This is a Performance Work Statement (PWS) for year-round cleaning and landscape maintenance services at the Class of 1961 Reconciliation Plaza located at the United States Military Academy, West Point, New York. The contract is effective November 2, 2026.

The Contractor shall provide comprehensive maintenance of a plaza containing sixteen inscribed stone monuments, mulched planting beds, granite edging, shrubs, and seasonal annuals. Services include initial seasonal opening by five business days before the first scheduled April reunion; eight monthly service visits from April through November; four monthly inspection and cleanup visits from December through March; cleaning of all sixteen monuments during every scheduled visit using non-aggressive, stone-safe methods; planting and maintenance of seasonal annuals; mulch and edging maintenance at two to three inches settled depth; plant replacement within five business days of identified failures; watering services using contractor-provided potable water; and debris removal. Paved pedestrian areas are excluded from maintenance. The Contractor must submit a work site accident prevention plan before work starts, obtain Government acceptance of proposed cleaning products and planting materials at least fifteen calendar days before initial use, and provide service reports within two business days after each visit and an annual summary within five business days after the November visit. All contractors must complete antiterrorism awareness training and iWATCH briefing training, obtain installation access credentials, and comply with security protocols. The contract requires reporting of all contractor and subcontractor labor hours through the System for Award Management (SAM) Service Contract Report by October 31 each year. Performance standards require 100 percent completion of scheduled service cycles, at least ninety-five percent bed area compliance, at least ninety percent healthy annuals, 100 percent timely incident reporting with zero unreported damage, and pressure washing of monument stone is prohibited.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

The Class of 1961 Reconciliation Plaza Maintenance

2 November 2026

PART 1

GENERAL INFORMATION

1. General: This is a non-personal service(s) contract under which the personnel rendering the service(s) are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees.

1.1 Description of Services/Introduction: This is a non-personal services contract to provide year-round cleaning and landscape maintenance of the Class of 1961 Reconciliation Plaza.

1.2 Background: The plaza contains sixteen (16) inscribed stone monuments: thirteen (13) within the principal planting bed and three (3) outside it. Other features include rough-cut stone bases, granite edging, mulched planting beds, shrubs, and seasonal annuals.

1.3 Scope: The Contractor shall provide the labor, supervision, plants, mulch, materials, tools, equipment, transportation, and water needed for the services in Part 5. Landscape maintenance applies to the principal planting bed and granite edging. The Contractor shall clean all sixteen (16) monuments during every scheduled service visit, including the three (3) monuments outside the principal bed; landscape maintenance at those three monuments is excluded. Paved pedestrian areas are excluded from cleaning, inspection, and maintenance.

The Contractor shall remove and dispose of all waste generated by its work.

1.4 Objectives: The objective of this contract is to provide clean monuments, healthy plantings, neat beds and edging, and a respectful appearance suitable for reunions and public use.

1.5 General Information:

1.5.1 Quality Control: The Contractor shall inspect completed work, correct deficiencies attributable to its performance at no additional cost, and prevent recurrence. No separate quality control plan or recurring quality control report is required.

1.5.2 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).

1.5.3 Recognized Holidays: Work shall not be performed on federally recognized holidays or during Government-directed closures unless authorized by the Contracting Officer (KO). If a submission is due on a holiday, it is due on the preceding business day.

New Year’s Day January 1 Birthday of Martin Luther King, Jr. Third Monday in January Washington’s Birthday (Presidents Day) Third Monday in February Memorial Day Last Monday in May Juneteenth National Independence Day June 19 Independence Day July 4 Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day November 11 Thanksgiving Day Fourth Thursday in November Christmas Day December 25

When a holiday falls on Saturday, it is observed on the preceding Friday; when it falls on Sunday, it is observed on the following Monday.

1.5.4 Operating Hours: Perform work between 0800 and 1600, Monday through Friday, unless otherwise authorized by the KO. Coordinate service dates with the Contracting Officer’s Representative (COR), including announced reunion and ceremonial events.

1.5.5 Place of Performance: Class of 1961 Reconciliation Plaza, United States Military Academy, West Point, New York 10996.

1.6 Security Requirements:

1.6.1 Access and General Protection: Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements established by the Garrison Commander and administered by the installation Provost Marshal Office, Director of Emergency Services, Security Office, or Directorate of Plans, Training, Mobilization, and Security (DPTMS). Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contract Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

1.6.2 Installation Access: Personnel shall complete installation screening at the Visitor Control Center (VCC) and obtain required passes before entry. Provide required personal information directly through the installation-approved process. No separate recurring personnel or vehicle roster is required by this PWS. Return Government-issued passes or credentials when no longer required. Personnel and vehicles are subject to installation searches and access restrictions.

1.6.3 Parking and Transportation: Use only Government-authorized contractor parking or staging areas. The Contractor shall furnish its own transportation and shall not use West Point shuttle services to transport workers.

1.7 Contractor Identification and Contract Authority: Contractor personnel shall identify their company affiliation when their status is not obvious. The COR may coordinate and inspect work but may not change the contract; only the KO may authorize changes.

1.8 Safety: The Contractor shall comply with applicable Federal, State, local, Army, and installation safety requirements and protect the public and Government property. Before starting work, the Contractor shall provide a contractor-prepared work site accident prevention plan specific to this work and its hazards to the Garrison Safety Office through the COR (A.001). Stop affected work and report incidents as required by paragraph 5.2.4.2.

1.9 Environmental Protection: The Contractor shall prevent chemical runoff, erosion, and damage to vegetation, masonry, drainage features, and adjacent property. The Contractor shall remove contractor-generated waste from the installation for lawful disposal.

1.10 Required Training:

1.10.1 AT Level I Training:

When annotated on the AT/OPSEC cover sheet Contractors are required to complete this training.

(a) Pursuant to Department of Defense Instruction Number 2000.16, “DoD Antiterrorism (AT) Standards,” dated October 2, 2006, each contractor employee requiring access to a Federally-controlled installation, facility and/or Federally-controlled information system(s) shall complete Level I AT Awareness Training on an annual basis and receive a certificate of completion. The training is accessible from any computer and is available at https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf follow the below instructions:

(1) Click – DOD CAC or No DOD CAC

(2) Next click - I am a U.S. mil, government civil servant, or contract employee

(3) Next click - I've been directed to take required training on JKO

(4) Next click - Courses

(5) I do not have a .MIL, .GOV, or .NDU.EDU address or I am a Multi-National Student

(6) Fill out the contact sheet and email to sponsor (COR)

(7) Sponsor (COR) will email to the JKO help desk The COR and contractor are responsible for ensuring that all applicable employees have completed antiterrorism awareness training and shall certify that their workforce has completed the training through the submission of completion certificate(s) to the Contracting Officer and the Contracting Officer’s Representative (if appointed) within five working days after contract award or prior to access to a Federally-controlled installation or information system.

(b) In the event that the automated system is not available (e.g., server problems), Level I AT Awareness Training can be provided by a qualified instructor. However, if the training is not completed online, the Level I AT Awareness Instructor qualification must be coordinated with the USAG Antiterrorism / Force Protection Officer (AT/FP) (or Installation Security equivalent) and the resultant name(s) of approved instructors shall be provided the contracting officer or designee along with all associated cost or schedule impacts to the contract.

(c) Antiterrorism performance (Level I AT Awareness Training attendance and compliance) may be documented as a performance metric under the resultant contract, and be part of past performance information in support of future source selections.

(d) Documentation of this training will be made available to the Installation Antiterrorism Officer upon request.

1.10.2 iWATCH Training:

When annotated on the AT/OPSEC cover sheet Contractors are required to complete this training.

iWATCH Training: The Contractor shall brief all personnel performing work under this contract on the local iWATCH program [training standards provided by the requiring activity Antiterrorism Office (ATO)]. This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award with the results reported to the COR NLT 45 calendar days after contract award. New employees/contractors shall complete the training within 10 calendar days of commencing performance of work under this contract.

PART 2

DEFINITIONS AND ACRONYMS

2.1 Definitions:

Acceptable Quality Level (AQL): The performance threshold used for Government surveillance. It does not relieve the Contractor of any PWS requirement.

Business Day: Monday through Friday, excluding federally recognized holidays and Government-directed closures.

Contracting Officer – means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.

Contracting Officer's Representative (COR) – As defined in DFARS 202.101, means an individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. DoD Instruction (DoDI) 5000.72, Part II Definitions states the following when defining a COR: “Defined in subpart 202.101 of Reference (f). Any individual delegated responsibilities pursuant to subpart 1.602-2 of Reference (e), regardless of local terminology, must be certified in accordance with this instruction. For example, local terminology can be COR, Contracting Officer’s technical representative, technical point of contact, technical representative, alternate COR, administrative COR, assistant COR, line item manager, task order manager, quality assurance personnel, quality assurance evaluator, or COR management.” In addition, Army Regulation 70-13, Chapter 2, paragraph 2-2g, states, in part, the following when providing other surveillance support personnel to assist the COR when needed, “…These other surveillance support personnel may serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR requirements and have been appointed by the Contracting Officer as alternate CORs.”

Contractor – means a supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.

Contractor-acquired Property - means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract and to which the Government has title.

Day: Calendar day unless otherwise stated.

Defective Service – means a service output that does not meet the standard of performance associated with the Performance Work Statement.

Deliverable – means anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

Government-furnished Property – As reflected in FAR 52.245-1, Government-furnished Property “means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract

Government Property - means all property owned or leased by the Government.Government property includes both Government-furnishedand Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.

Property Administrator - means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.

High Level Objective (HLO) – means a key overarching result-based objective for a project necessary to achieve the project’s vision. HLOs are similar to Level 2 in a Work Breakdown Structure. Each HLO may contain several statements to flesh out the areas necessary to meet the objective.

Physical Security – means that part of security concerned with physical measures designed to safeguard personnel; to prevent unauthorized access to equipment, installations, material, and documents; and to safeguard against espionage, sabotage, damage, and theft.

Quality Assurance – (or Government contract quality assurance) means the various functions, including, inspection, performed by the Government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.

Quality Assurance Surveillance Plan (QASP) – means the key Government-developed surveillance process document, and is applied to Performance-Based Service Contracting (PBSC). The QASP is used for managing Contractor performance assessment by ensuring that systematic quality assurance methods validate that Contractor quality control efforts are timely, effective, and are delivering the results specified in the contract or task order. The QASP directly corresponds to the performance objectives and standards (i.e., quality, quantity, timeliness) specified in the Performance Work Statement (PWS). It provides specific details on how the Government will survey, observe, test, sample, evaluate, and document Contractor performance results to determine if the Contractor has met the required standards for each objective in the PWS. The QASP, with very few if any exceptions, is an internal to Government document.

Quality Control – means all necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

Statement – means the specific results-based activities required to satisfy HLOs. A statement contains a result, the context of the statement, and the required action(s). Statements focus on “what” is to be accomplished; however they are not prescriptive in describing “how” the outcome is to be achieved. Each HLO may have several statements to flesh out the areas necessary to meet the objective. Statements are similar to Level 3 in a Work Breakdown Structure.

Subcontractor – means one that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.

Work Day - The number of hours per day the Contractor provides services in accordance with the contract.

Work Week - Monday through Friday, unless otherwise specified.

2.2 Acronyms:

AQL — Acceptable Quality Level AR — Army Regulation AT — Antiterrorism AT/FP — Antiterrorism / Force Protection ATO — Antiterrorism Officer CAC — Common Access Card COR — Contracting Officer’s Representative DFARS — Defense Federal Acquisition Regulation Supplement DoD — Department of Defense DOD — Department of Defense DoDI — Department of Defense Instruction DPTMS — Directorate of Plans, Training, Mobilization, and Security FAR — Federal Acquisition Regulation FPCON — Force Protection Condition FTE — Full Time Employee FY — Fiscal Year HLO — High Level Objective HQDA — Headquarters, Department of the Army IMCOM — Installation Management Command JKO — Joint Knowledge Online KO — Contracting Officer NLT — No Later Than OPSEC — Operations Security PBSC — Performance-Based Service Contracting PRS — Performance Requirements Summary PWS — Performance Work Statement QASP — Quality Assurance Surveillance Plan SAM — System for Award Management SCR — Service Contract Report STD — Standard USAG — United States Army Garrison USG — United States Government USMA — United States Military Academy VCC — Visitor Control Center

PART 3

GOVERNMENT PROPERTY AND SERVICES

3. Government Property and Services: No Government-furnished equipment, materials, storage, or water source is provided. The Government will provide local iWATCH briefing standards through the requiring activity Antiterrorism Officer and coordinate access as necessary.

PART 4

CONTRACTOR FURNISHED PROPERTY AND SERVICES

4.1 General: The Contractor shall furnish all personnel, supervision, equipment, plants, mulch, supplies, tools, vehicles, transportation, and other items required to perform the contract.

4.2 Materials: Furnish healthy, site-appropriate plants and stone-compatible cleaning products. Obtain Government acceptance of proposed planting and cleaning materials as required in Part 5.

4.3 Vehicles and Equipment: Furnish safe, serviceable vehicles and equipment and a self-contained supply of clean potable water for cleaning and watering when needed.

Protect stone and plantings from equipment damage. Pressure washing of monument stone is prohibited.

PART 5

SPECIFIC TASKS

5.1 Basic Services: The Contractor shall provide year-round landscape and monument maintenance within the Government-designated limits of Reconciliation Plaza. Services include initial seasonal opening and planting; monthly growing-season maintenance from April through November; seasonal closeout; monthly winter inspection and cleanup from December through March; cleaning of all sixteen (16) monuments during every scheduled service visit;

plant replacement; mulch and edging maintenance; debris removal; reporting; and protection of Government property. Paved pedestrian areas are excluded from recurring services. All services shall meet the performance standards and acceptable quality levels in Technical Exhibit A.

5.2 Tasks: Tasks consist of the following:

5.2.1 Initial Seasonal Opening

5.2.1.1 Initial Site Inspection and Cleanup: The Contractor shall inspect the Government-designated work limits, document pre-existing damage or deficiencies with dated photographs, and remove litter, leaves, branches, spent vegetation, weeds, loose soil, and other debris from the planting bed, granite edging, monument bases, and other areas within the work limits.

Paved pedestrian areas are excluded.

STD: The initial seasonal opening shall be completed not later than five (5) business days before the first scheduled April reunion or by the date stated by the Government, whichever is earlier. The plaza shall be clean, orderly, and ready for public use upon completion.

AQL: One hundred percent (100%) completion by the required date; zero unreported pre-existing damage or Contractor-caused damage.

Deliverable: A.003 Service Report - within two (2) business days after the visit, including before-and-after photographs.

5.2.1.2 Seasonal Planting and Mulch: The Contractor shall prepare planting beds; install healthy seasonal annuals in Government-approved locations and quantities; and install or replenish mulch. Plants shall be suited to the site exposure and anticipated early-season temperatures and capable of providing an attractive display through the growing season.

STD: Annuals shall be living, present, healthy, and free of significant disease or pest damage at acceptance. Mulch shall be evenly distributed at a settled depth of two (2) to three (3) inches and shall not contact monument stone, granite edging, shrub trunks, plant crowns, paved surfaces, drains, or utility covers.

AQL: At least ninety-five percent (95%) of inspected bed area compliant; one hundred percent (100%) compliance with restrictions against damaging mulch placement.

Deliverable: A.004 Seasonal Planting Submittal - at least fifteen (15) calendar days before planting.

5.2.1.3 Initial Monument Cleaning: The Contractor shall clean all sixteen (16) monument panels and their rough-cut stone bases and immediately associated stone surfaces using the accepted monument-cleaning method in paragraph 5.2.4.1. Paved pedestrian areas are excluded from cleaning.

STD: Monument surfaces shall be free of visible litter, loose soil, bird droppings, gum, stains, organic growth, residue, and other foreign material when viewed under normal daylight from approximately three (3) feet.

AQL: One hundred percent (100%) of the sixteen (16) monuments shall meet the cleanliness standard, with zero cleaning-related damage.

Deliverable: A.003 Service Report - within two (2) business days after the visit.

Deliverable: A.004 Monument Cleaning Plan - at least fifteen (15) calendar days before the initial cleaning.

5.2.2 Growing Season Maintenance April Through November

5.2.2.1 Monthly Service Visits: The Contractor shall perform one complete service visit during each calendar month from April through November, for a minimum of eight (8) visits per contract year. Visits shall be coordinated with the Government and, when practicable, completed before announced reunion or ceremonial events.

STD: Each required calendar month shall include one complete visit covering all growing-season tasks due under paragraphs 5.2.2.2 and 5.2.2.3.

AQL: One hundred percent (100%) of scheduled months serviced.

Deliverable: A.003 Service Report - within two (2) business days after each visit.

5.2.2.2 Planting Bed Plant and Mulch Maintenance: The Contractor shall weed planting beds; maintain neat edges; inspect annuals and established shrubs for health, damage, disease, pests, and water stress; remove spent flowers and dead or broken plant material;

maintain shrubs in their established form; replace dead, missing, severely declined, or damaged annuals; and redistribute or replenish mulch when required.

STD: No weed shall exceed one (1) inch in height or produce seed, and visible weed coverage shall not exceed five percent (5%) of any bed. At least ninety percent (90%) of seasonal annuals shall be living, present, and healthy. Identified annual failures shall be replaced within five (5) business days with plants of comparable type, size, color scheme, and maturity. Mulch shall remain at a settled depth of two (2) to three (3) inches and shall meet the placement restrictions in paragraph 5.2.1.2.

AQL: At least ninety-five percent (95%) of inspected bed area compliant; at least ninety percent (90%) of seasonal annuals healthy; one hundred percent (100%) timely replacement of identified annual failures; zero damaging mulch placement.

5.2.2.3 Monument and Work Area Cleanliness: During every scheduled service visit, the Contractor shall inspect and clean all sixteen (16) monuments to maintain the cleanliness standard using the accepted methods in paragraph 5.2.4.1. The Contractor shall inspect the planting bed, granite edging, monument bases, and adjacent areas within the work limits and report observed damage, settlement, loose stone, open joints, vandalism, or unsafe conditions.

Paved pedestrian areas are excluded from inspection, cleaning, and maintenance.

STD: All sixteen (16) monuments shall meet the three-foot cleanliness standard in paragraph 5.2.1.3 after every scheduled service visit; the work limits shall be free of visible litter, loose soil, plant debris, and work residue upon completion.

AQL: One hundred percent (100%) of the sixteen (16) monuments shall meet the standard after each visit, with zero Contractor-caused damage; one hundred percent (100%) of observed deficiencies shall be reported.

5.2.3 Seasonal Closeout

5.2.3.1 November Closeout: During the November visit, or on a date directed by the Government, the Contractor shall remove dead seasonal annuals after frost or when directed;

remove accumulated leaves and debris; weed the planting bed; redistribute existing mulch and add matching mulch when necessary to restore a settled depth of two (2) to three (3) inches;

clean all sixteen (16) monuments to the required standard; and leave the work area in an orderly winter condition. Living annuals shall not be removed before Government approval when they continue to provide an acceptable display. Paved pedestrian areas are excluded.

STD: All seasonal closeout work shall be completed during the November visit or by the Government-directed date, and the site shall meet all applicable bed, mulch, monument, and plaza cleanliness standards at acceptance.

AQL: One hundred percent (100%) complete and accepted by the required date.

Deliverable: A.003 Annual Closeout Report - within five (5) business days after the November visit.

5.2.4 Monument Cleaning and Property Protection

5.2.4.1 Material Safe Monument Cleaning: The Contractor shall clean polished, inscribed monument panels and rough-cut stone bases using the least aggressive effective method.

Cleaning shall preserve the polished finish, inscriptions, emblems, stone edges, joints, sealant, and surrounding masonry and shall not alter the appearance or surface texture.

STD: Before the first cleaning, the Contractor shall submit product data, equipment, dilution ratios, runoff controls, and a step-by-step method; perform a discreet test area;

and obtain Government acceptance. Cleaning shall use clean potable water, nonmetallic soft-bristle brushes or pads, and, when needed, a pH-neutral, stone-compatible cleaner. Acids, bleach, salts, abrasive powders, wire brushes, rotary abrasive tools, sandblasting, graffiti removers, sealers, coatings, unapproved chemicals, and pressure washing of monument stone are prohibited. The Contractor shall protect adjacent plantings, edging, and property from runoff or damage.

AQL: One hundred percent (100%) of the sixteen (16) monuments shall meet the required standard; zero cleaning-related damage, residue, streaking, alteration, or runoff impact.

Deliverable: A.004 Monument Cleaning Plan - at least fifteen (15) calendar days before initial cleaning.

5.2.4.2 Protection of Property and Incident Reporting: The Contractor shall protect monument faces and lettering, rough-cut bases, mortar joints, granite edging, parapet masonry, pavers, drains, utilities, lamps, shrubs, trees, turf, vehicles, buildings, and the public.

The Contractor shall immediately stop affected work and notify the Government upon discovering cracking, loose stone, open joints, failing sealant, unstable edging, blocked drainage, or any condition that cleaning or maintenance could worsen.

STD: The Contractor shall provide immediate verbal notice of damage, injury, spill, security concern, unsafe condition, or potential property damage and shall submit a written incident report with photographs and immediate controls within one (1) business day.

AQL: One hundred percent (100%) timely incident reporting; zero unreported Contractor-caused damage.

Deliverable: A.005 Incident Report - immediate verbal notice and written report within one (1) business day.

5.2.5 Winter Maintenance December Through March

5.2.5.1 Monthly Winter Inspection and Cleanup: The Contractor shall perform one scheduled inspection and cleanup visit during each calendar month from December through March, for a minimum of four (4) visits per contract year. Each visit shall include cleaning all sixteen (16) monuments to the required standard; removal of windblown litter and accessible plant debris from the work limits; inspection of monuments, bases, granite edging, planting bed, shrubs, and accessible drainage features; removal of broken plant material that presents a hazard; and reporting with photographs. Paved pedestrian areas are excluded from inspection, cleaning, and maintenance.

STD: One complete winter inspection and cleanup shall occur in each required calendar month, and the plaza shall be free of accessible windblown litter and plant debris upon completion.

AQL: One hundred percent (100%) of scheduled months serviced and reports submitted on time.

Deliverable: A.003 Service Report - within two (2) business days after each visit.

5.2.5.2 Excluded Winter Work and Deicing Protection: Snow and ice removal, deicing, major pruning, masonry repair, resetting of pavers or edging, graffiti removal, and storm response are outside recurring maintenance unless separately included in the contract or authorized by the Contracting Officer. The Contractor shall not apply deicing chemicals to monument stone, bases, edging, or planting beds.

STD: The Contractor shall perform no excluded work without contractual authorization and shall apply no deicing chemical to a prohibited surface or area.

AQL: Zero unauthorized work and zero application of deicing chemicals to prohibited surfaces or areas.

5.2.6 Watering and Irrigation

5.2.6.1 Watering Services: Water the newly installed and established annuals when needed to maintain plant health. The Contractor shall provide the labor, equipment, and self-contained water source and shall avoid damage to monument surfaces, edging, beds, and adjacent property.

STD: Watering frequency shall be sufficient to maintain at least ninety percent (90%) of annuals in healthy condition during hot or dry weather. Water shall be applied without uncontrolled runoff, erosion, ponding, or overspray onto monument panels.

AQL: At least ninety percent (90%) of annuals healthy; zero watering-related damage, erosion, uncontrolled runoff, or monument overspray.

5.2.7 Documentation and Reporting

5.2.7.1 Service Reports: The Contractor shall document each service visit, including the date; arrival and departure times; personnel; tasks completed; quantities installed or replaced;

deficiencies observed; corrective actions; and dated photographs.

STD: The complete and accurate report shall be submitted electronically to the Contracting Officer through the COR within two (2) business days after each service visit.

AQL: One hundred percent (100%) of required reports complete, accurate, and submitted by the due date.

Deliverable: A.003 Service Report - within two (2) business days after each service visit.

5.2.7.2 Annual Closeout Report: The Contractor shall provide an annual summary of service visits, plant replacements, recurring conditions, unresolved deficiencies, and recommended actions for the next season.

STD: The report shall be complete, accurate, supported by available service records and photographs, and submitted within five (5) business days after the November visit.

AQL: One hundred percent (100%) complete and timely.

Deliverable: A.003 Annual Closeout Report - within five (5) business days after the November visit.

5.3 Service Contract Reporting

5.3.1 System for Award Management (SAM) Service Contract Report (SCR): The Contractor shall report all Contractor labor hours, including subcontractor labor hours, required for performance of services provided under this contract for the Department of the Army through the secure data collection site at www.sam.gov. The Contractor shall complete all required data fields. Report labor performed during each Government fiscal year, October 1 through September 30, no later than October 31 of each calendar year. Reports may be submitted earlier. For assistance, use “View Assistance for SAM.gov” and “Contact Our Service Desk” on the SAM.gov website. If the contract period of performance ends before September 30, the Contractor shall complete the SCR within 30 calendar days after the contract end date.

Steps for Submitting a Service Contract Report (SCR)

1. Go to www.sam.gov and log in.

2. Select Entity Registrations, then Service Contract Reporting.

3. Select View by entity to see the service contracts for each entity. Select Add for the contract report.

4. On the Complete Service Contract Report page, enter the total amount invoiced for services performed during the previous Government fiscal year, including prime and subcontract amounts, and the prime contractor direct labor hours expended during that fiscal year.

SAM.gov calculates the prime contractor FTE equivalent using 2,080 hours.

5. Add required Tier 1 subcontractor information, then select Submit.

To edit a submitted report, return to the service contract reporting page, select View/Edit for the report, edit the available fields, and resubmit.

STD: Submit all Contractor and subcontractor labor hours required by paragraph 5.3.1 completely and by the stated suspense dates.

AQL: One hundred percent (100%) of required SAM service-contract reports shall be complete and timely.

Deliverable: A.006 SAM Service Contract Report, submitted through SAM.gov by the suspense dates in paragraph 5.3.1.

PART 6

APPLICABLE PUBLICATIONS

6. Applicable Publications: Apply the following documents to the work and requirements expressly identified in this PWS. Contract clauses are provided separately by the KO.

6.1 IMCOM Regulation 385-10, Safety Program, Chapter 4, including paragraph 4-1c, as provided with the requirements package.

6.2 Reconciliation Plaza AT/OPSEC Security Review Cover Sheet: Project-specific signed cover sheet identifying applicable AT Level I, access and general protection, and local iWATCH provisions.

6.3 Installation access, parking, safety, and environmental procedures furnished by the Government for contract performance.

PART 7

ATTACHMENT AND TECHNICAL EXHIBIT LISTING

7.1 Technical Exhibit A — Performance Requirements Summary

7.2 Technical Exhibit B — Deliverables Schedule

TECHNICAL EXHIBIT A

PERFORMANCE REQUIREMENTS SUMMARY

The five requirements below summarize the principal performance outcomes. All other PWS requirements remain enforceable. Surveillance methods describe Government evaluation and do not create additional Contractor reports.

PERFORMANCE

OBJECTIVE STANDARD PERFORMANCE

THRESHOLD / AQL

METHOD OF

SURVEILLANCE

PRS 1

Service cycle and seasonal readiness 5.2.1.1, 5.2.2.1, 5.2.3.1, 5.2.5.1

Open by five business days before the first April reunion or the Government-directed date, whichever is earlier; eight April– November visits; four December– March visits; clean all sixteen monuments every visit; complete November closeout.

100% of required visits and seasonal milestones completed on time.

Schedule and service-report review; opening and closeout inspection.

PRS 2

Plantings beds mulch and edging 5.2.1.2, 5.2.2.2, 5.2.6.1

Healthy annuals at acceptance;

weed, mulch, edging, and replacement standards in 5.2.1.2 and 5.2.2.2; water when needed under 5.2.6.1.

At least 95% of bed area compliant; at least 90% of annuals healthy; all identified failures replaced on time; zero damaging mulch placement, watering damage, uncontrolled runoff, or monument overspray.

Opening inspection and periodic sampling.

PRS 3

Monument cleanliness and safe methods 5.2.1.3, 5.2.2.3, 5.2.4.1

Clean all sixteen monuments every visit to the three-foot standard. Use the accepted method and test area; protect inscriptions, finish, bases, and adjacent property.

All sixteen compliant after every visit; zero cleaning damage, prohibited methods, residue, alteration, or runoff impact.

Verify method and test area before first use; inspect all sixteen monuments during each visit.

PRS 4

Protection of property and incident reporting 5.2.4.2, 5.2.5.2

Protect persons and property; stop affected work for unsafe or damaging conditions; give immediate verbal notice and a written incident report within one business day. No unauthorized excluded work or prohibited deicing.

100% timely incident reporting; zero unreported Contractor-caused damage, unauthorized excluded work, or prohibited deicing.

Site observation and incident-driven review.

PRS 5

Service documentation 5.2.7.1–5.2.7.2

Provide a complete, accurate service report and dated photographs after each visit within two business days. Provide the annual summary within five business days after the November visit.

100% complete, accurate, and timely required reports and photographs.

100% report review.

TECHNICAL EXHIBIT B

DELIVERABLES SCHEDULE

Submit one electronic copy to the KO through the COR unless otherwise stated. Related submissions may be combined if all content, deadlines, and required recipients are satisfied.

DELIVERABLE DUE DATE MINIMUM CONTENT AND ROUTING

A.001 Work site accident prevention plan Before work starts.

Contractor-specific work, hazards, and controls; provide to Garrison Safety Office through COR.

A.002 AT Level I and iWATCH evidence

AT: annually; certificates within five working days after award or prior to installation or information-system access, as stated in

1.10.1. iWATCH: within 30 calendar days after award; results NLT 45 calendar days after award;

new personnel within 10 calendar days of commencing performance.

AT completion certificates to KO and COR;

iWATCH results to COR. Training documentation available to the Installation Antiterrorism Officer upon request. No separate OPSEC or cyber training submission.

A.003 Service report and annual summary

Service report: within two business days after each visit. Annual summary: within five business days after November visit.

Date, arrival/departure, personnel, work, quantities, deficiencies, corrective actions, and dated photographs. November summary may be included in that visit report or provided as an addendum.

A.004 Planting and cleaning submittal

At least 15 calendar days before planting or initial cleaning, respectively.

One combined submission permitted. Plant types, quantities, and locations; cleaning products, equipment, dilutions, runoff controls, method, and test area. Obtain acceptance before planting or cleaning.

A.005 Incident report Immediate verbal notice; written report within one business day.

Event or condition, photographs, and immediate controls.

A.006 SAM Service Contract Report under 5.3.1

By October 31 each calendar year; if the contract ends before September 30, within 30 calendar days after contract end.

Report all Contractor and subcontractor labor hours through SAM.gov as specified in paragraph 5.3.1.