacity);
(II) Quantity (per trip or equipment-day);
(d) Other Critical Resource(s): Must be fully described.
iii) Section K: Offerors shall fill out and submit all portions of the clauses included in Section K.
- FAR clause 52.203-2
- DFARS clause 252.209-7999
- AFARS clause 5152.204-4032
3. NO-OFFER LETTER: If MATOC Contractor is unable to submit a proposal in response to this RFP, the Contractor shall submit a ‘No-Offer Letter’ by date and time specified in this solicitation.
4. All questions shall be submitted via electronic mail to the Contracting Officer, Mr. Stephen Edington at stephen.c.edington.civ@mail.mil, and the Contract Specialist, Ms. Jessica Gaskins at jessica.d.gaskins.civ@mail.mil, within 5 calendar days at 1700 hours (Korea Standard Time) from the date the solicitation is issued.
Section M - Evaluation Factors for Award
BASIS OF AWARD
BASIS OF AWARD
Award shall be made to the responsible offeror submitting the lowest priced, technically acceptable offer and completed Section K (Representations and Certifications) that satisfies all terms and conditions of this solicitation.
The Government will rely on the offer breakdown to perform a technical analysis to determine if the offeror has demonstrated an understanding of the requirement in the RFP by listing an appropriate amount of materials, labor, and transportation and equipment required to perform the contract IAW the Statement of Work, drawings, and OMA specification. Failure to include a significant element in the data may indicate that the offeror fails to understand the requirement, and will be grounds for finding the proposal to be technically unacceptable. The Government reserves the right to make a technical acceptability determination without any discussion with the offeror. The tax exemptions stated in Section K will be reviewed by the contracting officer for reasonableness and necessity to complete the Task Order. The contracting officer may reject a proposal if the offeror appears to have improperly overstated any proposed tax exemptions.
Analysis of offered prices will be performed to ensure that the final price is fair and reasonable in accordance with
FAR 15.404-1.