Specifications.pdf

PDF 989 KB Posted

Attached to
Paving Repairs, Bourne Bridge, Bourne, MA Federal contract opportunity
Solicitation number
W912WJ26BA006
Issued by
Department of the Army Corps of Engineers Engineering District New England

About this file

This is a comprehensive technical specification document for a pavement repair project on the Bourne Bridge over the Cape Cod Canal in Massachusetts. The U.S. Army Corps of Engineers is soliciting a contract for replacing the existing 2-inch thick bituminous concrete pavement wearing surface course on a 2,366-foot-long, 40-foot-wide section of the bridge. The project requires a Superpave Waterproofing Surface Course mix and involves replacing compression strip seals at six deck joint locations.

Key project requirements include completing the work during two specific time windows (May 1-21, 2026 or September 8-October 11, 2026), strict temperature and moisture limitations for paving, and maintaining traffic flow with one 12-foot lane in each direction during construction. The contractor must utilize multiple full production crews working 24/7, provide two law enforcement police details, and install new pavement markings across a 2,684-foot length, including a center double yellow line and white skip lines. The total pavement replacement will be performed in three sequential phases, with careful attention to surface preparation, joint adhesive application, and compaction specifications.

View the file

Other files for this federal contract opportunity

Other files attached to Paving Repairs, Bourne Bridge, Bourne, MA, newest first.
File Type Posted
Bid Abstract.pdf PDF
Solicitation Amendment W912WJ26BA0060004.pdf PDF
Drawings.pdf PDF
Solicitation Amendment W912WJ26BA0060002.pdf PDF
Solicitation Amendment W912WJ26BA0060003.pdf PDF
Solicitation Amendment W912WJ26BA0060001.pdf PDF
Solicitation - W912WJ26BA006.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number:

W912WJ26BA006

Pavement Repair, Bourne Bridge

Cape Cod Canal, Bourne, Massachusetts

Construction Solicitation and Specifications

November 2025

Pavement Repair, Bourne Bridge, Cape Cod Canal, Bourne, MA

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 41 00 BIDDING SCHEDULE

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 22 00 MEASUREMENT AND PAYMENT

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 71 23 FIELD ENGINEERING

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

DIVISION 05 - METALS

05 83 30 COMPRESSION SEAL JOINTS

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 10 00 BITUMINOUS CONCRETE PAVEMENT

32 17 23 PAVEMENT MARKINGS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.2 REFERENCES

1.3 SUBMITTALS

1.4 PROTECTION OF EXISTING STRUCTURES, UTILITIES, AND WORK

1.4.1 General

1.4.2 Debris Control

1.5 SUPERINTENDENCE BY THE CONTRACTOR

1.6 PROJECT/SITE CONDITIONS

1.6.1 Site Security

1.7 WORK SEQUENCE AND SCHEDULING

1.7.1 General

1.7.2 1.7.2 Work Sequence

1.7.3 Schedule

1.7.3.1 Initial Project Schedule

1.7.3.2 Periodic Schedule Updates

1.7.3.3 Weekly Progress Meetings

1.7.3.4 Rate of Progress

1.8 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES

1.9 CONTRACTOR USE OF PREMISES

1.9.1 Access to the Site and Storage/Staging Areas

1.9.2 Work Limits

1.9.3 Protection and Security

1.9.4 Work By Other Contractors

1.9.5 Emergency Contacts

1.9.6 Damaged Property

1.9.7 Contractor's Receipt of Supplies

1.9.8 Daily Clean Up

1.9.9 Government Sanitary Facilities

1.10 QUALITY ASSURANCE

1.11 GENERAL SAFETY REQUIREMENTS

1.11.1 General

1.11.2 Contractor's Project Superintendent

1.12 ENVIRONMENTAL PROTECTION

1.13 PRECONSTRUCTION CONFERENCE

1.14 AS-BUILT DRAWINGS

1.14.1 Preparation of As-Built Drawings

1.15 RECORD DRAWINGS

1.15.1 Final Record Drawing Annotation

1.15.2 Preparation and Submission of Record Drawings

1.15.3 Record Drawing Re-Submission Requirements

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 11 00 Page 1

-- End of Section Table of Contents --

SECTION 01 11 00 Page 2

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.

The project site is located on the Bourne Bridge over the Cape Cod Canal in Bourne, Massachusetts. The bridge carries State Route 28, consisting of four lanes with an Annual Average Daily Traffic (AADT) of approximately 50,000 vehicles. The work of this project includes removal and replacement of the existing 2-inch thick bituminous concrete pavement wearing surface course between the north and south abutments of the Bourne Bridge. The pavement on the abutments was recently replaced under a separate contract and is not included in this scope.

The pavement replacement area is approximately 2,366 feet in length by 40 feet in width. The new bituminous concrete wearing surface course shall be a Superpave Waterproofing Surface Course mix in accordance with Massachusetts State Specifications listed by MassDOT; refer to Specification Section 32 10 00 BITUMINOUS CONCRETE PAVEMENT. Compression strip seals shall be replaced at six deck joint locations within the pavement area; refer to Specification Section 05 83 30 COMPRESSION SEAL JOINTS. See Drawing Sheet S-101 that shows the area of pavement replacement and deck joint locations. Milling operations are strictly prohibited to demolish the existing bituminous wearing course due to risk of damage to the underlying steel grid deck.

Contract work on the bridge is required to be performed outside of the summer season defined as Memorial Day weekend (May 22, 2026) to Labor Day weekend (Sep 7, 2026). The Contractor is required to complete all contract work on the bridge during one of two periods; either May 1 - May 21, 2026 or September 8 - October 11, 2026. See Subpart 1.7 WORK SEQUENCE AND SCHEDULING for sequence and scheduling requirements.

Significant traffic control measures will be necessary for work on the bridge. When lane restrictions are implemented, the Contractor shall utilize multiple full production crews, operating 24 hours per day, 7 days per week, to complete work and minimize traffic disruptions.

The Contractor shall schedule and pay for two law enforcement police details, one Massachusetts State Police and one Bourne Police Department, for the entire duration when lane restrictions are in place for work on the bridge. Refer to Drawing Sheets G-002, C-101, C-102, C-103, C-104 and C-601 for the required traffic control plan, signage and message boards that shall be implemented and maintained by the Contractor. The required traffic control plan is to complete work in three sequential phases across the roadway. Work shall be completed in a 13-foot wide work area while one 12-foot wide travel lane in each direction is maintained for public travel across the bridge. All work on the bridge shall be coordinated with both the U.S. Army Corps of Engineers (USACE) and the Massachusetts

SECTION 01 11 00 Page 3

Department of Transportation (MassDOT).

The Contractor shall provide new pavement markings on the Bourne Bridge, including the new pavement area and abutments, a length of 2,684 feet, to replicate the existing striping layout. The striping configuration shall include a center double yellow line and white skip lines for lane division, consistent with the current traffic lane arrangement. All pavement markings shall be installed in accordance with the requirements specified in SECTION 32 17 23 PAVEMENT MARKINGS.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety and Occupational Health (SOH) Requirements

ERDC/ITL TR-12-1 (2015) A/E/C Graphics Standard, Release 2.0

ERDC/ITL TR-12-6 (2015) A/E/C CAD Standard, Release 6.0

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Initial Project Schedule ; G, RO

In accordance with the contract clauses, the Contractor shall, within 15 days after receipt of Notice to Proceed (NTP) or as otherwise determined by the Contracting Officer, submit for approval a practicable project schedule. When changes are authorized that result in contract time extensions, the Contractor shall submit a revised project schedule for approval by the Contracting Officer.

SD-07 Certificates

Periodic Schedule Updates ; G, RO

SD-11 Closeout Submittals

As-Built Drawings ; G, DO

As-built drawings, which are paper mark-ups and scanned PDF's of the paper mark-ups, showing all deviations which have been made from the contract drawings, shall be submitted to the Contracting Officer for approval at the completion of work. See Subpart AS-BUILT DRAWINGS for record keeping and submittal requirements.

SECTION 01 11 00 Page 4

Record Drawings ; G, DO

Record drawings, which are CAD and/or BIM files showing all deviations which have been made from the contract drawings, shall be submitted to the Contracting Officer for approval at the completion of work. See Subpart RECORD DRAWINGS for record keeping and submittal requirements.

1.4 PROTECTION OF EXISTING STRUCTURES, UTILITIES, AND WORK

1.4.1 General

The Contractor shall protect the existing bridge structures and all utilities from damage or interruption of service. Protect existing granite curbs, drain grates, joint angles, sidewalks and pavement adjacent to work areas. Damage or any interruption of service resulting from the Contractor's operations shall be repaired or service restored promptly at the expense of the Contractor.

1.4.2 Debris Control

Care shall be taken that no bridge material, pieces of support structures, debris, or any materials whatsoever, fall into the canal or to the ground. Should debris or construction materials fall from the bridge inadvertently, prompt corrective action shall be taken to prevent further occurrences and the fallen items shall be secured and removed. The Contractor shall take all precautions practicable to prevent items from falling from the bridge. Debris deposited on horizontal surfaces of the superstructure and piers shall be collected and disposed of properly.

Sweeping of debris off the bridge to the land or water below will not be permitted. No falling debris will be tolerated as the Canal is continually open to marine traffic.

1.5 SUPERINTENDENCE BY THE CONTRACTOR

A. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.

B. The qualified superintendent, and competent alternate, shall be capable of reading, writing, and conversing fluently in the English language.

C. The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

D. The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend partnering meetings, and quality

SECTION 01 11 00 Page 5 control meetings.

E. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.

F. The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

G. The project superintendent may not serve as the Site Safety and Health Officer (SSHO) nor the Contractor Quality Control (CQC) System Manager.

1.6 PROJECT/SITE CONDITIONS

1.6.1 Site Security

The Contractor shall report any vandalism, suspicious activities or devices to the Contracing Officer or local police as soon as possible.

The Contracting Officer will notify the Contractor of any heightened security measures and will expect vigilant monitoring of equipment, grounds and security fencing while working. At a heightened security posture, there may be work areas that are restricted. The Contracting Officer will notify the Contractor of these restricted areas.

1.7 WORK SEQUENCE AND SCHEDULING

1.7.1 General

Lane restrictions on the Bourne bridge shall not be implemented during the summer season defined as Memorial Day weekend (May 22, 2026) to Labor Day weekend (Sep 7, 2026). The purpose of this restriction is to minimize traffic impacts during peak season travel.

The specified Superpave Waterproofing Surface Course mix requires a minimum surface temperature of 50° Fahrenheit at the time of installation. This product is generally available from May through October, as reported by regional bituminous suppliers. The Contractor shall account for these conditions in the proposed construction schedule.

The Contractor shall complete all bridge-related work within one of the following periods: May 1 - May 21, 2026 or September 8 - October 11, 2026.

When lane restrictions are implemented, the Contractor shall utilize multiple full production work crews to work 24 hours per day, 7 days per week, to complete work and minimize the duration of lane restrictions on the bridge. The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in SPECIAL CONTRACT REQUIREMENTS, Clause COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR

1984) FAR 52.211-10.

Liquidated damages will be assessed for each day that the Contractor and

SECTION 01 11 00 Page 6 all traffic control devices are not completely removed from the bridge during the time periods specified.

1.7.2 1.7.2 Work Sequence

Work on the bridge shall be completed in three sequential phases across the roadway. Work shall be completed in a 13-foot wide work area with one 12-foot wide travel lane in each direction always maintained for public travel across the bridge. The Contractor shall determine the optimal sequence of operations within each phase, subject to traffic control constraints.

PHASE I: Closure of the Sidewalk Side Work Area

a. Remove the existing 2" thick bituminous concrete wearing surface within this work area.

b. Install 2" Superpave Waterproofing Surface Course. Refer to Section 32 10 00 BITUMINOUS CONCRETE PAVEMENT.

c. Replace compression strip seals at six joint locations.

PHASE II: Closure of the Middle Work Area

a. Remove the existing 2" thick bituminous concrete wearing surface within this work area.

b. Install 2" Superpave Waterproofing Surface Course. Refer to Section 32 10 00 BITUMINOUS CONCRETE PAVEMENT.

c. Replace compression strip seals at six joint locations.

PHASE III: Closure of the Curb Side Work Area

a. Remove the existing 2" thick bituminous concrete wearing surface within this work area.

b. Install 2" Superpave Waterproofing Surface Course. Refer to Section 32 10 00 BITUMINOUS CONCRETE PAVEMENT.

c. Replace compression strip seals at six joint locations.

The line striping work on the roadway shall be done after completing all other pavement and joint work in phases 1, 2 and 3.

1.7.3 Schedule

1.7.3.1 Initial Project Schedule

The initial project schedule shall be in the form of a chart graphically indicating the sequence proposed pursuant to FAR Clause 52.236-15 "Schedules for Construction Contracts". Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all activities. The chart shall be prepared to show the starting and completion dates of all work phases on a linear horizontal time scale beginning with date of Notice to Proceed and indicating calendar days to completion. The scheduling of the entire project is required. The Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion

SECTION 01 11 00 Page 7 of the project. This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised.

Anticipated adverse weather delay days shall be included in the schedule.

Submit the Initial Project Schedule for approval within 30 calendar days after notice to proceed is issued.

The Contractor shall not work on Federal legal holidays unless otherwise authorized by the Contracting Officer. The following legal holidays will be observed:

January 1 January 19 February 16 May 25 June 19 July 4 September 7 October 12 November 11 November 26 December 25

1.7.3.2 Periodic Schedule Updates

An updated schedule showing actual progress shall be submitted monthly and with each pay request. Changes to the base-line schedule shall be outlined in a narrative describing the reason for the change.

1.7.3.3 Weekly Progress Meetings

Conduct a weekly meeting with the Government (or as otherwise mutually agreed to) for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress, and to review planned activities for the upcoming two weeks. Use the current approved schedule update for the purposes of this meeting and for the production and review of reports. At the weekly progress meeting, address the status of RFIs, RFPs and Submittals.

1.7.3.4 Rate of Progress

Should the Contractor fail to maintain a satisfactory rate of progress in accordance with the Contractor's approved progress schedule, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought up to schedule and maintained.

1.8 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES

The Contractor shall be responsible for the following:

(1) Determining the trucking and hauling routes and associated restrictions to and from the work, to include the coordination for the use of such routes with local, State, and Federal authorities.

(2) Complying with all local, State, and Federal regulations and restrictions when using any facilities or hauling routes.

SECTION 01 11 00 Page 8

1.9 CONTRACTOR USE OF PREMISES

1.9.1 Access to the Site and Storage/Staging Areas

Access to the project site is limited to the specified dates scheduled for work and as indicated on the contract drawings. The Contractor is responsible for maintaining access necessary for its equipment, material, and plant to and from the work area.

Access to temporary facilities and storage/staging areas shall be as specified in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS. Confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

1.9.2 Work Limits

Work shall be restricted to the limits of the work as shown on the contract drawings and to storage areas as indicated in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, as shown on the contract drawings, and as indicated by the Contracting Officer.

1.9.3 Protection and Security

a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.

b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.

c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.

1.9.4 Work By Other Contractors

During the performance period of this contract, no other work is anticipated to occur by other contractors.

1.9.5 Emergency Contacts

The Contractor shall provide a list of emergency contacts to be used in the event of an emergency. The list shall include the contact names, addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.9.6 Damaged Property

Work shall proceed in a manner which will minimize disturbance or risk of damage to structures and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.

1.9.7 Contractor's Receipt of Supplies

The Contractor shall be responsible for all arrangements for the receipt

SECTION 01 11 00 Page 9 of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.

1.9.8 Daily Clean Up

The Contractor shall at all times keep rubbish from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be removed from the premises daily.

1.9.9 Government Sanitary Facilities

Toilet facilities are not available on site for the Contractor's use. The Contractor shall provide portable toilets for its personnel and subcontractors as specified in Section 01 50 00 TEMPORARY CONSTRUCTION

FACILITIES AND CONTROLS.

1.10 QUALITY ASSURANCE

A. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.

B. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government.

Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.

C. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.

D. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.

E. The Contractor shall submit all requests for changes in writing to the Contracting Officer. Do not proceed with changes without possession of written authorization of the Contracting Officer.

F. The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.

1.11 GENERAL SAFETY REQUIREMENTS

1.11.1 General

The Contractor shall take all necessary precautions in observing safety regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and

SECTION 01 11 00 Page 10 egress. Temporary closures shall not compromise life safety, security or fire safety.

1.11.2 Contractor's Project Superintendent

The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of violations, etc., and including that of any subcontractor's work.

1.12 ENVIRONMENTAL PROTECTION

To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 19 ENVIRONMENTAL PROTECTION, and all applicable federal, state, and local laws and regulations concerning environmental protection pollution control and abatement.

1.13 PRECONSTRUCTION CONFERENCE

The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the U.S. Army Corps of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contractor's Superintendent, Quality Control Representative, and Site Safety and Health Officer (SSHO) shall attend this conference.

1.14 AS-BUILT DRAWINGS

Maintain at the jobsite one set of paper full-size contract drawings marked to show all deviations that have been made from the contract drawings, including buried or concealed construction and utility features revealed during the course of construction. Record the horizontal and vertical location of all buried utilities that differ from the contract drawings. These drawings shall be available for review by the Contracting Officer at all times. Upon completion of the work, submit the original marked set of prints to the Contracting Officer for approval. Also, provide PDFs of the current working redlines and/or markups complying with the as-built drawings and markup requirements. Requests for partial payments will not be approved if the marked prints and PDF files are not current, and request for final payment will not be approved until the marked prints and PDF files are submitted to and approved by the Contracting Officer.

1.14.1 Preparation of As-Built Drawings

The entries shall be made in the jobsite set of prints at the time field changes are made, pertinent information collected, or need for corrections established, as a continuing process during the life of the contract. As revised drawings are issued by the Contracting Officer, revised prints shall be introduced into the set to replace the superseded drawings and all applicable notations previously made on the superseded drawings transferred to the current prints. Carefully prepared sketches, not less than 8-1/2" x 11", may be used to depict changes or added information in lieu of notations on the actual prints. Staple sketches to the prints

SECTION 01 11 00 Page 11 affected by the change. All plan views, sections, elevations, profiles, diagrams, details, or schedules affected by a change shall be marked up as required to reflect the change. All notations or changes made on the prints shall be in sufficient detail to clearly depict the change.

Colored pens or pencils shall be used to make notations on the record prints as follows:

Red pen or pencil shall be employed to indicate added or corrected work or information.

Green pen or pencil shall be used to show the deleted or incorrectly depicted work or information.

Blue or black pen or pencil shall be used to show information not to be recorded on the drawings but included on the marked-up prints for explanatory or clarification purposes for the benefit of the Contracting Officer.

1.15 RECORD DRAWINGS

The record drawings are the final compilation of actual conditions reflected in the as-built drawings. The record drawings are CAD and/or BIM files produced from the source drawing files and marked-up as-built drawings.

The Contractor shall request the full set of electronic drawings, in the source CAD and/or BIM format, for Record Drawing preparation, after award and at least 30 days prior to required use. The Government will provide one set of "as-designed" electronic CAD and/or BIM files. The CAD and/or BIM files are provided to enable preparation of record drawings. If discrepancies exist between the CAD and/or BIM files and the contract PDF drawings, correct the CAD and/or BIM files to show the contract PDF drawings. The Government has no responsibility to modify any GFM due to changes in the design that occur after award.

The Contractor shall prepare the CAD drawing files in AutoCAD Version 2021. The Contractor shall prepare the BIM files in Revit Version 2021.

If additional drawings are required, prepare them using the specified electronic file format applying the same graphic standards specified for original drawings, ERDC/ITL TR-12-6 and ERDC/ITL TR-12-1 . The title block and drawing border to be used for any new final record drawings must be identical to that used on the contract drawings.

If a sheet needs to be added between two sequential sheets, append a Supplemental Drawing Designator in accordance with ERDC/ITL TR-12-6 , "Adding a Drawing Sheet", and ERDC/ITL TR-12-1 , "Adding or Deleting Drawing Sheets and Index Sheet Procedures".

Provide electronic PDF files of all CAD and/or BIM contract drawings sheets associated with the record drawing submittal. Compile and organize the PDF set to match the contract drawings.

1.15.1 Final Record Drawing Annotation

When final revisions have been completed, show the wording "RECORD DRAWING AS-BUILTS" followed by the name of the Contractor in letters at least 3/16 inch high on the cover sheet drawing. Show the wording "RECORD DRAWING AS-BUILTS" in the revision block of each drawing.

SECTION 01 11 00 Page 12

1.15.2 Preparation and Submission of Record Drawings

Within 30 days after Government approval of all of the working as-built drawings, prepare the final CAD and/or BIM record drawings and submit CAD and/or BIM and PDF drawing files. Also submit all external references (x-refs), plot style files, and all other required CAD and/or BIM resource files. The Government will promptly return one set of prints annotated with any necessary corrections. Within 7 calendar days revise the CAD and/or BIM files accordingly at no additional cost and submit one set of final CAD and/or BIM files and PDF files to the Government. Drawing files and storage media submitted will become the property of the Government upon final approval. Failure to submit final record drawings as specified will be cause for withholding any payment due under this contract.

Approval and acceptance of final record drawings must be accomplished before final payment is made.

1.15.3 Record Drawing Re-Submission Requirements

If elements of a record drawing submittal are rejected, provide the following for each re-submission, in addition to any information required in Section 01 33 00 SUBMITTAL PROCEDURES:

A. Re-submit all CAD and/or BIM components, including updated content in response to Government comments.

B. Provide a copy of all Government review comments.

C. Provide a disposition/response to each Government review comment for a back-check of the re-submission deliverable.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

SECTION 01 11 00 Page 13

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 CONTRACT COST BREAKDOWN

1.2 JOB PAYMENT ITEM

1.3 BIDDING SCHEDULE - PAYMENT ITEM

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 1

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 CONTRACT COST BREAKDOWN

The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.

1.2 JOB PAYMENT ITEM

The pPayment item for the work of this contract for which contract job payments will be made is listed in the BIDDING SCHEDULE and described below. The job price and payment made for the item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.3 BIDDING SCHEDULE - PAYMENT ITEM

The payment item for the work of this contract on which the contract progress payments will be based is listed in the BIDDING SCHEDULE and is described below. All costs for items of work, which are not specifically mentioned to be included in the Bidding Schedule job price payment item shall be included in the listed job item shown.

A. Item Number 0001, "All Work".

All costs for labor, equipment, and materials for all steel repair, painting, and other work of this project, as shown on the contract drawings and in accordance with the specifications.

Unit of Measure: Job.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 2

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 MINIMUM INSURANCE REQUIREMENTS

1.2 SUPERVISION

1.3 PRECONSTRUCTION CONFERENCE

1.4 PARTNERING

1.4.1 Team-Led (Informal) Partnering

1.5 ELECTRONIC MAIL (E-MAIL) ADDRESS

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.

1.2 SUPERVISION

See Section 01 11 00 SUMMARY OF WORK, Subpart SUPERINTENDENCE BY THE

CONTRACTOR.

1.3 PRECONSTRUCTION CONFERENCE

See Section 01 11 00 SUMMARY OF WORK, Subpart PRECONSTRUCTION CONFERENCE.

1.4 PARTNERING

The Contractor shall host the partnering session within 45 calendar days of contract award. To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the Contractor and key subcontractors are required to participate in the Partnering process.

1.4.1 Team-Led (Informal) Partnering

a. The Contractor will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be led by the Contractor's Project Manager.

b. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, at the Contractor's temporary trailer.

c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contractor.

d. The Partners will determine the frequency of the follow-on sessions.

e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.

SECTION 01 30 00 Page 2

1.5 ELECTRONIC MAIL (E-MAIL) ADDRESS

Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.1.1 Submittal Information

1.1.2 Project Type

1.1.3 Submission of Submittals

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

1.2.2 Approving Authority

1.2.3 Work

1.3 SUBMITTALS

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

1.4.1.1 Approval Codes

1.4.2 For Information Only

1.4.3 Sustainability Reporting Submittals (S)

1.5 PREPARATION

1.5.1 Transmittal Form

1.5.2 Submittal Format

1.5.2.1 Format of SD-01 Preconstruction Submittals

1.5.2.2 Format for SD-02 Shop Drawings

1.5.2.2.1 Drawing Identification

1.5.2.3 Format of SD-03 Product Data

1.5.2.3.1 Product Information

1.5.2.3.2 Standards

1.5.2.3.3 Data Submission

1.5.2.4 Format of SD-04 Samples

1.5.2.4.1 Sample Characteristics

1.5.2.4.2 Sample Incorporation

1.5.2.4.3 Comparison Sample

1.5.2.5 Format of SD-05 Design Data

1.5.2.6 Format of SD-06 Test Reports

1.5.2.7 Format of SD-07 Certificates

1.5.2.8 Format of SD-08 Manufacturer's Instructions

1.5.2.8.1 Standards

1.5.2.9 Format of SD-09 Manufacturer's Field Reports

1.5.2.10 Format of SD-10 Operation and Maintenance Data (O&M)

1.5.2.11 Format of SD-11 Closeout Submittals

1.5.3 Source Drawings for Shop Drawings

1.5.3.1 Source Drawings

1.5.3.2 Terms and Conditions

1.6 QUANTITY OF SUBMITTALS

1.6.1 Number of SD-04 Samples

1.7 INFORMATION ONLY SUBMITTALS

1.8 PROJECT SUBMITTAL REGISTER

1.8.1 Submittal Management

SECTION 01 33 00 Page 1

1.8.2 Preconstruction Use of Submittal Register

1.8.3 Contractor Use of Submittal Register

1.8.4 Approving Authority Use of Submittal Register

1.8.5 Action Codes

1.8.5.1 Contractor Action Codes

1.8.6 Delivery of Copies

1.9 VARIATIONS

1.9.1 Considering Variations

1.9.2 Proposing Variations

1.9.3 Warranting that Variations are Compatible

1.9.4 Review Schedule Extension

1.10 SCHEDULING

1.11 GOVERNMENT APPROVING AUTHORITY

1.11.1 Review Notations

1.12 DISAPPROVED SUBMITTALS

1.13 APPROVED SUBMITTALS

1.14 APPROVED SAMPLES

1.15 WITHHOLDING OF PAYMENT

1.16 STAMPS

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 33 00 Page 2

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.1.1 Submittal Information

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

1.1.2 Project Type

The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

1.1.3 Submission of Submittals

Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:

SD-01 Preconstruction Submittals

Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.

Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.

SECTION 01 33 00 Page 3

Certificates Of Insurance

Surety Bonds

List Of Proposed Subcontractors

List Of Proposed Products

Baseline Network Analysis Schedule (NAS)

Submittal Register

Schedule Of Prices Or Earned Value Report

Accident Prevention Plan

Work Plan

Quality Control (QC) plan

Environmental Protection Plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after

SECTION 01 33 00 Page 4 installation.

Investigation reports

Daily logs and checklists

Final acceptance test and operational test procedure

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Confined space entry permits

Text of posted operating instructions

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system or material, including special notices and (SDS)concerning impedances, hazards and safety precautions.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.2.2 Approving Authority

Office or designated person authorized to approve the submittal.

1.2.3 Work

As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.

SECTION 01 33 00 Page 5

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register ; G, RO

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."

1.4.1.1 Approval Codes

A. Construction Division {"AO" (Area Office), "RO" (Resident Office), or "PO" (Project Office) Reviewer}: An "AO", "RO", or "PO" in column "f" indicates that the submittal review action is by New England District Construction Division. Send all such submittals to the project Resident or Area Engineer, as applicable.

B. Engineering Division {"DO" (District Office) Reviewer): A "DO" on the attached submittal register, column "f" indicates that the submittal review action is by the New England District, Engineering Division, or other organization in the District Office. Send all such submittals to the project Resident or Area Engineer for distribution to the appropriate approving authority.

C. Government acceptance is required for submittals with a "G, A" designation.

1.4.2 For Information Only

Submittals not requiring Government approval will be for information only. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."

1.4.3 Sustainability Reporting Submittals (S)

Submittals for Guiding Principle Validation (GPV) or Third Party Certification (TPC) are indicated with an "S" designation. These submittals are for information only and for use as specified in Section

01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING.

Schedule submittals for these items throughout the course of construction as provided; do not wait until closeout.

SECTION 01 33 00 Page 6

1.5 PREPARATION

1.5.1 Transmittal Form

Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms are attached at the end of this section and are included in the RMS CM software that the Contractor is required to use for this contract.

Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.5.2 Submittal Format

1.5.2.1 Format of SD-01 Preconstruction Submittals

When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.

Provide data in the unit of measure used in the contract documents.

1.5.2.2 Format for SD-02 Shop Drawings

Provide shop drawings not less than 8-1/2 by 11 inches nor more than 30 by 42 inches, except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required.

Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.

a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.

b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.

Submit an electronic copy of drawings in PDF format.

1.5.2.2.1 Drawing Identification

Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph

IDENTIFYING SUBMITTALS.

Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.

Reserve a blank space on the right-hand side of each sheet for the Government disposition stamp.

SECTION 01 33 00 Page 7

1.5.2.3 Format of SD-03 Product Data

Present product data submittals for each section as a complete, bound volume. Include a table of contents, listing the page and catalog item numbers for product data.

Indicate, by prominent notation, each product that is being submitted;

indicate the specification section number and paragraph number to which it pertains.

1.5.2.3.1 Product Information

Supplement product data with material prepared for the project to satisfy the submittal requirements where product data does not exist. Identify this material as developed specifically for the project, with information and format as required for submission of SD-07 Certificates.

Provide product data in units used in the Contract documents. Where product data are included in preprinted catalogs with another unit, submit the dimensions in contract document units, on a separate sheet.

1.5.2.3.2 Standards

Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .