This is a Performance Work Statement (PWS) for security gate maintenance, inspection, repair, and replacement services at Aberdeen Test Center (ATC), Aberdeen Proving Ground, Maryland. The contract is non-personal services and requires the contractor to maintain all gates and associated components in continuous working and serviceable condition in accordance with commercial industry standards. The scope covers four main Restricted Area entrance/exit gates (Gate 13, Gate 24, Gate 25, and Post 10) plus ten sensitive range area gates, with contractor responsibility extending to gate operators, hardware, and components up to the point where the AMAG Symmetry access control system sends valid open/close commands. The contractor must furnish all labor, materials, tools, and equipment, including a man-lift for inspecting the Gate 13 outbound gate, and obtain all necessary technical information independently as no Government Furnished Information will be provided.

The contract includes a 12-month base period plus four one-year option periods, with services performed at APG North and South locations plus Churchville Test Area. Contractor personnel must be available Monday through Friday, 8:00 a.m. to 4:30 p.m., excluding weekends and Federal holidays. Preventive maintenance on main gates occurs semi-annually (April and October, by the 15th of each month), while range/test area gates receive annual PM (October, by the 15th). Emergency response timelines require on-site response to main gates within the next business day and range gates within the second business day, with written cost estimates provided within one business day and repairs completed within 14 days of approval. Non-emergency repairs are scheduled mutually between contractor and the Contracting Officer's Representative (COR). Documentation requirements include written reports within five business days of each service visit detailing gate conditions, services performed, deficiencies, and repair recommendations with cost estimates. The PWS also includes optional requirements for ATEC HQ Drop Gates (Building 2202) covering quarterly and semi-annual preventive maintenance with operational testing, debris/drainage maintenance, hydraulic/power unit verification, structural/hardware inspection, and electrical/controls maintenance. Performance standards require 100% PM completion per schedule, 95% emergency response compliance, 98% gate operability after service, and 95% documentation quality and timeliness.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

ATC SECURITY GATE AND GATE OPERATOR

INSPECTION, MAINTENANCE, REPAIR AND REPLACEMENT

Aberdeen Test Center (ATC), Aberdeen Proving Ground, MD

1.0 SCOPE OF WORK

This is a non-personal services contract to perform inspection, preventive maintenance, and repair services on security gates and associated components at the U.S. Army Aberdeen Test Center (ATC), Aberdeen Proving Ground (APG), Maryland. The Contractor shall maintain all gates and components in continuous working and serviceable condition. This is a commercial services requirement. The Contractor shall perform all work in accordance with commercial industry standards for automated security gate inspection, maintenance, and repair.

1.1 General

ATC is a multi-purpose test center with diverse test capabilities and facilities located in the Restricted Area of Aberdeen Proving Ground. ATC has full responsibility for supporting and controlling access to Restricted Areas located at both APG North and South. Restricting access to these areas is a mission essential requirement for safety, test integrity and security. All Restricted Area gates are automated using the AMAG Symmetry access control system supported by ATC and Army Research Laboratory (ARL) issued Restricted Area photo access credentials.

In addition to the four (4) Restricted Area entrance and exit points, ATC uses automated gates to control access to ten (10) sensitive range areas inside the Restricted Area. Full-time access to the Restricted Area and ranges is required to support full test mission execution.

1.2 Period and Place of Performance

The period of performance includes one year (12-month) base period and four (4) one-year option periods. Services shall be performed at Aberdeen Proving Ground (APG North and South) and the Churchville Test Area.

2.0 Scheduling

Contractor personnel shall be available Monday through Friday between 8:00 a.m. and 4:30 p.m., excluding weekends and Federal holidays. The Contractor shall notify the Contracting Officer’s Representative (COR) at least a week prior to performing scheduled preventive maintenance so arrangements can be made for escorts.

3.0 Technical Requirements

The Contractor shall furnish all labor, materials, tools, equipment, and resources necessary to inspect, maintain, and repair the gates and associated components identified in this PWS. Priority of effort shall be given to the main Restricted Area access gates (Gate 13, Gate 24, Gate 25, and Post 10).

The Contractor is responsible for the gate operators, gate hardware, and associated components up to the point where the AMAG Symmetry access control system sends a valid open/close command. The Contractor is not responsible for maintenance, repair, programming, or software support of the AMAG Symmetry system or the HID MultiCLASS card readers. Those systems are maintained by others.

If the AMAG system and card reader are functioning and sending a valid open/close signal, the Contractor shall diagnose and repair the gate operator and physical gate hardware. Linear and LiftMaster numeric keypads and pedestrian turnstiles listed in the equipment inventory are included in the scope of this contract.

No Government Furnished Information (GFI), manuals, drawings, or other technical data will be provided. The Contractor is responsible for obtaining all necessary technical information required to perform the work.

3.1 Preventive Maintenance (PM)

The Contractor shall perform preventive maintenance in accordance with manufacturer recommendations. PM tasks include inspection of operators, control units, physical gate components, loop inductance testing, lubrication, battery testing and replacement (where applicable), and firmware updates. The Contractor shall be prepared to replace common wear parts (e.g., guide roller assemblies, guide chain guards, ice/debris scrapers and brushes, photo eye reflectors, drive wheels, etc.) during preventive maintenance or emergency repairs. The Contractor shall maintain ready access to these parts so that replacement can normally be accomplished on the same visit or within the response times required by this PWS. Pre-stocking of parts at the Contractor’s facility is not required, provided the Contractor can meet the repair timelines.

The Contractor shall furnish all equipment required to perform the work, including a man-lift or equivalent to properly inspect the Gate 13 outbound gate. No lift will be provided by the Government.

Table 3.1 – Preventive Maintenance Schedule

Gate Group
Frequency
Months
Initiation Deadline
Main Restricted Area Gates (Gate 13, Gate 24, Gate 25, Post 10)
Semi-Annual
April & October
No later than the 15th of the month
Range / Test Area Gates (10 locations)
Annual
October
No later than the 15th of the month

3.2 Equipment Summary

Table 3.2a – Main Restricted Area Gates (Semi-Annual PM)

Location / Gate
Gate Operator
Barrier Arm
Control / Keypad / Other
Notes
Gate 13, Colleran Road
HySecurity SlideDriver II 40 (2)
LiftMaster MAT-DC-BB3 (2)
AMAG + HID Readers + Turnstile
Primary Restricted Area Gate (North) + pedestrian turnstile
Gate 24, Combat Drive
HySecurity SlideDriver II 40 (2)
FAAC Model 640 (2)
AMAG + HID Readers
Secondary Restricted Area Gate
Gate 25, Bush River Road
HySecurity SlideDriver II 40 (1)
LiftMaster MAT-DC-BB3 (2)
AMAG + HID Readers
Access to Phillips Army Airfield
Post 10, Ricketts Point Road
HySecurity SlideDriver II 40 (1)
None
AMAG + HID Readers
Main Restricted Area Gate (South)

Table 3.2b – Range / Test Area Gates (Annual PM)

Location / Gate
Gate Operator
Barrier Arm
Control / Keypad / Other
Notes
Bldg. 338
LiftMaster SL585 (2)
—
Linear Numeric Keypad (3)
Automotive maintenance area
UTF/LWE, Old Baltimore Road
LiftMaster SL585 (1)
—
Linear Numeric Keypad (1)
Sensitive test range
Poverty Island C Tower
LiftMaster SL585 (1)
—
Linear Numeric Keypad (1)
Sensitive test range
BTD Range Gate, Radar Road
LiftMaster SL585 (1)
—
Linear Numeric Keypad (2)
Sensitive test range
Bldg. 714F, Michaelsville Road
LiftMaster SL585 (1)
—
Linear Numeric Keypad (1)
Sensitive test area
Phillips Army Airfield
LiftMaster SL585 (2)
—
Linear Numeric Keypad (2)
Airfield entrance
Bldg. 5014, Boothby Hill Rd
LiftMaster SL585 (1)
—
Linear Numeric Keypad (1)
Rear apron & test bays
Gate 18, Colleran Road
LiftMaster HDSL24UL (1)
—
AMAG + HID + Turnstile
Outbound + pedestrian turnstile
Churchville Test Area, State Hwy 136
LiftMaster SL585 (1) + HDSL24UL (1)
—
Linear Numeric Keypad (2)
Churchville test range
Ford’s Farm Gate
HySecurity SlideDriver II 40 (1)
—
SCH-MTK15 Card Reader
Sensitive test range

* Note on Barrier Arms: Barrier arms at Gates 13, 24, and 25 are non-functional and have not been in use for multiple years. These barrier arms shall be maintained in “as-is” condition only. The Contractor is not required to restore them to operational status under this contract. Should the Government later decide to reinstate any barrier arms, such work will be handled as additional work via contract modification.

3.3 Emergency and Remedial Repairs

· Definition of Emergency: An emergency is a gate or component failure that the COR (or designated Government representative) determines requires priority response because it creates a safety hazard, significantly impacts mission operations, or prevents necessary access/egress. The COR will identify a request as an “Emergency” at the time of notification. Routine or non-urgent repairs will be handled as remedial work under the normal scheduling process and are not subject to the emergency response times below.

· When the COR notifies the Contractor of an Emergency: Main Gates (13, 24, 25, Post 10) – respond on-site no later than the next business day following notification; Range Gates – respond on-site no later than the second business day following notification. Emergency response is required only during normal business hours (Monday through Friday). Notifications received after normal business hours, on weekends, or on Federal holidays will be treated as received at the start of the next business day.

When possible, the Contractor shall repair the gate immediately. When parts are required, the Contractor shall provide the COR with a written cost estimate (price and availability) within one (1) business day of the on-site response. Upon COR approval, the Contractor shall complete the repair within fourteen (14) days of approval. If the repair cannot be completed within fourteen (14) days, the Contractor shall notify the COR of the reason and provide a revised completion date. Non-emergency (remedial) repairs will be scheduled mutually between the Contractor and the COR and are not subject to the emergency response timelines. Comment by Langrehr, Jennifer B CIV USARMY ACC (USA): Note for KO: Should this read KO/COR approval?

3.4 Optional Requirements

3.4.1 Optional Requirements (ATEC Drop Gates – Bldg. 2202)

The equipment and associated maintenance tasks listed in Tables 3.4a and 3.4b represent optional requirements for the Army Test and Evaluation Command (ATEC) HQ Drop Gates. The Government reserves the right to exercise these optional services at any time during the contract period of performance via a formal contract modification. The Contractor is not authorized to perform work on, or bill for, these optional items unless specifically directed to do so by the Contracting Officer (KO) through the activation of the corresponding Optional Contract Line Item Numbers (CLINs)."

3.4a Optional ATEC Drop Gate Equipment Summary

Location / Gate
Gate Operator
Frequency
Control / Keypad / Other
Notes
Bldg. 2202 (West Side)
Nasatka Security, Model XXI-14L-M

Date February 2014

Quarterly and Semi-Annual PM
Active Loops, Safety Controls & HPU
Army Test and Evaluation Command (ATEC) HQ
Bldg. 2202 (East Side)
Nasatka Security, Model XXI-14L-M

Date February 2014 (or similar)

Semi-Annual Preventive Maintenance
Active Loops, Safety Controls & HPU
Army Test and Evaluation Command (ATEC) HQ

Table 3.4b – Optional PM Requirements and Standards

Component Group
Standard Commercial Performance Task Description
Frequency
Location
Operational & Safety Testing
Perform full cycle tests, check synchronization with traffic signals/arms, and verify vehicle detection loop responsiveness and emergency/EFO functions.
Quarterly / Semi-Annually
Bldg. 2202 (West & East)
Debris & Drainage Maintenance
Clear and inspect the barrier pit, top plate hinge lines, and receiver sockets of dirt, debris, standing water, or ice. Verify pump and drainage systems.
Quarterly / Semi-Annually
Bldg. 2202 (West & East)
Hydraulic & Power Units
Verify HPU fluid levels, check for leaks, test operational pressures against OEM specifications, and replace hydraulic fluid/filters (annually).
Quarterly / Semi-Annually
Bldg. 2202 (West & East)
Structural & Hardware Integrity
Lubricate pivot joints/hinge pins. Inspect high-stress fasteners, mounting bolts, concrete anchors, and structural welds for signs of stress, fatigue, or wear.
Quarterly / Semi-Annually
Bldg. 2202 (West & East)
Electrical & Controls
Inspect electrical enclosures, clean dust/debris, tighten screw terminals, check wiring, and test standby UPS battery backup capacities.
Quarterly / Semi-Annually
Bldg. 2202 (West & East)

3.5 Documentation

Within five (5) business days of each inspection or service visit, the Contractor shall provide a written report to the COR. The report shall detail the operating condition of each gate, services performed, deficiencies identified, and recommendations for repairs or parts replacement. When repairs are recommended, the report shall include a cost estimate with parts pricing, availability, and proposed timeline. The COR will review and approve or disapprove the estimate and establish a completion timeline.

4.0 PERFORMANCE REQUIREMENTS SUMMARY (PRS)

Performance Objective
Performance Standard
AQL
Method of Surveillance
Frequency
Preventive Maintenance Completion
All PM completed per schedule
100%
PM reports & Government verification
Per PM event
Emergency Response (Main Gates)
On-site response within next business day
95%
Government log / Contractor report
As occurring
Emergency Response (Range Gates)
On-site response within second business day
95%
Government log / Contractor report
As occurring
Gate Operability
Gates returned to full automated operation
98%
Government observation
After each service
Documentation Quality & Timeliness
Reports submitted complete and on time
95%
Government review
Per deliverable
Safety & Coordination
Full compliance with safety and coordination requirements
100%
Government observation
Continuous

File details come from the government source that posted it. Updated .