1 T - 1 1 OF 1 TITLE SHEET
CIVIL
T-1
TITLE SHEET
A
B C D
E F G H
SCHEDULE OF DRAWINGS
RING NO. RING NO.DWG. NO. DWG. NO.SHT. NO. SHT. NO.DESCRIPTION OF DRAWINGS DESCRIPTION OF DRAWINGSREF. NO. REF. NO.REVISION STATUS REVISION STATUS
SYMBOL BY
DESIGNED BY
SUBMITTED BY
USING AGENCY
APPROVED BY
PROJECT NO. DRAWING NO. REF NO.
SCALE :
ZONE DATE APVD.
UTILITIES
SHEET OF
REVIEWED BY
DESCRIPTION
BLDGS & GROUNDS
CHIEF, ENGR’G DIV
CHK’D
REVISIONS
IMCOM
FIRE & EMERGENCY SVC
SAFETY
ENERGY MANAGER
DEPARTMENT OF THE ARMY
US ARMY INSTALLATION MANAGEMENT COMMAND
HEADQUARTERS, UNITED STATES ARMY GARRISON, RED CLOUD
ENGINEERING DIVISON, DPW, USAG-RED CLOUD
UNIT #15707, APO AP 96258-5707
ENVIRONMENT
FORCE PROTECTION
CHOE, S M.
AS SHOWN
FEWR NO. 107195
WARRIOR BASE
WARRIOR BASE
107195
LOCATION PLAN
SITE LAYOUT PLAN AND SCOPE OF WORK
MISC. DETAILS
REPAIR PARKING AREA NEAR FIRE STATION AND MOTOR POOL
REPAIR PARKING AREA NEAR FIRE
STATION AND MOTOR POOL
JOINT LAYOUT PLAN
PCC PAVEMENT DETAIL
C - 1
C - 2
C - 3
C - 4
C - 5
C-1
A
B C D
E F G H
SYMBOL BY
DESIGNED BY
ENERGY MANAGER
SUBMITTED BY
USING AGENCY
APPROVED BY
PROJECT NO. DRAWING NO. REF NO.
SCALE :
ZONE DATE APVD.
UTILITIES
SHEET OF
REVIEWED BY
DESCRIPTION
BLDGS & GROUNDS
CHIEF, ENGR’G DIV
DES
CHK’D
REVISIONS
IMCOM
FIRE & EMERGENCY SVC
SAFETY
ENVIRONMENT
DEPARTMENT OF THE ARMY
US ARMY INSTALLATION MANAGEMENT COMMAND
HEADQUARTERS, UNITED STATES ARMY GARRISON, RED CLOUD
ENGINEERING DIVISON, DPW, USAG-RED CLOUD
UNIT #15707, APO AP 96258-5707
CIVIL
WARRIOR BASE
THIS PROJECT
NOTE: THE CONTRACTOR’S HAUL ROUTE, STORAGE AND OPERATION AREA WILL
BE DESIGNATED BY THE DPW DURING THE SITE ORIENTATION.
WARRIOR BASE
WONJU
POHANG
MOKPO
TONGYEONG
SEOUL
DONGDUCHEON
UIJEONGBU
CHUNCHEON
1OSAN
DAEJEON
E A S T S E A
BUSAN
WAEGWAN
JINHAE
DAEGU
MUNSAN
W E S T
S E A
INCHEON
GWANGJU
NOT TO SCALE
L O C A T I O N M A P
GUNSAN
PYEONGTAEK
MASAN
N
- 1
SCALE: 1 / 1200
LOCATION PLAN
LOCATION PLAN
CHOE, S M.
H F/T
F /T
F /T
F /T
2173(LIGHT-16EA)
294 2170
206T
Fire Station
NEW TRASH BIN
Water Tank
33,000 GAL
120,000 GAL
Water Tank
Toilet
Waste Water
Treatment Plant
Water Treatment Plant
MAIN GATE
REPAIR PARKING AREA NEAR FIRE
STATION AND MOTOR POOL
107195
FEWR 107195
REPAIR PARKING AREA NEAR FIRE
STATION AND MOTOR POOL
C-2
AS SHOWN
CHOE, S M.
A
B C D
E F G H
SYMBOL BY
DESIGNED BY
ENERGY MANAGER
SUBMITTED BY
USING AGENCY
APPROVED BY
PROJECT NO. DRAWING NO. REF NO.
SCALE :
ZONE DATE APVD.
UTILITIES
SHEET OF
REVIEWED BY
DESCRIPTION
BLDGS & GROUNDS
CHIEF, ENGR’G DIV
FORCE PROTECTION
CHK’D
REVISIONS
IMCOM
FIRE & EMERGENCY SVC
SAFETY
ENVIRONMENT
DEPARTMENT OF THE ARMY
US ARMY INSTALLATION MANAGEMENT COMMAND
HEADQUARTERS, UNITED STATES ARMY GARRISON, RED CLOUD
ENGINEERING DIVISON, DPW, USAG-RED CLOUD
UNIT #15707, APO AP 96258-5707
- 2
SCALE: 1 / 350
SITE LAYOUT PLAN
1:350
0 40M302010
SITE LAYOUT PLAN AND SCOPE OF WORK
- 5
N
- 4
WARRIOR BASE
REPAIR PARKING AREA NEAR FIRE
STATION AND MOTOR POOL
107195
MODIFY ONE(1) M/H TO MATCH
NEW PAVEMENT LEVEL. SEE
SCOPE OF WORK
SCHEDULE #1 (REPAIR/MAINTENANCE)
2. MODIFY ONE(1) M/H TO MATCH NEW
PAVEMENT LEVEL.
F/T
F /T
FUEL
TANK FUEL
TANK
C
70.00
.0
5.00
REPLACE PCC PAVEMENT W/ NEW,
APPROX. 5,120.0 SM. SEE
- 5
274 275 276
1. REPLACE PCC PAVEMENT W/ NEW.
REPLACE CON’C CURB,
APPROX. 63.0 LM. SEE
3. REPLACE CON’C CURB.
AC PAVEMENT AREA
C-3
AS SHOWN
CHOE, S M.
A
B C D
E F G H
SYMBOL BY
DESIGNED BY
ENERGY MANAGER
SUBMITTED BY
USING AGENCY
APPROVED BY
PROJECT NO. DRAWING NO. REF NO.
SCALE :
ZONE DATE APVD.
UTILITIES
SHEET OF
REVIEWED BY
DESCRIPTION
BLDGS & GROUNDS
CHIEF, ENGR’G DIV
FORCE PROTECTION
CHK’D
REVISIONS
IMCOM
FIRE & EMERGENCY SVC
SAFETY
ENVIRONMENT
DEPARTMENT OF THE ARMY
US ARMY INSTALLATION MANAGEMENT COMMAND
HEADQUARTERS, UNITED STATES ARMY GARRISON, RED CLOUD
ENGINEERING DIVISON, DPW, USAG-RED CLOUD
UNIT #15707, APO AP 96258-5707
- 3
SCALE: 1 / 350
1:350
0 40M302010
SITE LAYOUT PLAN AND SCOPE OF WORK
N
WARRIOR BASE
REPAIR PARKING AREA NEAR FIRE
STATION AND MOTOR POOL
107195
F/T
F /T
FUEL
TANK FUEL
TANK
C
.0
5.00
274 275 276
5.00
5.00
.0
JOINT LAYOUT PLAN
R
R
R
R
R
R R R R R R R R R R
R
RRR
R R R
R
R
R
R R R R R R
RRR
RR
R R
R R
R R
R R R R R
R R
R
R
LEGEND :
EXPANSION JOINT
REINFORCED PCC
CONTRACTION JOINT
R
R
R
CONTRACTION JOINT,
APPROX. 1,645.0 LM.
EXPANSION JOINT,
APPROX. 222.0 LM
REINFORCED PCC CONCRETE,
APPROX. 885.0 SM.
CONTRACTION JOINT
NOTE; DOWEL DIAMETER AS INDICATED
THIS END OF DOWEL
D13 BARS @ 305 OC
DOWELED CONSTRUCTION JOINT
25mm DIA X 406mmL @ 305 OC
THIS END OF DOWEL
CONSTRUCTION JOINT SEALANT DETAIL
FNSH GRADE
25mm DIA X 400mmL @ 380 OC
THIS END OF DOWEL
EXST PCC PAVEMENT
TACK COAT
SECTION
SLAB REINFORCEMENT DETAIL
(ODD-SHAPED SLAB & MISMATCHED JOINT)
PLAN
NOT TO SCALE
DOWELED
EDGE OF PCC PAVEMENT
FOR PCC REINFORCED PAVEMENT ONLY
JOINT SEALANT
PAINT AND OIL
203 203
OR CONSTRUCTION JOINT
D13 BARS @ 305 OC EW
OR 300mm X 300mm X
13mm DIA WELDED WIRE FABRIC
OR 300mm X 300mm X
13mm DIA WELDED WIRE FABRIC
NOT TO SCALE
THICKENED EDGE EXPANSION JOINT
19mm PREFORMED JOINT FILLER
NOT TO SCALE
JOINT SEALANT
JOINT SEALANT
PAINT AND OIL
EXPANSION JOINT SEALANT DETAIL
NOT TO SCALE
BOND BREAKING TAPE OR
SEPARATING MATERIAL
(3mm WIDER THAN NOMINAL WIDTH OF JOINT)
19mm PREFORMED JOINT FILLER
POURED JOINT SEALANT
203 203
CAST-IN-PLACE OR
DRILL & GROUT DOWEL
NEW PCC PAVEMENT
NOT TO SCALE
POURED JOINT SEALANT
BOND BREAKING TAPE OR
SEPARATING MATERIAL
(3mm WIDER THAN
NOMINAL WIDTH OF JOINT)
BUTTED JOINT
BLDG & MANHOLES OR
OTHER STRUCTURES
203203
240mm THK PCC
SURFACE COURSE
JOINT SEALANT
NOT TO SCALE
TRANSITION FOR
THICKENED EDGE
EXST AC SURFACE COURSE
EXST BASE COURSE
EXST SUBBASE COURSE
240mm THK PCC PAVEMENT
350mm THK 100%%% COMPACTION BASE COURSE
THICKENED EDGE
NEW PCC/ EXST AC PAVEMENT JOINT
NOT TO SCALE
TYPICAL-PCC PAVEMENT SECTION
AND THICKENED EDGE
NOTE: 1. SEALANT DEPTH MUST BE 1.0 TO 1.5 TIMES THE WIDTH.
350mm THK 100% COMPACTION
BASE COURSE
EXPANSION JOINT BETWEEN
NEW/EXST PCC PAVEMENT
NOT TO SCALE
200 200
EXPANSION CAP SLIP FIT
NEW PCC PAVEMENT
DRILL & GROUT DOWEL
JOINT SEALANT
PAINT AND OIL
25.4mm DIA X 406mmL @ 305mm OC
.7
.4
75 MAX
107.3 +-12.7
T
O
T O
.5
A
B C D
E F G H
SYMBOL BY
DESIGNED BY
ENERGY MANAGER
SUBMITTED BY
USING AGENCY
APPROVED BY
PROJECT NO. DRAWING NO. REF NO.
SCALE :
ZONE DATE APVD.
UTILITIES
SHEET OF
REVIEWED BY
DESCRIPTION
BLDGS & GROUNDS
CHIEF, ENGR’G DIV
FORCE PROTECTION
CHK’D
REVISIONS
IMCOM
FIRE & EMERGENCY SVC
SAFETY
ENVIRONMENT
DEPARTMENT OF THE ARMY
US ARMY INSTALLATION MANAGEMENT COMMAND
HEADQUARTERS, UNITED STATES ARMY GARRISON, RED CLOUD
ENGINEERING DIVISON, DPW, USAG-RED CLOUD
UNIT #15707, APO AP 96258-5707
- 4
SCALE: NONE
PCC PAVEMENT DETAIL
CHOE, S M.
CIVIL
C-4
AS SHOWN
PCC PAVEMENT DETAIL
NO.6-150X150 WWF
NO.6-150X150 WWF
NO.6-150X150 WWF
CONTRACTION JOINT
NOT TO SCALE
JOINT SEALANT
WWF #6 X #6 /150 X 150
NOT TO SCALE
CONTRACTION JOINT SEALANT DETAIL
BOND BREAKING TAPE OR
SEPARATING MATERIAL
(3mm WIDER THAN
NOMINAL WIDTH OF JOINT)
COMPRESSIBLE, NONSHRINKING, NONSTAINING,
NONREACTIVE TO SEALANT AND
NON-ABSORPTING FILLER MATERIAL
EXTRUDED BUTYL OR
POLYCHLOROPRENE FOAM RUBBER
3 (MIN)
T
O
T
O
13 TO 16
POURED JOINT SEALANT
4C
4D
4E
4F
4G
4H
4I
4J
4J1
4J2
4G
4G
4I
4H
4H
4J2
4G
4A
4B
REPAIR PARKING AREA NEAR FIRE
STATION AND MOTOR POOL
107195
EXISTING MANHOLE MODIFICATION
E X
S T
P O
R T
IO
N
T O
R E
M A
IN
1200200 200
ALL CONCRETE DUST, & RUST (TYP)
CLEAN EXISTING REBAR TO REMOVE
ROUGHEN, CLEAN &
TO POURING CONCRETE
APPLY EPOXY PRIOR
EXST REINFORCING
D10 BARS @ 300mm OC
NEW TOP OF MANHOLE
CI MANHOLE COVER OR STEEL GRATING COVER
E X
T E
N S
IO
N
L A
P S
P L
IC
E
V A
R
IE
S
TOP OF PAVED
CONC COLLAR
FIN GRADE
300 300
D10 BAR @ 200mm OC
D13 BAR @ 200mm OC
EXST TOP OF MH
- 5
SCALE: NONE
CIVIL
C-5
AS SHOWN
CHOE, S M. WARRIOR BASE
REPAIR PARKING AREA NEAR FIRE
STATION AND MOTOR POOL
107195
A
B C D
E F G H
SYMBOL BY
DESIGNED BY
ENERGY MANAGER
SUBMITTED BY
USING AGENCY
APPROVED BY
PROJECT NO. DRAWING NO. REF NO.
SCALE :
ZONE DATE APVD.
UTILITIES
SHEET OF
REVIEWED BY
DESCRIPTION
BLDGS & GROUNDS
CHIEF, ENGR’G DIV
FORCE PROTECTION
CHK’D
REVISIONS
IMCOM
FIRE & EMERGENCY SVC
SAFETY
ENVIRONMENT
DEPARTMENT OF THE ARMY
US ARMY INSTALLATION MANAGEMENT COMMAND
HEADQUARTERS, UNITED STATES ARMY GARRISON, RED CLOUD
ENGINEERING DIVISON, DPW, USAG-RED CLOUD
UNIT #15707, APO AP 96258-5707
MISC. DETAIL
15025
AC PAVEMENT
R=13
10 THICK EXPANSION
JOINT W/ SEALER
SEE PLAN FOR FINISH
R R
NFSM
"C"
"C
CAST IN PLACE
CONCRETE CURB
21 MPa
NOTE ;
1. PROVIDE EXPANSION JOINTS AT MAX. 15.0 M.
INTERVALS (MATCH SIDEWALK)
2. "C" DIMENSION CONSTANT EQUALS PAVEMENT
SECTION MINUS 300.
3. CONCRETE COMPRESSIVE STRENGTH SHALL BE
21 MPa AT 28 DAYS.
EXISTING MANHOLE MODIFICATION1
- 5
SCALE: NONE
| 107195-1 |
| 107195-2 |
| 107195-3 |
| 107195-4 |
| 107195-5 |
| 107195-6 |
File details come from the government source that posted it. Updated .