This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for vegetation control services at Mansfield Hollow Lake in Connecticut. The amendment, issued by the U.S. Army Corps of Engineers New England District, revises the descriptions for Contract Line Item Numbers (CLINs) 0001 and 0002 to remove references to cutting vegetation. The solicitation closing date remains January 15, 2026, at 2:00 PM Eastern.

The amendment includes a Request for Information (RFI) addressing a vendor's question about vegetation treatment procedures. The response clarifies that non-woody vegetation only requires chemical treatment and does not need to be cut or removed. Only the South Mansfield Hollow Dam treatment area will require "Cut Stump Chemical Treatment," which involves cutting, removing, and chemically treating stumps of woody vegetation. The contract covers chemical vegetation control services for two areas: Dike B (approximately 3 acres) and North Dam area (approximately 7 acres), with specific instructions outlined in the Performance Work Statement.

View the file

Other files

File Type Posted
Amendment W912WJ26QA029-0002.pdf PDF
Attachments 26QA029.pdf PDF
Solicitation W912WJ26QA029.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Continuation of Supplies or Services and Prices/Costs

The following CLIN(s) / SLIN(s) / ELIN(s) were modified:

INFORMATION FROM TO CHANGED

BY

Description Contractor shall provide all labor, materials, equipment and transportation to provide cutting and chemical vegetation control services to the Dike B area (Approximately 3 acres) at Mansfield Hollow Lake, Mansfield Center, CT in accordance with the Performance Work Statement.

Contractor shall provide all labor, materials, equipment and transportation to provide chemical vegetation control services to the Dike B area (Approximately 3 acres) at Mansfield Hollow Lake, Mansfield Center, CT in accordance with the Performance Work Statement.

INFORMATION FROM TO CHANGED

BY

Description Contractor shall provide all labor, materials, equipment and transportation to provide cutting and chemical vegetation control services to the North Dam area (Approximately 7 acres) at Mansfield Hollow Lake, Mansfield Center, CT in accordance with the Performance Work Statement.

Contractor shall provide all labor, materials, equipment and transportation to provide chemical vegetation control services to the North Dam area (Approximately 7 acres) at Mansfield Hollow Lake, Mansfield Center, CT in accordance with the Performance Work Statement.

Continuation of Description

W912WJ26QA0290001

Miscellaneous text in this section has been added to:

REQUEST FOR INFORMATION:

QUESTION 1: What is the procedure for the weedy grasses and such? Can those be hit with a line trimmer and material left (as it would be a finely shredded mess) or just spray the weeds, only cutting and removing woody material?

RESPONSE 1: Non-woody vegetation (such as tall grass and undesirable plant species) only requires chemical treatment. It is not required for the non-woody vegetative growth to be cut or removed. Only the South Mansfield Hollow Dam treatment area will require the "Cut Stump Chemical Treatment" which includes cutting, removing and chemically treating stumps of the woody vegetation. Please refer to Part 5.3. , of the Performance Work Treatment Locations Statement. The descriptions in CLINS 0001 and 0002 have been revised to remove the cutting verbiage.

W912WJ26QA0290001

IDCode: J
Page: 1
Pages: 3
AmendNo: 0001
EffDate: 07 JAN 2026
ReqNo:
ProjNo:
IssCode: W912WJ
AdmCode:
IssuedBy: W2SD ENDIST NEW ENGLAND

KO CONTRACTING DIVISION, 696 VIRGINIA ROAD

CONCORD, MA 01742-2751

UNITED STATES

ALICIA LACROSSE, EMAIL: ALICIA.N.LACROSSE@USACE.ARMY.MIL TELEPHONE: 978-318-8902

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W912WJ26QA029
SolDate: 05 JAN 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE CONTINUATION
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: Amendment is necessary to provide responses to questions from industry and revise the descriptions in CLINS 0001 and 0002.

Solicitation closing remains January 15, 2026 at 2:00 PM Eastern.

All other terms and conditions remain unchanged.

ContNameTitle:
CoNameTitle: JENNIFER SAMELA
ContDate:
CODate: 07 JAN 2026