W91CRB-17-Q-5003 updated Q&A
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ
W91CRB-17-Q-5003
QUESTION NO. 1: What is the operating voltage?
ANSWER: 220V/50Hz Type C and E socket
QUESTION NO. 2: Can you please advise the shipping address for generator requested under solicitation W91CRB-17-Q-5003?
ANSWER: Reference solicitation page 2, Narrative A0001, instruction 4 as well as page 12, Narrative F0001 entitled “Shipping Instructions – Country of Mongolia.”
QUESTION NO. 3: On your request for a Kohler or equivalent 500kW mobile generator you have 50Hz listed in the specification for the frequency. US models will have 60Hz. Can you clarify the frequency that is needed for this solicitation?
ANSWER: This is a generator to be used in the country of Mongolia through Foreign Military Sales. 50Hz is what is needed, if you choose to offer 50Hz/60Hz selectable, it would be acceptable, but must be included in the price and not separately priced.
QUESTION NO. 4: I am looking over the Solicitation W91CRB-17-Q-5003, SOW (page 4) 3.2.1.1 -- MIL- STD-130N I have read this standard & not sure what labels are required. Can you help lead me to what is needed?
ANSWER: Only UID labels are required.
QUESTION NO. 5: We see where it states that the machine is shipping to the Republic of Mongolia.
However it also states in Shipping Instructions that DCMA will pick up. Does that mean that DCMA will be responsible for shipping to Mongolia and the vendor only need to ship to the US port designated by
DCMA?
ANSWER: All shipping is to be coordinated through the contractor’s specific DCMA office, transportation department.
QUESTION NO. 6: Is it required in the bid that the machine have both RFID tags and UID markings?
ANSWER: UID only.
QUESTION NO. 7: For the most part this type of unit will be made outside of the USA, because of the 50 Hz issue, can the inspection be carried out at the supplier facility? You would save money that way, these units do not have to comply with EPA tier system because they are going overseas.
ANSWER: All inspections are coordinated through DCMA for US owned companies only.