Amendment_Questions.pdf
PDF 6 KB Posted
- Attached to
- Cloud-based, web-scale Library Service Platform (LSP) Federal contract opportunity
- Solicitation number
- W91QF419Q0018
About this file
Amendment Questions with answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Changes-Outline_06-26-19.pdf | ||
| 20190614_LED_Requirements_final.docx | DOCX document | |
| W91QF4-19-Q-0018_0002_Amendment.pdf | ||
| 20190418_Solicitation_Questions_Response.pdf | ||
| 20190409_SolAmended_W91QF419Q0018-0001.pdf | ||
| 20190405_Attachment1_RequirmentsDescription_Final.pdf | ||
| 20190405_Sol_W91QF419Q0018.pdf | ||
| 20190405_Attachment1_RequirmentsDescription_Final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Can you identify the specific changes made to the new LED Requirements document v15 when compared with the 20190405_Attachment1_RequirmentsDescription_Final document included in the original solicitation?
A1. An outline of the major changes is included here. Major changes include Security requirements, Discovery definitions and requirements and deletion of a few requirements
(barcodes, versioning, ect....)
2. Should the acknowledgement of the amendment be returned with our new RFP response or should it be returned separately to you?
A2. An acknowledgement of the original solicitation and all posted amendments should be included with the submission.
3. Should we resubmit all forms, including updated signature pages with our new RFP response?
A3. Yes
4. Is pricing to be resubmitted using the same 20190409_SolAmended_W91QF419Q0018-0001 document?
A4. Yes, please submit pricing using the W91QF419Q0018-0001 document
5. We have one question regarding Appendix C in the RFI. Are the migration and implementation dates listed up-to-date with the new timeline?
A5. That is our hope but per 4.1.1. J Government preferred migration timetable is listed in
Appendix C. Any other proposed timeline must have all migration tasks and GO live dates completed 60 days before identified legacy system sunset dates. All Discovery system setup must begin on contract start date.
File details come from the government source that posted it.