PWS_Command_Center_Maintenance.docx

DOCX document 52 KB Posted

Attached to
Command Center Maintenance
Solicitation number
W9133L-16-R-0029
Issued by

About this file

Draft PWS

View the file

Other files

File Type Posted
Sources_Sought_FBO_Command_Center_Maintenance.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FOR

ANG Command Center/CAT, Audio/Visual Maintenance Service Agreement

1.0 General:

1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform Audio/Visual Equipment diagnostic and maintenance services, as defined in this PWS

1.2 Background: The ANG Command Center has multiple audio visual system components by various manufacturers (Crestron, Avocent, Extron), that have been integrated within the ANG Command Center and the ANG CAT to provide an enhanced common operational picture during routine and emergency operations.

1.3 Period of Performance (PoP): The Period of Performance shall be one Base Year of 12 months and three (3) 12-month option years.

1.4 General Information:

1.4.1 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary.

1.4.2 Quality Assurance (QA): The Government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) (defect rate(s)).

1.4.3 Recognized Holidays: In the event of a system failure rendering the on duty controller without the ability to perform the mission, the contractor shall perform services on these holidays. The following are recognized US holidays. The contractor shall perform services on these days:

1.4.3.1 New Year’s Day: January 1st

1.4.3.2 Martin Luther King, Jr.’s Birthday

1.4.3.3 President’s Day

1.4.3.4 Memorial Day

1.4.3.5 Independence Day: July 4th

1.4.3.6 Labor Day

1.4.3.7 Columbus Day

1.4.3.8 Veteran’s Day: November 11th

1.4.3.9 Thanksgiving Day

1.4.3.10 Christmas Day

1.4.4 Place and Performance of Services: The contractor will not be required to remain onsite. The contractor shall only perform on site when a service request call has been placed with the contractor’s onsite support center. The contractor shall provide non-emergency services between the hours of 0730-1630, Monday through Friday or emergency service for critical failure, 24 hours per day, seven (7) days a week as determined by on duty controller, except when the Government facility/installation is closed due to local or national emergencies, or similar Government-directed facility/installation closings. Onsite performance shall be at the ANG Command Center, Building 3500, room 1500, Fetchet Ave, Joint Base Andrews, MD 20760. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. The contractor shall keep in mind that the stability and continuity of the work force is mission essential to the Government.

1.4.4.1 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.4.2 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times. The contractor shall ensure compliance with all regulations and orders of the installation which may affect performance.

1.4.5 Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1.4.5.1 COMSEC/IT Security. All communications with DOD organizations are subject to communications security (COMSEC) review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, the contractor is advised that any time contractor place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DOD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.

1.4.5.2 Use of Government Information Systems (IS) and access to Government networks is a revocable privilege, not a right. Users are the foundation of the DoD strategy and their actions affect the most vulnerable portion of the AEI. Contractor employees shall have a favorable background investigation or hold a security clearance and access approvals commensurate with the level of information processed or available on the system. Contractor employees shall:

a. Comply with the command's Acceptable Use Policy (AUP) for Government owned IS and sign an AUP prior to or upon account activation.

b. Complete initial and/or annual Information Assurance (IA) training as defined in the IA Best Business Practices (BBP) training (https://informationassurance.us.army.mil).

c. Mark and safeguard files, output products, and storage media per classification level and disseminate them only to individuals authorized to receive them with a valid need to know.

d. Protect IS and IS peripherals located in their respective areas in accordance with physical security and data protection requirements.

e. Practice safe network and Internet operating principles and take no actions that threaten the integrity of the system or network.

1.4.5.3 Protection of Personally Identifiable Information (PII). The contractor shall protect all Personally Identifiable Information (PII) encountered in the performance of services in accordance with DFARS 224.103 and DoDD 5400.11, Department of Defense Privacy Program, and DoD 5400.11-R. If a PII breach results from the contractor’s violation of the aforementioned policies, the contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals who’s PII has been compromised.

1.4.5.4. CAC Requirements: N/A

1.4.5.4.i. HSPD-12 Background Investigation Requirements: N/A

1.4.5.4.ii. Trusted Associate Sponsorship System (TASS): N/A

1.4.5.5 AT Level 1 Awareness Training (AT): N/A

1.4.5.6 Information Assurance (IA)/Information Technology (IT) Training: N/A

1.4.5.7 Information Awareness: N/A

1.4.5.8 WATCH Training. N/A

1.4.5.9 OPSEC Training. N/A

1.4.5.10 OPSEC SOP/Plan. N/A

1.4.5.11 Classified Information. N/A

1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.4.6.1 Key Control. N/A

1.4.6.2 Lock Combinations: N/A

1.4.7 Special Qualifications: N/A

1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with Federal Acquisition Regulations Subpart 42.5. The KO, Contracting Officer’s Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor’s performance. At these meetings, the Contracting Officer will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, (or the KO if a COR is not assigned), to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.10 Identification of Contractor Employees: All contractor personnel will be required to obtain and wear badges which will be issued upon arrival to the work area. For Authentication purposes, the company will provide a list of personnel who are qualified and authorized to troubleshoot and repair the audio visual system within the ANG Command Center and CAT. This list will include an employee’s full name and social security number to validate clearance levels. All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities/ Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed.

1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The Contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.

1.4.12 Contractor Travel N/A

1.4.13 Data Rights The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.15 Phase In / Phase Out Periods N/A

1.4.16 Telework: N/A

2.0 Definitions and Acronyms:

2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government designated by the KO to monitor contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5 DELIVERABLE. Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.8 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.

2.2 ACRONYMS:

AEI

AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation AT/OPSEC Antiterrorism/Operational Security CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DOD Department of Defense FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services IA Information Assurance IS Information System(s) KO Contracting Officer OCI Organizational Conflict of Interest ODC Other Direct Costs PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TE Technical Exhibit

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government will not provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:

3.1 Property: The Government will furnish the necessary workspace and telephones required for the contractor to perform the services outlined in this PWS.

3.2 Materials: N/A

3.3 Equipment: N/A

3.4 Services: The contractor shall be escorted by Government personnel into controlled/restricted areas for the duration of the work day as required and as operations allow.

3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):

4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish all materials required to perform these services as indicated in Section 5 of this document.

5.0 Requirements: The contractor shall provide a service plan that will protect and ensure continuing productivity, including adjustment of equipment to manufacturer’s specifications. The contractor will provide up to four (4) reprograming and/or re-routing of, and/or re-naming of source targets within the Crestron and Avocent system as required due to technology changes. The contractor shall provide maintenance and upgrade services necessary to ensure the Command Center Systems are functioning as if manufacturer coverage was being provided by the Manufacturers’ warranty. The contractor shall respond to service requests placed via contractor on call center within the timeframe specified in section 5.1.1 of this document.

5.1 On call Onsite Support Services

5.1.1 The contractor shall provide on call 24/7 customer support services in order to maintain equipment continuity at the same standards as the manufacturer. Response time shall be provided within four (4) hours or less regardless of urgency.

5.2 Equipment Maintenance and Repairs and Equipment System Upgrades per manufacturer standards.

5.2.1 The contractor shall reinstall and align repaired faulty equipment to an operating status as it was prior to the equipment malfunctioning.

5.2.1.1 At the contractor’s expense, the contractor shall provide overnight shipping for all parts and equipment under repair to ensure equipment downtime remains at a minimum.

5.2.2 The contractor shall provide up to four (4) preventive maintenance visits per year per manufacturer recommendations for all equipment.

5.3 The contractor shall provide for expedited repairs at no additional cost to the government if faulty equipment cannot be repaired by the onsite technician. This coverage shall extend to all parts and labor needed for equipment breakdown (excludes lamps, filters and image retained optical surfaces and assemblies).

5.4 The contractor shall provide two (2) equipment system programming changes/upgrades per the manufacturer standards. Programming upgrades shall be required due to technology changes. The request shall be made by the COR or designated representative.

5.5 Contractor Manpower Reporting Application (CMRA):

5.5.1 The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Air National Guard Command Center/CAT via a secure data collection site.

5.5.2 The contractor shall completely fill in all required data fields using the following web address: http://www.ecmra.mil/. Reporting inputs shall be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk at http://www.ecmra.mil.

6.0 Applicable Publications: Publications applicable to this PWS are listed below: None

TECHNICAL EXHIBIT 1

Performance Requirements Summary

This Performance Requirements Summary includes performance standards. The Government will use these standards to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).

PWS Paragraph
Task
Performance Standard
Acceptable Quality Levels (AQL)
Surveillance Method / By Whom
5.0
The Contractor shall Enhance manufacturers’ warranties through prompt on-site service, unlimited 24/7 technical phone support and training.
The Contractor shall provide prompt on-site service, unlimited 24/7 phone support and training as required within established timeframes at the request of the on-duty controller.
20 minute maximum technical phone support to restore audio/visual system serviceability.
Periodic Inspection - COR will review monthly work order and logs.
5.1.1
The Contractor shall provide 24/7 hour response, seven days a week as required.
The Contractor shall provide prompt unlimited 24/7 on-site service within established timeframes at the request of the on-duty controller.
95% success rate for prompt unlimited 24/7 on-site service within established timeframes at the request of the on-duty controller
Periodic Inspection - COR will review monthly work order logs.

5.2.1.

The Contractor shall provide reinstallation and alignment of repaired equipment.
The Contractor shall provide at no cost, reinstallation and alignment of repaired equipment.
95% success rate for contractor to at no cost, reinstall and align repaired equipment to restore audio/visual system serviceability.
Periodic Inspection - COR will review monthly work order logs.
5.2.1.1
The Contractor will provide overnight shipment for all parts and equipment under repair.

The Contractor will provide at no cost, overnight shipment for all parts and equipment under repair as required

95% success rate the Contractor will provide at no cost, overnight shipment for all parts and equipment under repair as required

Periodic Inspection - COR will review monthly work order logs.

5.2.2

The Contractor will provide four (4) preventative maintenance visits per year
The Contractor shall provide at no cost, four preventative maintenance visits per year as required to maintain system functionality
95% success rate for on-site response within pre-coordinated timeframe for preventative maintenance.
Periodic Inspection - COR will review monthly work order logs.

5.3

The contractor shall provide for expedited repairs at no additional cost to the government if faulty equipment cannot be repaired by the onsite technician. This coverage shall extend to all parts and labor needed for equipment breakdown (excludes lamps, filters and image retained optical surfaces and assemblies).I

The Contractor will provide paid expedited repairs where available.

95% success rate the Contractor will provide paid expedited repairs where available.

Periodic Inspection - COR will review monthly work order logs.

5.4

The Contractor will cover two reprogramming events, due to technology changes/upgrades or customer needs
The Contractor will cover two reprogramming events, due to technology changes/upgrades or customer needs
95% success rate Contractor will cover two reprogramming events, due to technology changes/upgrades or customer needs
Periodic Inspection - COR will review monthly work order logs.

(Ver. Jun 2014)

File details come from the government source that posted it. Updated .