W91QVN-17-R-0003
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
Repaint Gen exteriors, Bldg's
FFP
No. 1778 thru 1787 (Total 10 each Gen's buildings) FOB: Destination
PURCHASE REQUEST NUMBER: F3J3CE6166A002
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
War Hazard
FFP
Expected Losses from War Hazard are Zero (0) FOB: Destination
NET AMT
Section C - Descriptions and Specifications
Notice to Offerors Regarding Logistics Cost Sharing (LCS) Program:
This solicitation is conducted under the LCS program and will result in a contract between the Government of the Republic of Korea (ROK) and the contractor. ROK will directly pay the contractor. No appropriated funds of the United States (US) shall be obligated for payment due under this contract.
In accordance with the International Agreement between the US and ROK, titled “Amendment to the Implementing Agreement between the United States Forces Korea and the Republic of Korea Ministry of National Defense Concerning Logistics Cost Sharing” (hereinafter “International Agreement”), signed by the parties on 14 October 2015:
"The parties hereby agree that all LCS work must be accomplished in the ROK or its territorial waters and that all equipment and supplies that are to be acquired with ROK Government funds shall be manufactured in the ROK, and all LCS service work shall be carried out by Korean contractor(s), the Korea Railroad Corporation, or the ROK military. The term ‘Korean contractor(s)’ is defined as an entity, that, including its parent, is a domestic corporation under the Korean Tax Act and whose domestic status is recorded in the Certified Copy of Register or its successor document. A parent is defined as an entity that holds more than 50/100 of the total issued and outstanding shares in another company, as reflected in the Stock Change Certificate.”
See Section L, Instructions to Offerors, for submission requirements related to LCS solicitations.
SOW
TECHNICAL PROVISIONS - I
STATEMENT OF WORK
PROJECT NO. TITLE LOCATION
| 83910 | Repaint the outside of the Gen's Buildings, | Osan AB |
| 1778~1787 (total 10 each Gen's buildings) |
1. GENERAL: The work to be performed for completion of this project shall be as described below, and executed by the contractor. The Contractor shall provide all labor, tools, equipment, transportation, materials and other necessary resources for the Projects to repair Hardened Aircraft Shelters (HAS) and A-10 Flows Aircraft Shelters, in accordance with the Statement of Work (SOW), technical detail specifications and drawings.
*CONTRACT TYPE: This is an individual work plan task order.
1.1 Work by Contractor: The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as listed below and in accordance with the drawings, sketches and specifications.
1.2 Work by In-House Forces: Not applicable to this project.
1.3 Work by Troop Labor: Not applicable to this project.
2. PRINCIPAL FEATURES: This project includes the following principal features:
2.1. Schedule #I, Repair (K): All work shall be in accordance with the attached drawings and specifications.
2.1.1. Architectural Work
2.1.1.1. Provide double steel pipe scaffolding around the buildings for temporary works including fabricating and dismantling.
2.1.1.2. Repair of moving cracks larger than 3mm (1/8 inch) in diameter shall be by routing out and filling the crack using an approved urethane caulk or other crack repair materials. Cracks larger than 6 mm (1/4 inch) in diameter shall be routed out and fitted with approved polyethylene backer rod prior to caulking or applying other crack repair materials.
2.1.1.3. Clean and prepare the concrete surface areas with water jet cleaning such as exterior arched roof, roof over baffle, exterior wall of baffle, exterior wall of bulkhead and rear to apply acrylic fluid-applied water proofing coating system by removing all loose/flaking particles, grease, laitance, jagged steel reinforcing bar, dust, dirt and other contaminants.
2.1.1.4. After removing any loose debris and contamination from the existing pits or holes or cracks all over the concrete surfaced areas, fill them with approved concrete repair materials so that they are flush with the surrounding substrate.
2.1.1.5. Spalled sections of the concrete should be resurfaced using approved slurry-coat of concrete repair materials, trowelled smooth over the affected area.
2.1.1.6. Prepare the concrete surfaced areas with concrete grinding and plastering to correct irregularities and roughness.
2.1.1.7. Apply primer of foundation coat - reinforcing fabric - second base coat - finish coat - second finish coat on the concrete surfaced areas according to the standard procedure of acrylic fluid-applied water proofing coating system. The total dry film thickness (DFT) required at any locations shall be at least 40 mils more and the colors shall be according to the HAS exterior finish standard in Osan AB architectural compatibility plan.
2.1.1.8. Clean and prepare the ferrous surface areas such as interior metal arched panel (SSPC SP 10), shelter door trim (SSPC SP 6), personnel door/frame (SSPC SP 6), metal plate (SSPC SP 6), rear door (SSPC SP 6) according to SSPC (Steel Structure Painting Council) procedure of standard surface preparation (SP) in the O&MA Specification.
2.1.1.9. Apply the MPI (Master Painters Institute) approved epoxy gloss paint/coating with the primer designated by manufacturer on the interior metal arched panels including all electrical and mechanical items. The color shall be according to the HAS interior finish standard in Osan AB architectural compatibility plan.
2.1.1.10. Apply the MPI approved alkyd exterior semi-gloss or exterior water-based light industrial coating semi-gloss paint/coating with the MPI approved alkyd anti-corrosive metal primer on the shelter door trim, personnel door/frame, metal plate, rear door. The color shall be according to the HAS interior finish standard in Osan AB architectural compatibility plan.
2.1.1.11. Apply the MPI approved exterior latex flat paint/coating with primer on the concrete surfaced shelter door inside and outside. The color shall be according to the HAS interior finish standard in Osan AB architectural compatibility plan.
2.1.1.12. Re-stencil the building numbers and warning signs on existing wall, door, and floor of the HASs and Flow shelters as it used to be.
2.1.1.13. Remove all debris originated from this project and clean up the job site.
2.1.1.14. The contractor shall be responsible for repairing all damage to existing areas caused by this project and to match condition to adjacent areas.
3. CONTRACT PERFORMANCE PERIOD: 160 calendar days after receipt of the Notice to Proceed (NTP).
4. REMARKS:
4.1 This is a ROK LCS funded project. As a result, all the construction materials used on this project shall be purchased locally from Korean manufacturers complying with O&MA specifications, especially paint/coating materials shall be approved by MPI (Master Painters Institute) and acrylic fluid applied water proofing coating shall be approved by ASTM D 6083 (Standard Specification for Liquid Applied Acrylic Coating Used in Roofing) since ROK LCS Funds shall not to be used to purchase off-shore end products.
4.2 FINAL SITE ADAPTED DRAWINGS: The contractor shall complete drawings which consist of conceptual and final adapted drawings with design analysis including engineering calculations and specification. The contractor shall be responsible for its own design, work quality, full compliance with the solicitation and its accepted proposal, and shall be liable for its faults. The contractor shall complete the 100% design drawing package of this project after 14 calendar days (2 weeks) after receipt of notice to proceed on the contract.
4.3 All the work in this project will be performed at Bravo Diamond and A-10 Flows area that are designated as Restricted Areas (RA) in Osan AB. So consideration in your proposal shall reflect with anticipation for break in work schedule due to unexpected aircraft operation or base exercise activities.
4.4 SPECIAL REQUIREMENTS FOR SUBMITTALS (WORK PLAN):
4.4.1. Conceptual Drawing which shall consist of roof plan, front and side elevation, front and side section, exterior and interior finish schedule. The finish schedule in the drawing shall clearly show all materials such as paint/coating with approved MPI numbers, acrylic fluid applied waterproofing materials, crack repair materials using the finish schedule table categorized according to surface area, base material, FSC (Federal Standard Colors) number, surface preparation method, primer/first coat, intermediate coat, top coat, coating system DFT (Dry Film Thickness) and Master Painters Institute (MPI) number/gloss levels in top rows and the related area such as Arched roof, Roof over baffle, Exterior wall of baffle, Exterior wall of bulk head & rear, Metal arched panel area, Shelter door trim, Shelter door surface, Personnel door/frame, metal plate, and rear door in first column on left side
4.4.2 Offer breakdown
4.4.3. Certificates and test reports approved by MPI for paint/coating materials and ASTM D 6083 & ASTM E 108 (Class A) or ASTM D6083 & ANSI/UL 790 for acrylic fluid-applied water proofing coating materials.
TECHNICAL PROVISIONS - II
TECHNICAL DETAIL SPECIFICATIONS
PROJECT NO. TITLE LOCATION
| 83910 | Repaint the outside of the Gen's Buildings, | Osan AB |
| 1778~1787 (Total 10 each Gen's buildings) |
1. GENERAL: The project shall comply with the “Standard Technical Specifications for O&MA Projects, Korea” dated 24 January 2014 by the Department of the Army, Installation Management Command. The current specifications are available through US Forces Korea (USFK) website http://www.usfk.mil/Portals/105/Documents/Contracting/NewContract/2014-OMA-SPECS_REVISION-1.pdf. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.
2. OTHER APPLICABLE PARTICULAR SPECIFICATIONS OR GUIDES: The project shall comply with the “Osan AB Architectural Compatibility Plan (Osan AB ACP)” dated 01 January 2009 by the 51st Civil Engineer Squadron, and the particular specification “Section 07141 ACRYLIC FLUID-APPLIED WATERPROOFING”, which is attached below on this solicitation. If there are any conflicts or discrepancies between the O&MA specification and the particular specification or guides, the latter ones shall take precedence over the O&MA Specs.
SECTION 07141
ACRYLIC FLUID-APPLIED WATERPROOFING
TABLE OF CONTENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DELIVERY, STORAGE, AND HANDLING
1.4 JOB CONDITIONS
1.5 WARRANTY
PART 2 PRODUCTS
2.1 ROOF WATERPROOFING SYSTEM MATERIALS
2.2 ROOFING SYSTEM
2.3 WATER REPELLENT COATING MATERIALS
PART 3 EXECUTION
3.1 PRE-ROOFING MEETING
3.2 SURFACE EXAMINATION
3.3 SURFACE PREPARATION
3.4 COATING APPLICATION
3.5 CLEANUP
PART 1 GENERAL
This specification covers a liquid-applied water-dispersed 100 percent acrylic elastomeric latex coating used for roof waterproofing. This specification also covers a water-repellent coating applied to concrete or masonry wall surfaces.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
ASTM B 117 Standard Practice for Operating Salt Spray (Fog) Apparatus
ASTM D 523 Standard Test Method for Specular Gloss
ASTM D 722 Standard Test Method for Grease Resistance of Paper
ASTM D 1475 Standard Test Method for Density of Liquid Coatings, Inks, and Related Products
ASTM D 1640 Standard Test Method for Drying, Curing, or Film Formation of Organic Coatings at Room Temperature
ASTM D 1653 Standard Test Method for Water Vapor Transmission of Organic Coated Films E1-1999 R
ASTM D 1712 Standard Practice for Resistance of Plastics to Sulfide Staining
ASTM D 1729 Standard Practice for Visual Appraisal of Colors and Color Differences of Diffusely-Illuminated Opaque Materials
ASTM D 2244 Standard Test Method for Calculation of Color Differences from Instrumentally Measured Color Coordinates
ASTM D 3359 Standard Test Method for Measuring Adhesion by Tape Test
ASTM D 4214 Standard Test Method for Evaluating the Degree of Chalking of Exterior Paint Films
ASTM D 5034 Standard Test Method for Breaking Strength and Elongation of Textile Fabrics (Grab Test)
ASTM D 5035 Standard Test Method for Breaking Force and Elongation of Textile Fabrics (Strip Method
ASTM D 5201 Standard Practice for Calculating Formulation Physical Constants of Paints and Coatings
ASTM D 6083 Standard Specification for Liquid Applied Acrylic Coating Used in Roofing
ASTM E 96 Standard Test Method for Water Vapor Transmission of Materials
ASTM E 108 Standard Test Methods for Fire Tests of Roof Coverings
ASTM E 514 Standard Test Method for Water Penetration and Leakage Through Masonry.
ASTM G 7 Standard Practice for Atmospheric Environmental Exposure Testing of Nonmetallic Materials
ASTM G 154 Standard Practice for Operating Florescent Light Apparatus for UV Exposure of Nonmetallic Materials
FACTORY MUTUAL ENGINEERING AND RESEARCH (FM)
FM 4470 Approval Standards for Class 1 Roof Covers
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES in O&MA Standard SPEC 2014:
SD-02 Shop Drawings; G
Drawings showing coating system details, flashing details, fastening patterns where applicable for insulation, and expansion joint details.
Detail showing construction of water cutoffs to be used at membrane terminations at the end of a day's work to seal the roofing system from water intrusion.
SD-03 Product Data; G.
Catalog cuts, technical data, product description, illustrations, diagrams, performance charts, brochures, etc...
SD-06 Test Reports; G.
Report signed by authorized official of a certified independent testing laboratory verifying conformance of properties as per ASTM D 6083 and class A fire rating as per ASTM E 108 or Class 1 as per FM 4470.
SD-07 Certificates; G.
Applicator's Qualifications: A copy of approved applicator letter and/or certificate as issued by the manufacturer of the elastomeric acrylic coating system.
SD-08 Manufacturer’s Instruction; G.
Manufacturer's instructions for preparing and applying the membrane, flashings, seams, insulation, nailers and other accessories.
Material safety data sheets (MSDS): all materials required to have MSDS.
1.3 DELIVERY, STORAGE, AND HANDLING
Deliver waterproofing materials in manufacturer's original, unopened containers, with labels intact and legible. Containers of materials covered by a referenced specification number shall bear the specification number, type, and class of the contents. Deliver materials in sufficient quantity to continue work without interruption. Store and protect materials in accordance with manufacturer's instructions, and use within their indicated shelf life.
Materials shall be stored in an area specifically designated for that purpose, in accordance with manufacturer's recommendations, where temperatures will not be less than 10 degrees C (50 degrees F) or higher than 38 degrees C (100 degrees F). When hazardous materials are involved, adhere to special precautions of the manufacturer, unless precautions conflict with local, state, and federal regulations. Promptly remove from the site materials or incomplete work adversely affected by exposure to moisture or freezing. Store materials on pallets and cover from top to bottom with canvas tarpaulins.
1.4 JOB CONDITIONS
Do not apply elastomeric acrylic coating system components when the ambient and/or surface temperature is below 10 degrees C (50 degrees F) or above 43 degrees C (110 degrees F), if any surface moisture is present, when the dew point is within 3 degrees C (5 degrees F) of the surface temperature, or when there is a possibility of temperatures falling below 0 degrees C (32 degrees F) within a 24 hour period. Do not apply if weather conditions will not permit complete cure before rain, dew, fog or freezing temperatures occur. Do not sprays apply if the wind velocity exceeds 16 kilometer per hour (10 MPH) without taking appropriate precautions to eliminate over-spray. Take all measures necessary to protect unrelated surfaces from coating over-sprays or spillage. Furnish all scaffolding and the necessary equipment to complete the work. Scaffolding shall comply with all requirements as to safety. Provide drop cloths and other forms of protection necessary to protect all adjoining surfaces to render them completely free of overspray and splashes. Any surfaces that have been damaged or splattered shall be cleaned, restored, or replaced. If sealant is applied prior to sealer, a test must be conducted prior to installation to verify compatibility of the sealer and sealant. For interior application, provide ventilation or forced air circulation during and after interior application of sealer until any odor is no longer evident.
1.5 WARRANTY
Upon completion of the roof coating system, a final inspection shall take place to determine the dry film thickness (DFT) of the fluid applied acrylic membrane and to verify that the system meets the manufacturer's requirements and project specifications for warranty. The contractor shall notify all interested parties in advance of said inspection. Upon acceptance, deliver to the COR a copy of the fully executed 10-year materials and labor warranty.
PART 2 PRODUCTS
2.1 ROOF WATERPROOFING SYSTEM MATERIALS
A seamless, fluid applied 100 percent acrylic membrane system designed for application over concrete or metal substrates.
2.1.1 Reinforcement Fabric
Non-woven, stitch bonded polyester fabric for reinforcement of joints, horizontal seams, non-crimped vertical seams, damaged areas, roof terminations and flashings, skylights and other openings, vents, conduits, HVAC equipment and other protrusions. Polyester fabric shall meet or exceed the following physical properties:
A. Fabric Weight (ASTM D 3776): 3.0-4.0 oz per square yard
B. Mullen Bursting Strength (ASTM D 3786): 145 lbs per square inch
C. Tearing Strength (Trapezoid, ASTM D 5587): 20 lbs (length), 25 lbs (width)
D. Breaking Force (1" cut strip, ASTM D 5035): 42 lbs (length), 28 lbs (width)
E. Elongation at Break (1" cut strip, ASTM D 5035): 28 percent (length), 80 percent (width)
2.1.2 Fluid-Applied Base Coat (Primer or Foundation Coat)
100 percent pure acrylic co-polymer internally plasticized to maintain elastomeric properties, designed for adding film build prior to application of the intermediate and finish coats.
2.1.3 Fluid-Applied Intermediate Coat and Finish Coat
100 percent pure acrylic co-polymer in the specified finish color internally plasticized to maintain elastomeric properties, designed to provide a permanently flexible, weather-resistant topcoat. Coating material and coating shall meet or exceed all properties specified in ASTM D 6083, as verified by a certified independent testing agency.
2.1.4 Fluid-Applied Encapsulation Coat
100 percent pure acrylic co-polymer, low viscosity, designed to saturate through and encapsulate the Reinforcement Fabric on detail areas as well as the body of the roof. It also penetrates into and seals the existing substrate, while blocking asphaltic bleed-through.
2.1.5 Reinforcement Tape for Metal Roof Surface
Self-adhesive, butyl-backed fabric for use as an alternative to reinforcement fabric in reinforcing joints, horizontal seams, non-crimped vertical seams, damaged areas, roof terminations and flashings, skylights and other openings, vents, conduits, HVAC equipment and other protrusions.
2.1.6 Acrylic Mastic
Single package, high tensile acrylic mastic for use in reinforcing crimped vertical seams, and as an alternative to reinforcement fabric or reinforcement tape on other seams and detail areas. Also used for encapsulating and sealing fastener screws of metal roof.
2.1.7 Concrete Repair Material
High strength acrylic polymer concrete renovation and repair material shall be applied, blended with portland cement at the jobsite. It is for use in repairing damaged mortar, filling voids and resurfacing spalled concrete surfaces.
2.1.8 Fluid-Applied Metal Primer
Single package, acrylic metal primer shall be applied to provide corrosion protection, flash rust resistance and enhanced adhesion over steel, aluminum and galvanized metal roof surfaces.
2.2 ROOFING SYSTEM
The roofing system shall have a Class A fire rating on a noncombustible deck when tested according to the procedures outlined in ASTM E 108.
2.3 WATER REPELLENT COATING MATERIALS
2.3.1 Clear Water repellent sealer
Water repellent sealer shall be a water-based, clear blend of reactive silane with a silicone emulsion designed to provide invisible water-repellency and protection from the intrusion of chloride salts, airborne pollution and deicing chemicals over vertical and horizontal concrete, masonry and brick surfaces. Product is supplied in either a pre-diluted 5 percent solids by volume concentration, or in concentrate form that is diluted at the jobsite to achieve the specified solids, and shall meet the following minimum requirements:
A. Solids by volume: 5 to 10 percent (+/-2) [ASTM D 5201]
B. Viscosity: 1,000 to 1,500 cps at 24 degree C (75 degree F) [ASTM D 2196]
C. Dry time: 15 to 20 minutes at 24 degree C (75 degree F), 50 percent R.H.
[ASTM D 1640]
D. Cure time: 1 to 2 hours at 24 degree C (75 degree F), 50 percent R.H.
[ASTM D 1640]
E. Temperature Limits for Service Conditions: -56 degree C to 93 degree C (-70 degree F to 200 degree F)
F. Resistance to Accelerated Weathering: Treated specimen shall show no deleterious effects, no surface checking, cracking or delamination after 3,000 hours of testing in accordance with ASTM G 154 in a QUV cabinet.
G. Resistance to Wind Driven Rain: After 40 hours of continuous testing, treated precast concrete panel shall show no apparent moisture penetration into the substrate. Test conducted in a pressurized test chamber producing
12.7 cm (5 inch) of water pressure, equivalent to 100 mph wind pressure (161km/hr) as per ASTM E 154.
H. Resistance to Salt Spray: Treated sample shall show no deleterious effects, no surface checking, cracking or delamination following 500 hours of continuous exposure. Testing shall be in accordance with ASTM B 117 in a Harshaw Salt Spray Cabinet. Test specimens shall be treated cement asbestos board or equal.
I. Resistance to Sulfide Staining: No discoloration after 15 minutes immersion in saturated hydrogen sulfide gas solution when tested in accordance with ASTM D 1712. Compare with control specimen not exposed to hydrogen sulfide gas solution.
J. Resistance to Chemical Reagents: Specimen shall exhibit none or slight color change and no softening or deterioration after 7 days immersion in the following chemicals: ammonium hydroxide - 10 percent; sodium hydroxide
- 10 percent; mineral spirits, KB value 38. Inspection is compared to specimen not exposed to chemical reagents.
K. Verification of Minimum 5-Year Exposure to Appropriate Climate: Sealer shall have been in use in a similar climatic region 5 years or more and show no sign of fading, peeling or flaking. Supply project locations exceeding 5 years of service.
L. Moisture Vapor Transmission: Must allow moisture from building interior to pass through the substrate and stain with a perm rating of greater than
5.00 when tested in accordance with ASTM E 96.
2.3.2 Water repellent stain
Water repellent stain shall be an water-based, modified acrylic, penetrating stain designed to provide long term color uniformity, ultraviolet resistance, alkali and pollution resistance, plus water repellency without disturbing the natural texture of the substrate. It shall be for use over vertical, abovegrade, smooth or textured concrete, exposed aggregate concrete, glass reinforced concrete, brick, stone, stucco and other masonry surfaces. Water repellent stain shall meet the following minimum requirements:
A. Solids by volume shall be a maximum of 30 percent (+/-2) [ASTM D 2697]
B. Weight per gallon shall be a minimum of 9.2 (+/-.2) lbs. [ASTM D 1475]
C. Dry time shall be 15 minutes at 24 degree C (75 degree F), 50 percent R.H.
[ASTM D 1640]
D. Cure time shall be 1 hour at 24 degree C (75 degree F), 50 percent R.H.
[ASTM D 1640]
E. Gloss (Angular Reflectance) shall be 4 at 60 degree Gardner [ASTM D 523]
F. Adhesion to Concrete shall be a minimum of 700 lbs./sq. in. [ASTM D 3359]
G. Temperature Limits for Service Conditions shall range from -56 degree C to 93 degree C (-70 degree F to 200 degree F).
H. Toning pigments shall be inorganic oxides.
I. Resistance to Accelerated Weathering: Color retention and ultraviolet resistance of the treated specimen shall meet the following requirements after 3,000 hours of testing in accordance with ASTM G 154 in a QUV cabinet.
1. Color Retention: Within five (5) N.B.S. (National Bureau of Standards) units when tested in accordance with ASTM D 2244; or shall show no appreciable change when tested in accordance with ASTM D 1729. Inspection is compared to unweathered specimen.
2. Ultraviolet Resistance: No chalking or flaking when tested in accordance with ASTM D 4214 and D 722.
J. Resistance to Accelerated Atmospheric Exposure: Specimen shall exhibit no visible change after 12-month exposure in accordance with ASTM G 7.
K. Resistance to Salt Spray: Color retention and degree of efflorescence of the treated specimen shall meet the following requirements after 500 hours of testing in accordance with ASTM B 117 in a Harshaw Salt Spray Cabinet.
1. Color Retention: Within five (5) N.B.S. (National Bureau of Standards) units when tested in accordance with ASTM D 2244; or shall show no appreciable change when tested in accordance with ASTM D 1729. Inspection is compared to unweathered specimen.
2. Degree of Efflorescence: Specimen shall exhibit no efflorescence. L.
Resistance to Sulfide Staining: No discoloration after 15 minutes immersion in saturated hydrogen sulfide gas solution when tested in accordance with ASTM D 1712. Compare with control specimen not exposed to hydrogen sulfide gas solution.
M. Resistance to Chemical Reagents: Specimen shall exhibit none or slight color change and no softening or deterioration after 7 days immersion in the following chemicals: ammonium hydroxide - 10 percent; sodium hydroxide
– 10 percent; mineral spirits, KB value 38. Inspection is compared to specimen not exposed to chemical reagents.
N. Verification of Minimum 10 Year Exposure to Appropriate Climate: Stain shall have been in use in a similar climatic region 10 years or more and show no sign of fading, peeling or flaking. Supply project locations exceeding 10 years of service.
O. Moisture Vapor Transmission: Must allow moisture from building interior to pass through the substrate and stain with a perm rating of greater than
5.00 when tested in accordance with ASTM E 96.
PART 3 EXECUTION
3.1 SURFACE EXAMINATION
Verify that all surfaces are ready to receive work. Roof surfaces shall be clean, dry, structurally sound, stable and well secured. The roof surface shall be free of excessive ponding water. A roof surface that allows standing water 48 hours after a rain shall be considered unacceptable. All water shall be allowed positive drainage from the roof. Inspect condition of flashing details adjacent to protrusions, penetrations, roof mounted equipment, curbs, walls, parapets, drains and roof edge to ensure that details are acceptable and will maintain a weather-tight installation after being properly detailed and coated. Inspect parapets to ensure that concrete, masonry or metal caps are sound. Caulk, reinforce or replace as necessary in order to bring parapet and parapet cap into a weathertight condition. Determine moisture content of existing substrate, insulation and deck. Moisture content of 15 percent or greater indicates a potential problem. Work shall not proceed until the cause of high moisture content is verified and condition is corrected.
3.2 SURFACE PREPARATION
3.2.1 CONCRETE ROOFING SUBSTRATE
3.2.1.1 All surfaces shall be clean and dry, and free of any dirt, dust, gravel, oil, surface chemicals or other contaminants that may interfere with optimum adhesion.
3.2.1.2 Any unsound areas in the roof deck, including deterioration, pitted or spalled concrete, excessive moisture content, etc. shall be repaired or replaced.
3.2.1.3 Roof deck areas shall have positive slope-to-drain. Tapered insulation, cant strips, spray-applied polyurethane foam or other similar materials shall be used to build up affected roof surfaces as necessary.
3.2.1.4 Fill any pits or holes in the concrete with concrete repair material so they are flush with the surrounding substrate. Spalled sections of the concrete should be resurfaced using a slurry-coat of concrete repair material, trowelled smooth over the affected area.
3.2.1.5 "Moving cracks" larger than 3 mm (1/8 inch) in diameter shall be routed out and filled using an approved urethane caulk. Cracks larger than 6 mm (1/4 inch) in diameter shall be routed out and fitted with polyethylene backer rod prior to caulking.
3.2.1.6 Inspect parapets to ensure that concrete, masonry, wood or metal caps are sound. Caulk, reinforce or replace as necessary in order to bring parapet and parapet cap into a weathertight condition.
3.2.1.7 All concrete surfaces, whether new or existing, shall be cleaned using an approved biodegradable cleaner, following manufacturer's instructions. Rinse thoroughly with fresh water under high pressure (minimum 2,000 psi - 13,790 Kpa) to remove the solution from the roof. Heavy deposits of dirt or contamination may require agitation with a stiff-bristle broom or similar mechanical scrubber. Allow the roof to dry thoroughly.
3.2.1.8 Prime all concrete surfaces with one coat of concrete prime material at a rate according to manufacturer's instruction to seal and solidify the surface.
3.2.1.9 Reinforce all "moving" cracks and/or seams, control joints, vertical/horizontal interfaces, roof termination points, openings, around the base of all vents pipes and other protrusions, as well as HVAC units and other roof mounted equipment with reinforcement fabric embedded into encapsulation coat. Cut a strip of reinforcement fabric (width depending upon the detail) to the desired length, and center it over the detail area. Apply encapsulation coat liberally from the top side using a brush or roller, working the encapsulation coat into the fabric so as to eliminate air pockets, wrinkles and gaps. Ensure that the reinforcement fabric is thoroughly saturated, encapsulated and fully adhered to the substrate.
3.2.2 METAL ROOFING SUBSTRATE
3.2.2.1 Metal surfaces to be coated shall be clean, dry, sound, and free of dirt, grease, oil, and any other contaminants that might interfere with the adhesion of the elastomeric acrylic coating.
3.2.2.2 All mechanical fasteners shall be checked for integrity. Retighten or replace as necessary. "Stripped out" fasteners shall be replaced using a larger diameter fastener.
3.2.2.3 Unsound rust shall be wire brushed, sandblasted or mechanically abraded to remove all loose rust. Metal panels deteriorated to the point that their structural integrity is compromised shall be replaced.
3.2.2.4 Remove excessive amounts of asphaltic-based or other deteriorated patching/flashing materials if present.
3.2.2.5 Check all seams to ensure that they are tight and flush. Excessive gaps or deflection between panels shall be eliminated by installing additional screws or rivets as necessary to restrict deflection to 6 mm (1/4 inch) or less.
3.2.2.6 All metal surfaces, whether new or existing, shall be cleaned using an approved biodegradable cleaner, following manufacturer's instructions. Rinse thoroughly with fresh water under high pressure (minimum 2,000 psi - 13,790 Kpa) to remove the solution from the roof. Heavy deposits of dirt contamination may require agitation with a stiff-bristle broom or similar mechanical scrubber. Allow the roof to dry thoroughly.
3.2.2.7 All existing "sound" rusted areas shall be primed with metal primer according to the manufacturer's instructions.
3.2.2.8 If the roof has been previously coated with aluminized asphalt of any kind, a penetrating primer must apply to prevent potential "leafing" of the surface. Consult coatings manufacturer prior to application of the acrylic coating system over aluminized asphalt surfaces.
3.2.2.9 Fill gaps between 6 and 13 mm (1/4 and 1/2 inch) at panel seams, joints and protrusions with an approved single-component urethane caulk. Fill gaps larger than 13 mm (1/2 inch) such as at the ridge cap, roof edge and/or interface of dissimilar materials, using polyethylene backer rod or spray applied polyurethane foam.
3.2.2.10 All horizontal (end-lap) seams and vertical (side-lap) seams which have not been factory crimped or presealed, roof terminations and flashings, around drains, scuppers and skylights, and the base of all vents, conduits, HVAC equipment and other protrusions shall be reinforced using one or more of the following methods:
A. Apply base coat acrylic elastomer liberally, using a brush or roller, along the area to be detailed. While the base coat is still wet, embed a strip of 15 to 30 cm (6 to 12 inch) reinforcement mesh for end-lap seams.
For side-lap seams, use 5 to 10 cm (2 to 4 inch) reinforcement mesh, as per detail requirements, centered over the seam, joint or interface. Work the reinforcement mesh into the base coat, applying additional material as necessary to totally encapsulate the reinforcement fabric.
B. Cut a length of 15 cm (6 inch) reinforcement tape to the desired length, peel off the release backing, center over the end-lap detail area and press firmly into place, removing all wrinkles and bubbles. For side lap seams 5 to 10 cm (2 to 3 inch) reinforcement tape may be used. A wallpaper seam roller is helpful in securing the reinforcement tape to the metal deck.
C. Apply a minimum of two (2) coats of acrylic mastic, using a brush, roller or airless spray, to a total thickness of 60 to 80 dry mils (1,524 to 2,032 microns) over the detail area. Extend the sealant a minimum of 8 cm (3 inch) on either side of seams, joints and interfaces.
3.2.2.11 At the interface of any metal with a dissimilar material, detail the joint using one of the following methods:
A. Apply 15 cm (6 inch) reinforcement mesh embedded into base coat as previously described in 3.3.3.10 a.
D. Apply a strip of 15 cm (6 inch) reinforcement tape as previously described in 3.3.3.10 b.
E. Apply two (2) coats of acrylic mastic to a total thickness of 60 to 80 mils (1,524 to 2,032 microns) as previously described in 3.3.3.10 c.
3.2.3 SURFACE PREPARATION FOR WATER REPELLENT SEALER AND STAIN
Surfaces to receive water-repellent sealer or stain shall be structurally sound, clean, dry, fully cured, and free from dust, efflorescence, scale, or other foreign materials. Methods and materials used for cleaning of substrate shall be as recommended by the manufacturer of the water-repellent sealer or stain. Materials such as curing agents, form release agents, bond breakers and other concrete production materials shall be completely removed in accordance with the particular manufactures printed instructions for removal prior to coating application.
3.3 COATING APPLICATION
3.3.1 CONCRETE ROOFING SUBSTRATE
3.3.1.1 All detail work shall be allowed to dry thoroughly prior to application of the acrylic coating.
3.3.1.2 Immediately prior to application of the acrylic coating system, all dust, dirt and other contaminants shall be blown off the roof surfaces to be coated using high pressure compressed air.
3.3.1.3 Apply encapsulation coat to a small section of roof where the fabric reinforcement will begin. Embed and encapsulate the end of the reinforcement fabric roll so that it is anchored at that point. Roll out a 1.2 to 3 meter (4 to 10 foot) section of fabric, and either spray apply or pour encapsulation coat evenly over the top side at the rate according to the manufacturer's instructions, allowing the fabric to conform to the surface contours. Work the encapsulation coat evenly throughout the fabric using a soft-bristle broom or roller so that it is totally encapsulated, eliminating any air pockets, wrinkles or gaps. Take extra care to ensure that edges of the fabric are well saturated and adhered. Overlap consecutive passes of reinforcement fabric a minimum of 5 cm (2 inch) on each side. Use encapsulation coat to embed reinforcement fabric in this manner over all concrete roofing surfaces.
3.3.1.4 Substrate porosity and texture will determine the amount of encapsulation coat required to saturate and encapsulate the reinforcement fabric. Allow the encapsulation coat to dry thoroughly prior to applying the base coat to the roof.
3.3.1.5 Apply base coat, using airless spray or roller, at the rate according to the manufacturer's instructions.
3.3.1.6 After allowing base coat to dry thoroughly, apply intermediate coat (in desired color), using airless spray or roller, at the rate according to the manufacturer's instructions. Apply intermediate coat in a perpendicular direction to the base coat.
3.3.1.7 After allowing intermediate coat to dry thoroughly, apply finish coat (in desired color), using airless spray or roller, at the rate according to the manufacturer's instructions. Apply finish coat in a perpendicular direction to the intermediate coat.
3.3.1.8 The total minimum dry film thickness required at any location shall be 40 mils (1,016 microns).
3.3.1.9 The top coat shall extend up and over the top of all parapets, as well as all vent pipes and other protrusions, to terminate a minimum of 7.6 cm (3 inch) above the substrate, creating a self-terminating flashing and so as to provide an aesthetically pleasing appearance. To lock in the system at perimeter walls, wrap the fabric up the parapet and under the counter-flashing, or up and over the parapet, extending down onto the front face.
3.3.2 METAL ROOFING SUBSTRATE
3.3.2.1 All detail work shall be allowed to dry thoroughly prior to application of the acrylic coating.
3.3.2.2 Immediately prior to application of the acrylic coating system, all dust, dirt and other contaminants shall be blown off the roof surfaces to be coated using high pressure compressed air.
3.3.2.3 Apply base coat, using airless spray or roller, at the rate according to the manufacturer's instructions.
3.3.2.4 After allowing base coat to dry thoroughly, apply intermediate coat (in desired color), using airless spray or roller, at the rate according to the manufacturer's instructions. Apply intermediate coat in a perpendicular direction to the base coat.
3.3.2.5 After allowing intermediate coat to dry thoroughly, apply finish coat (in desired color), using airless spray or roller, at the rate according to the manufacturer's instructions. Apply finish coat in a perpendicular direction to the intermediate coat.
3.3.2.6 The total minimum dry film thickness required at any location shall be 30 mils (762 microns).
3.3.2.7 The top coat shall extend up and over the top of all parapets, as well as all vent pipes and other protrusions, to terminate a minimum of 7.6 cm (3 inch) above the substrate, creating a self-terminating flashing and so as to provide an aesthetically pleasing appearance. To lock in the system at perimeter walls, wrap the fabric up the parapet and under the counter-flashing, or up and over the parapet, extending down onto the front face.
3.3.3 WATER REPELLENT SEALER AND STAIN APPLICATION
Mixing and application of water-repellent sealer and stain shall be in accordance with manufacturer's printed application instruction. Applicator shall apply a field test on a small inconspicuous area of the actual building surface to determine the best absorption rate to achieve color uniformity, as well as to determine suitability of the application technique.
3.4 CLEANUP
3.4.1 Maintain work and work areas in accordance with clean, safe condition at all times during coating installation. Remove excess materials, trash and debris daily.
3.4.2 At the completion of the project, clean area of any spills and containers, and clean up all roofing debris, leaving jobsite in a clean and orderly condition.
APPENDIX "A"
LIST OF APPLICABLE CONTRACT DRAWINGS
GENERAL: The work shall conform to the drawings, all of which form a part of the specifications. The drawings are from the “Standard Detail Drawings for OMA Projects, Korea”, dated 1 October 2003, issued by the Department of the Army, Installation Management Agency, Korea Region Office
| Drawing | Sheet | Reference | ||
| Number | Number | Number | Description | Date |
1 of 1 T-001 Floor Plan 10 Sep 15
Section F - Deliveries or Performance
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 160 calendar days after Notice of Proceed (NTP). The time stated for completion shall include final cleanup of the premises.
(End of clause)
Section J - List of Documents, Exhibits and Other Attachments
SUMITTAL REGISTER
Note 1: The Submittal Register in Section J above, identifies the documentation that will be made available for approval and review by the Government in the performance of this task order. It is the contractor's responsibility that this data is in compliance with the corresponding OMA specification that is referenced.
Section K - Representations, Certifications and Other Statements of Offerors
52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)
(a) The offeror certifies that --
(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –
(i) Those prices,
(ii) The intention to submit an offer, or
(iii) The methods of factors used to calculate the prices offered:
(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and
(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.
(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --
(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or
(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);
(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and
(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.
(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.
(End of Provision)
5152.204-4032 REPRESENTATIONS AND CERTIFICATIONS
(a) SUBCONTRACTING:
If the offeror contemplates subcontracting, it must obtain prior written approval of subcontractor from the PCO or ACO, and list below: (1) the names and addresses of the subcontractor(s), (2) the type of subcontracting, and (3) the estimated price for each subcontract.
(b) AFFILIATED OFFERORS:
(1) Business concerns are affiliates of each other when, either directly or indirectly, one concern controls or has the power to control the other, or a third party controls or has the power to control both.
(2) Each offeror shall furnish, below, the following information:
(i) Whether the offeror has any affiliates;
(ii) The names and addresses of all affiliates of the offeror; and
(iii) The names and addresses of all persons and concerns exercising control or ownership of the offeror and any or all of its affiliates, and whether they are common officers, directors, stockholders holding controlling interest, or otherwise.
AFFILIATED CONCERNS. : (Name, location and, in detail, controlling interest in each)
(c) PRINCIPAL OWNER(S) OR STOCKHOLDER(S):
Each offeror shall list below the name(s) and address(es) of the principal owner(s) or stockholder(s) of the company and percentage of ownership. If a major portion is publicly traded and/or otherwise widely distributed, state that, with the percentage so affected.
(d) STANDARDS OF CONDUCT CERTIFICATION:
This is to certify that, to the best of my knowledge and belief, except as described below, no representative of this firm who deals with US Government employees on any aspect of this procurement is a former US Government employee, to include former US military personnel. I understand that this certification is continuing in nature and places a duty on me and my firm to notify the Contracting Officer of any additional individual(s) who fit the above description prior to the individual's assuming duties.
(i) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
(ii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
(iii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
Firm ____________________________________________________ Name _____________________________________________________ Signature __________________________________________________
Title _____________________________________________________ Date of Execution ____________________________________________
(e) TAXES:
(1) References:
(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."
(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.
(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.
(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.
(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
This item will be imported specifically for this contract? Yes _____ No _____
(ii) Special Excise Tax:
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
Name of item manufacturer
(iii) Value Added Tax (VAT):
Input VAT on materials purchased for this contract. 10% _____ Input VAT on transportation leased/rented for this contract.10% _____ Input VAT on equipment leased/rented for this contract. 10% _____ Input VAT on services purchased for this contract. 10% _____ Output VAT on total contract amount. 10% _____
(iv) Special Excise (Petroleum) Tax:
No. of U/P Liters w/o Tax Tax/Unit Total Tax Amount Regular Gasoline ________ (L) ________ w________ w_____________ Premium Gasoline ________ (L) ________ w________ w_____________ Diesel ________ (L) ________ w________ w_____________ Other ________ (L) ________ w________ w_____________
(v) Education Tax.
(3) Name of the oil company from which POL products will be purchased:
Oil Company: _________________________________________ (Name only)
(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.
Signed (Chop)
(f) CERTIFICATIONS AND REPRESENTATIONS
By submitting an offer, each offeror agrees to be bound by all certifications and representations in this solicitation. The Government reserves the right to require any and all certifications and representations to be completed and signed in hard copy by the successful offeror prior to contract award. Failure of an offeror to complete the certifications and representations within the time directed by the Contracting Officer may result in a determination that the contractor is not a responsible offeror for this acquisition.
5152.232-4028 – Funding of ROK MND Contracts
FUNDING OF ROK MND CONTRACTS
(a) This is a contract between the Government of the Republic of Korea (ROK) and the contractor. ROK will directly pay the contractor.