Attachments 27QA001_Revised.pdf
PDF 2 MB Posted
- Solicitation number
- W912WJ27QA001
About this file
This document contains informational photographs for a federal contract opportunity involving the installation of a generator system and associated electrical infrastructure at a facility with existing gate operations and control systems.
The project requires installation of a minimum 20 kW generator on a 20' x 20' square concrete pad, with the pad location centered where an existing tree will be removed prior to contract start. The generator will be accompanied by propane tanks and electrical distribution equipment configured within a 30' x 30' fenced area. Key infrastructure components include approximately 230 feet of underground conduit running from a generator pull box (located 130 feet from the pad) across an area with significant rock and vegetation to a pull box at gate operator stairs, where 30 feet of surface-mounted 2" PVC conduit extends to an existing wood control panel. An existing underground electric conduit is also present near the pad location. Electrical connections from the generator to the pull box system will connect to existing controls at the top of a dike, with the existing generator connection to be removed. The pad configuration, including spacing requirements for the generator, propane tanks, and electrical distribution equipment, will be finalized between the contractor and the Technical Point of Contact prior to installation, with adjustments made based on actual equipment dimensions and applicable safety regulations for combustibles.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ27QA001-0003.pdf | ||
| Amendment W912WJ27QA001-0002.pdf | ||
| Amendment W912WJ27QA001-0001.pdf | ||
| Solicitation Survey 27QA001.pdf | ||
| Attachments 27QA001.pdf | ||
| Solicitation W912WJ27QA001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Informational Photos (REVISED)
Image 1: Aerial photo showing where concrete pad is to be placed and where existing underground conduit is.
Min 20 kW
E6COUANM
Pencil
Image 2: Aerial photo showing conduit span to gate operator stairs/ pull box. Pull box at stairs has surface mounted 30’ of 2” PVC conduit extending to the wood control panel.
30’
Image 3: Photo showing the proposed site for the generator pad, fence, propane tanks and generator. Tree and stump will be removed before the start of contract. The center of the new pad will be in the location of the existing tree.
Image 4: Photo showing the proposed site from another angle
Image 5: Photo showing the generator pull box in line with the pull box on the stairs. 130' Approximately 230’ of conduit is ran from this point across to the stairs.
Cross-Out
Image 6: Photo showing the pull box on the stairs and the run to the generator pull box.
Image 7: Photo showing existing control panel at top of dike. Electrical connections are to be ran from generator to pull box, then up to these controls. Existing generator connection will be removed.
Image 8: Mock drawing of generator pad layout. Configuration will be finalized between contractor and TPOC prior to installation. Configuration will change based on generator dimensions, tank dimensions and safety regulations for combustibles. Drawing not to scale. *Note - the 20' x 20' pad shall be a square shape.
Min 20 kW
Pencil
File details come from the government source that posted it. Updated .