This is a Request for Quotations (RFQ) issued by the U.S. Army Corps of Engineers for preliminary title commitments and related services for seven parcels located in Plymouth, Massachusetts. The solicitation seeks a contractor to provide title evidence, title insurance, and optional closing services for temporary work area easements related to the Plymouth Long Beach Dike repair project.
The primary deliverables include preliminary title commitments within 30 days of contract award, with options for title commitment continuations, closing services, and final title insurance policies for each parcel. The contract will be awarded based on price alone, with no technical proposal required. Vendors must be registered in the System for Award Management (SAM) and submit quotes via email by September 2, 2025. The total period of performance is one year from contract award, with various optional tasks that can be exercised by the government, including title research, continuations, closing services, and final title policies for individual parcels along Ryder Way in Plymouth.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ25QA082-0004.pdf | ||
| Amendment W912WJ25QA082-0003.pdf | ||
| Amendment W912WJ25QA082-0001.pdf | ||
| Solicitation W912WJ25QA082.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Solicitation/Contract Form Continuation
The following changes have been made:
INFORMATION FROM TO
Response Due Date 29 Aug 2025 02 Sep 2025
Miscellaneous text in this section has been added to:
REQUEST FOR INFORMATION:
QUESTION 1: Since this is a fixed-price requirement, could you confirm how the Government envisions structuring the title and closing services? Title costs often fluctuate depending on the nature of the transaction, so we want to be sure we approach pricing correctly.
RESPONSE 1: As a firm-fixed price contract, the Government will only pay for the services provided at the agreed upon awarded amounts for each line item in the bid schedule. Vendors should account for fluctuating costs in their quote pricing, and any changes in costs are a risk assumed by the awarded Contractor.
QUESTION 2: Are the seven parcels expected to be purchased by the United States or disposed of/sold?
RESPONSE 2: No. The Government is not purchasing any of these parcels in fee or disposing of/selling the parcels. (See answer to question 4 below.)
QUESTION 3: The solicitation references parcels at 3R, 7, 9R, 11, 15, 17, and 21 Warren Avenue in Plymouth, but also elsewhere mentions Ryder Way. Could you confirm whether the Warren Avenue addresses are the official parcel references we should use for our title commitments?
RESPONSE 3: The parcel references in your question do not match the parcel number referenced in the solicitation. The parcel numbers are as follows: PARCEL ID: 037A-000-000Q-000 PARCEL ID: 037A- 000-000O-003, also known as 370 Ryder Way PARCEL ID: 037A-000-000O-004, also known as 322 Ryder Way PARCEL ID: 037A000-000O-006, also known as 318 Ryder Way PARCEL ID: 037A-000- 000S-000, also known as 228 Ryder Way PARCEL ID: 037A-000-004-000, also known as 152 Ryder Way PARCEL ID: 037A-000-003-000, also known as Ryder Way.
QUESTION 4: Can you provide more information on these properties and expectations? Are these fee acquisitions or easement acquisitions?
RESPONSE 4: The purpose of this action is to obtain temporary work area easements to allow the Government sufficient access and time to these parcels to repair and/or maintain the existing Plymouth Long Beach Dike.
QUESTION 5: What is the physical address for APN 037A-000-000Q-000 as the other parcels indicate a physical address?
RESPONSE 5: According to the Town of Plymouth, MA assessor's office web site, no physical address is provided for parcel no. 037A-000-000Q-000. However, the parcel overlaps Ryder Way, Plymouth, Massachusetts.
W912WJ25QA0820002
QUESTION 6: What is the physical address for APN 037A-000-003-000 as the other parcels indicate a physical address?
RESPONSE 6: A search of the Town of Plymouth, MA assessor's office records for parcel no. 037A-000- 003-000 simply references "Ryder Way" and a Certificate of Title No. 77594. The Massachusetts Registry District of the Land Court shows a deed referencing the property address as being "Warren's Cove, Plymouth, MA" and indicating the owner is the Trust for the benefit of Louise W. Meyer and others dated October 17, 1977, The Certificate of Title indicates Barbara W. Meyer, Orin H. Meyer, Robert H. Meyer and Richard R. Meyer as being the trustees. The Certificate of Title is recorded with the Plymouth County Registry District of the Land Court as Certificate No. 77954, Document No. 291340 recorded on September 29, 1998. No physical address number is provided for this parcel. Therefore, there is no known physical address for this parcel.
QUESTION 7: What will the Government provide to a contractor as part of an assignment of work -vesting deed? Aerial map of acquisition area?
RESPONSE 7: The Government will provide any/all maps, construction maps and information known by the U.S. Army Corps of Engineers to assist in identifying the parcels so as to allow the awarded vendor to complete their work.
QUESTION 8: Does the Government have copies of vesting deeds that they can provide to an offeror for evaluation for search quotes?
RESPONSE 8: No. Vesting deeds should be provided to the Government by the awarded Contractor.
QUESTION 9: Does the Government have acquisition values for each parcel? We would need this for quoting title insurance.
RESPONSE 9: Currently, no. The Government anticipates obtaining an appraised value for the temporary work area easements in-house, after the initial title exams are provided.
QUESTION 10: In the Technical Requirements, paragraphs 1.a. and 6. address ownership of subsurface rights. Mineral severance deeds identify the owner of the subsurface rights at the time of the severance.
a. Typically the Government wants us to identify the severance and provide a copy of the mineral severance deed. Is this acceptable?
b. In considering the above, this solicitation appears to require the contractor to identify the present owner of the subsurface rights meaning that the ownership needs to be traced from that severance whenever it was to the present day. This type of work is not performed by title companies. It is typically performed by landmen and outside of traditional title searches and difficult to quote without basic information about the severance. Please confirm that this step is not a requirement of this solicitation.
c. If it is confirmed that present day subsurface rights ownership is to be determined, would the Government consider removing this requirement from the basic pricing of the search work in the solicitation and handling this as a separate task to be quoted only when it is needed such as for closing costs described in Part III, paragraph 5.
RESPONSE 10a-c: The Government is no longer requesting subsurface mineral rights information in the title exam. The Performance Work Statement has been revised to remove this requirement.
QUESTION 11: Regarding closing services:
a. Please confirm that the Government will prepare the deed.
b. Please confirm that the deed will come with the Acceptance by Grantee page pre-signed by the Government.
c. Please confirm that the Government will prepare the "Payment and Closing Sheet".
d. Is a mailaway closing whereby the documents can be shipped to the seller for execution and notarization?
RESPONSE 11a: Yes, the Government will draft the easement deed.
RESPONSE 11b. Yes, the deed will come with the Acceptance by Grantee page pre-signed by the Government.
RESPONSE 11c. No, the Government has the option to exercise CLIN option number nine (9) thru fifteen (15), for closing services.
RESPONSE 11d. If the landowners are out of state, yes, the easements will be sent out for signature either by the Government or the Closing Attorney.
QUESTION 12: The solicitation states that an award will be made based on price only. Please confirm that a narrative proposal regarding technical expertise and past performance, etc. is not required as part of an offer for this work.
RESPONSE 12: Correct, the award will be made on price alone, and a narrative proposal regarding technical expertise and past performance is not required.
QUESTION 13: Do the sellers have legal representation/counsel in these transactions or are the sellers required to have legal representation/counsel in these transactions or are you aware if the sellers have legal representation/counsel in these transactions?
RESPONSE 13: Currently, is unknown whether any of the landowners are represented by counsel or will be in the future. The one exception currently known is the Town of Plymouth, Massachusetts, which is represented by Town Counsel. It is not a requirement of the Government that the parties be represented by counsel.
QUESTION 14: Are these transactions considered residential or commercial transactions?
RESPONSE 14: Based upon the limited information known, it is believed that these transactions will be residential transactions. These parcels consist mostly of vacant land and/or residential structures which appear to be vacation home(s), beach rental(s) or possibly primary residence(s).
Continuation of Description
Miscellaneous text in this section has been modified to:
INSTRUCTION TO VENDORS:
VENDORS SUBMITTING A QUOTE IN RESPONSE TO A SOLICITATION ARE RESPONSIBLE
FOR ADHERING TO ALL INSTRUCTIONS AND TERMS AND CONDITIONS INCLUDED IN THE
SOLICITATION. FAILURE TO DO SO MAY RESULT IN QUOTES BEING DEEMED NON-
RESPONSIVE.
INFORMATION:
This is a Request for Quotations (RFQ) in accordance with Federal Acquisition Regulation (FAR) Parts 12 and 13.
Potential vendors are notified that the basis on which award will be made is price alone.
All responsible sources may submit a quote which, if timely received, must be considered by the Agency.
The Government may request that a vendor respond to a Quote Verification after the solicitation closes, but prior to award. The vendor shall respond in sufficient detail to all questions or statements no later than the response date and time listed in the correspondence. Failure to do so may result in quotes being deemed non-responsive and removed from consideration. The Government is under no obligation to provide extensions for responses.
Previous contract was awarded to: N/A
Previous contract awarded amount: N/A
Interested vendors are advised that scope may differ from previous contract.
No additional information on previous contracts will be provided.
QUESTIONS REGARDING SOLICITATIONS:
Questions regarding the solicitation shall be directed to the Contract Specialist:
Name: Alicia LaCrosse
Phone: 978-318-8902
Email: Alicia.N.LaCrosse@usace.army.mil
Technical Points of Contact shall not provide responses to interested vendors.
QUOTE SUBMISSION:
Quotes shall be submitted via email to the Contract Specialist listed above no later than the closing date and time identified in the solicitation or subsequent amendments.
The Government is under no obligation to consider any quote received after the solicitation closing date or time.
BID SCHEDULES:
If a Bid Schedule is included in the solicitation, vendors shall complete the bid schedule in its entirety (all tasks, all years).
Vendors shall enter $0.00 on Bid Schedules in which items are Not Separately Priced. Blank entries will not be considered and will result in quotes being deemed non-responsive.
Failure to complete the Bid Schedule in its entirety and return same with a quote will result in quotes being deemed non-responsive.
SITE VISITS:
If dates/times for site visits are included in the solicitation, then interested vendors will be permitted to visit the site during those dates/times. No other dates/times will be permitted for site visits.
If no dates/times for site visits are included in the solicitation, then interested vendors shall contact the Technical Point of Contact as identified in the solicitation to schedule a site visit.
No site visits will be permitted AFTER a solicitation closes.
SYSTEM FOR AWARD MANAGEMENT (SAM) REGISTRATIONS:
In accordance with FAR Clause 52.204-7:
Vendors are REQUIRED to be registered in SAM when submitting a quotation and shall continue to be registered until time of award, during performance, and through final payment.
"Registered" in SAM means that the Government has marked the record "Active".
The Government will deem quotes non-responsive from vendors that do not have an active SAM at the time of quote submission or by date/time of solicitation closing.
Provide Unique Entity Identifier (UEI): ___________________________
Provide CAGE code: ____________________________
SUBMITTALS:
Submittals (Accident Prevention Plan, Activity Hazard Analyses, Products, etc.) and Certifications /Licenses (10-hour OSHA, 30-hour OSHA, Competent Person in Fall Protection, Electrician's License, etc.) that are specified in the scope as required by this solicitation are not to be submitted with a quote.
The awarded Contractor will be required to provide all submittals and certifications within the time stated in the solicitation and resultant contract. Failure to do so may result in termination.
SECURITY REQUIREMENTS:
General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (eg., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed;
the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures -this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clauses of this contract, should FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something):
All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
PERFORMANCE WORK STATEMENT :(REVISED)
Preliminary Title Commitments
Plymouth Long Beach Dike, Federal Navigation Project (Dike Repair)
I. General:
1. SCOPE OF WORK: Provide all supervision, labor, materials, equipment, certifications, licenses, permits, and transportation to obtain, generate, and provide preliminary title commitments for seven (7) parcels of land in the Town of Plymouth, County of Plymouth, Commonwealth of Massachusetts.
Preliminary title commitments shall be executed in compliance with practice standards for the Commonwealth of Massachusetts and the duration of the period of search for the title commitments shall be a minimum of sixty (60) years in accordance with the Regulations of the Attorney General Governing the Review and Approval of Title for Federal Land Acquisitions (2016). Preliminary title commitments based on and/or written off of previously issued policies or so called "back policies" shall not be sufficient. Additionally, the Government may choose to exercise options for an update (Continuation) to the preliminary title commitments on any or all of the seven (7) parcels of land, options for closing and escrow services, including review and comment on the associated deed and any curative materials, and any other tasks necessary to close the transaction and ensure that good and marketable title to the real estate interests vest in the United States of America for any or all of all the parcels of land, as well as options for final American Land Title Association (ALTA) U.S. Policy - 9/28/91 (revised 12/03/12) on any or all of the parcels of land.
2. LOCATION: The following properties are located in the Town of Plymouth, County of Plymouth, Commonwealth of Massachusetts and use a parcel ID (Map, Block, Lot, Unit) from the Town of Plymouth Assessors' Office:
PARCEL ID: 037A-000-000Q-000
PARCEL ID: 037A-000-000O-003, also known as 370 Ryder Way
PARCEL ID: 037A-000-000O-004, also known as 322 Ryder Way
PARCEL ID: 037A000-000O-006, also known as 318 Ryder Way
PARCEL ID: 037A-000-000S-000, also known as 228 Ryder Way
PARCEL ID: 037A-000-004-000, also known as 152 Ryder Way
PARCEL ID: 037A-000-003-000, also known as Ryder Way
3. SCHEDULE: The preliminary title commitments will be due 30 days from contract award and the overall period of performance for the task order shall be 1 year from the Contract Award to allow for government review, corrections and revisions as necessary. The Pre-Work Conference shall be completed within 7 days of Contract Award.
4. PRE-WORK CONFERENCE: Prior to the start of any work, the Technical Point of Contact (TPOC) will schedule and conduct a "Pre-Work Conference" by phone. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the TPOC to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's administration and inspection of contract work or obtain other pertinent information that might be required. At the Pre-Work Conference the contractor shall provide the name of the Contractor Point of Contact with a telephone number and email for project coordination. The Pre-Work Conference will discuss the authority of the TPOC; correspondence, communication, security, and administrative procedures; and invoice and payment.
5. NOTIFICATION TO COMMENCE WORK/ORDERING: The Contracting Officer may exercise each task identified in the Table 1 by sending a formal modification identifying the tasks exercised by the Government. The corresponding performance period for each task identified in the table will apply. The contractor shall not commence work on any task prior to receipt of a formal modification signed by the Contracting Officer.
6. DELIVERABLES: Preliminary title commitments shall be provided within 30 days of contract award.
The Government reserves up to 30 days for review and acceptance on each deliverable from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall resubmit to the Government in an acceptable form within 7 days of the Government's response, unless additional time is granted by the Government in writing. The contractor shall ensure each deliverable identified in Table 1 is submitted to the TPOC not later than its identified period of performance.
Table 1
Deliverable Unit Quantity Period of Performance
Contract Line Item (CLIN): 0001 preliminary title commitments (including all source material) for:
Assessor Parcel ID: 037A-000-000Q-000, Plymouth, Massachusetts
Assessor Parcel ID: 037A-000-000O-003, 370 Ryder Way, Plymouth, Massachusetts
Assessor Parcel ID: 037A-000-000O-004, 322
Assessor Parcel ID: 037A000-000O-006, 318
Parcel
To be delivered within 30 days of contract award
Assessor Parcel ID: 037A-000-000S-000, 228
Assessor Parcel ID: 037A-000-004-000, 152
Assessor Parcel ID:037A-000-003-000, Ryder Way, Plymouth, Massachusetts
CLIN: 0002 OPTION
One of most recent continuation preliminary title commitment for:
Assessor Parcel ID: 037A-000-000Q-000, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0003 OPTION
Assessor Parcel ID: 037A-000-000O-003, 370 of option exercise.
CLIN: 0004 OPTION
Assessor Parcel ID: 037A-000-000O-004, 322
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0005 OPTION
One of most recent preliminary title continuation
Assessor Parcel ID: 037A000-000O-006, 318 Ryder of option exercise.
CLIN: 0006 OPTION
Assessor Parcel ID: 037A-000-000S-000, 228
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0007 OPTION
Assessor Parcel ID: 037A-000-0004-000, 152
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0008 OPTION
One of most recentcontinuation
Preliminary title commitment for:
Assessor Parcel ID: 037A-000-003-000, Ryder
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0009 OPTION
Real Estate for Temporary Work Area closing services Easement (TWAE) over Assessor Parcel ID: 037A- 000-000Q-000, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0010 OPTION
Real Estate for Temporary Work Area closing services Easement (TWAE) over Assessor Parcel ID: 037A- 000-000O-003, 370 Ryder Way, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0011 OPTION
Real Estate for Temporary Work Area closing services Easement (TWAE) over Assessor Parcel ID: 037A- 000-000O-004, 322 Ryder Way, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0012 OPTION
Real Estate for Temporary Work Area closing services Easement (TWAE) over Assessor Parcel ID:
037A000-000O-006, 318 Ryder Way, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0013 OPTION
Real Estate for Temporary Work Area closing services Easement (TWAE) over Assessor Parcel ID: 037A- 000-000S-000, 228 Ryder Way, Plymouth, Massachusetts of option exercise.
CLIN: 0014 OPTION
Real Estate for Temporary Work Area closing services Easement (TWAE) over Assessor Parcel ID: 037A- 000-004-000, 152 Ryder Way, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0015 OPTION
Real Estate for Temporary Work Area closing services Easement (TWAE) over Assessor Parcel ID:037A- 000-003-000, Ryder Way, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0016 OPTION
Final title and insurance policy for Assessor Parcel ID: 037A-000-000Q-000, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0017 OPTION
Final title and insurance policy for Assessor Parcel ID: 037A-000-000O-003, 370 Ryder Way, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0018 OPTION
Final title and insurance policy for Assessor Parcel ID: 037A-000-000O-004, 322 Ryder Way, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0019 OPTION
Final title and insurance policy for Assessor Parcel ID: 037A000-000O-006, 318 Ryder Way, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0020 OPTION
Final title and insurance policy for Assessor Parcel ID: 037A-000-000S-000, 228 Ryder Way, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0021 OPTION
Final title and insurance policy for Assessor Parcel ID: 037A-000-004-000, 152 Ryder Way, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
CLIN: 0022 OPTION
Final title and insurance policy for Assessor Parcel ID:037A-000-003-000, Ryder Way, Plymouth, Massachusetts
Parcel 1 To be delivered within fourteen (14) days of option exercise.
7. PAYMENT: The Contractor shall not submit an invoice until the Government has formally reviewed, accepted and approved delivery of the products and services under this contract. The invoice may be submitted by email to the TPOC, Patrick.E.Dolan@usace.army.mil, with copies to Maureen.A.
Mccabe@usace.army.mil and Helen.M.Mahdi@usace.army.mil. The invoice shall include the invoice date, contract number, description of work and total amount due per line item. The invoice must also include the company letterhead, and this must match the data that is registered in the System for Award Management (SAM) registry.
II. Technical Requirements
1. OWNERSHIP:
a. Land will be deemed contiguous even though portions thereof are separated by roads, railroad rights of way, streams, etc. If there has been a severance of the surface and the subsurface of the land, Unless otherwise determination of what constitutes a tract will be based on ownership of the surface.
specified in the Work Order, the title document ordered shall cover the entire ownership of the tract(s), and if certain estates are vested in others than the owner , or subsurface interests or owners of the surface the title document ordered shall cover all such outstanding estates . The title document or interests ordered shall furnish pertinent information such as parties, dates, and recordation data regarding mineral the deeds under which the present owner acquired title severance deeds and or owners of the minerals thereto.
b. Where there has been a severance in the surface and subsurface of the land, it is contemplated that there may be multiple acquisitions pertaining to the same tract of land. In the event that the contract has furnished a Title Policy covering acquisition of the surface owners' interest and the land, the Technical Point of Contact reserves the right to order additional title documents covering the acquisition of the outstanding minerals underlying the same tract. The Contractor shall be paid for such title documents at the appropriate unit prices set forth in the pricing schedule.
2. REMUNERATION:
a. Payment shall be made on a lump sum basis, based on the prices identified on the Pricing Schedule for each of the tasks. The contractor can submit an invoice after each deliverable has been reviewed and accepted by an authorized Government Representative, but not more frequently than once per calendar month.
b. The contractor shall review any and all curative actions submitted by the Government, discuss any proposed curative actions with US Army Corps of Engineers (USACE) legal staff, and will delete, remove and/or amend exceptions in compliance with law. The contractor will have open communications with USACE legal staff, including communications by phone, facsimile and electronic mail, with a view toward curing title deficiencies. If requested by USACE legal staff, contractor shall provide a marked-up preliminary title commitment reflecting, among other things, title defect(s), removal of exceptions, and valid title through the date of recording of the temporary work area easement(s). Any time or costs associated with such discussions will not be billed separately, but instead is factored in the contract price for the title evidence items specified herein.
c. The cost of title insurance shall be limited solely to the title insurance premium. Payment for title insurance shall be made after the ALTA U.S. Title Insurance Policy(s) has/have been issued showing title to be vested in the United States of America for the easement interest acquired. The contractor shall assume and pay all charges of the company issuing the policy(s) to be furnished under this contract. If court judgments result in the need for endorsements to the Title Policy to increase the limits of liability, the Government shall issue a Request for Proposal for additional title insurance. Payment in such cases will be limited to the fee for the endorsement and the units of title insurance in excess of the units covered by the previously issued Title Policy or endorsement.
3. The Contractor represents, and it is a condition of any obligation of the Government hereunder, that the company which is to issue Title Insurance Policies under this contract, is authorized and qualified in the Commonwealth of Massachusetts to issue ALTA U.S. Title Insurance policies. If the contractor is an attorney, the pricing schedule must be accompanied by the written commitment of a company so qualified, to issue Title Insurance Policies and Commitments ordered hereunder, and a statement by said company that the contractor/attorney is its agent and can issue policies in its name.
4. At a minimum, the Preliminary title commitment document must extend for a period of no less than 6 months.
5. EXECUTION:
a. The Preliminary Title Commitments (hereinafter "Preliminary Commitment") to be furnished shall be based on a thorough search and examination of the public records affecting the title to the land. The Contractor shall correct or revise the source or derivation of title of the present owner or owners, contained in such description, if necessary, or otherwise furnish an appropriate derivation of title as required by law or local practice. The Preliminary Commitment shall be unqualified for the period of search (the specified duration of the period of search is defined infra), shall contain the legal description of the property as furnished by the government, and shall be immediately followed by a reference to the source of title of the present owner. The Preliminary Title Commitment and Final Title Policy shall be issued only on the most recent forms approved by the Attorney General of the United States and the ALTA for acquisitions by the United States (the following information, though correct at the time this specification was written, is provided for the contractor's information only, and is not guaranteed: ALTA U.S. Policy - 9/28/91 form, revised 12/03/12 is the ONLY currently approved policy form). Delivery of Preliminary Commitment and Final Title Policy on forms other than those so approved will be considered a nonconforming delivery.
b. The duration of the period of search for the title examination shall be sixty (60) years in accordance with the Regulations of the Attorney General Governing the Review and Approval of Title for Federal Land Acquisitions (2016) and in compliance with practice standards for the Commonwealth of Massachusetts, whichever is longer. A Preliminary Commitment, Continuation, or Final Title Policy based on and/or written off of previously issued policies or so called "back policies" shall not be sufficient.
c. In addition, Title Policies for tracts acquired by condemnation proceedings shall include information regarding the United States' immediate predecessor in the title, in language similar to the following:
"Title to the estate or interest covered by this Title Policy at the date hereof is vested in the United States of America by virtue of a Declaration of Taking, as evidenced by Lis Pendens Notice or [or Judgment on Declaration of Taking], dated _______________, recorded in _____________ Book _________, page _________ of the records of ____________, _________ . Prior to the Declaration of Taking, title was vested in ____________ ."
6. The Preliminary Commitment will disclose the name or names of the record owner or owners of the property described therein. It will disclose the full name of every person and entity in whom title to any interest to be acquired by the United States is vested, as shown by the public records or otherwise known to the title provider. Where subsurface estates or interests in the property to be acquired are owned by persons, corporations, or other legal entities, other than the owners of the surface estate, the present record owners of each such outstanding estate or interest and all pertinent data relating thereto shall be shown in the Title Policy unless otherwise specified in the order.
7. The Preliminary Commitment must identify all documents affecting any interest to be acquired by the United States (e.g., liens, easements, rights-of-way, affirmative and restrictive covenants, and competing records of ownership) revealed by the records search. Exceptions from coverage under the Final Title Policy for these interests must specifically identify each holder.
8. The Preliminary Commitment shall be executed and shall contain in Schedule B thereof the names and addresses, as disclosed by the public records, of all persons or entities having any liens on or rights or interests in the property described therein, in order that they may be joined as parties defendant in a condemnation proceeding if one is necessary. Schedule B exclusions shall include legible copies of the source material in PDF format with functioning hyperlinks to the source documents and said high quality PDFs attached as an addendum to the Final Title Policy. Source documents also include recorded plans, either recorded independently or referenced in a recorded instrument, such a deed, easements, mortgages etc.
9. The Preliminary Commitment shall contain sufficient information concerning defects, liens, encumbrances, and other matters excepted, to enable an attorney examining the policy to determine the nature and extent of such exceptions and their probable effect on the validity of the title to the land described. It shall also state or be accompanied by a report specifying the evidence or action, if any, which will be acceptable to the corporation issuing the Final Title Policy, as a basis for the issuance of a Continuation deleting each such defect, lien, encumbrance, and other matter from the Final Title Policy.
10. Each Preliminary Commitment shall contain a detailed statement of any taxes and special assessments of record which are a lien on the property described. Such statement will include, at a minimum, the current assessment information, including name of taxpayer, district (if applicable) assessment, and dollar amount. The statement will also either clearly itemize all delinquent taxes or affirmatively state that there are no delinquent taxes.
11. If the Preliminary Commitment contains any objection with respect to liens for taxes, assessments, or bonds of a special improvement district, such objections will be followed by references to the statutes pursuant to which such special improvement district was organized, its taxes and assessments levied and its bonds issued and any other facts necessary to enable an examining attorney to determine the nature and extent of the lien, if any, created by such taxes, assessments, or bonds, on the land described therein.
12. If the Preliminary Commitment shows title in a record owner who is deceased, it shall also state therein, or be accompanied by a statement indicating whether a judicial proceeding, affidavits of heirship, or some other form of proof will be acceptable to the title company as the basis for the issuance of a Final Title Policy showing title in the United States upon execution and recordation of a deed to the United States from such persons shown by such proof to be all heirs of the deceased.
13. If the Preliminary Commitment shows record title in a state, county municipality, or other subdivision of the state, or in a corporation, or a church or other religious, educational, or charitable institution or organization, or in a person or persons acting in a fiduciary or similar capacity, without authority to convey the property in the absence of specific authorization, the Preliminary Commitment shall disclose the incapacity of or limitation on the authority to convey the property and shall specify what action, if any, is necessary before a valid conveyance of the property may be made to the United States and what proof thereof will be required by the title company before issuing a Final Title Policy showing valid title to the property in the United States.
14. A Preliminary Commitment containing any exception or objection with respect to rights or possible rights under the provisions of Section 13 of the Selective Training and Service Act of 1940 (50 USC App. 313), or the Soldiers and Sailors Civil Relief Act of 1940, as amended (50 USC App. 501-509) must:
a. Contain the name of each person having such rights, and the address of any such person, if known.
b. Contain or be accompanied by a statement of the company issuing the policy showing the nature and extent of the interest in the land of each such person, and
c. If any such person has an actual interest in the land, contain or be accompanied by a transcript of the proceeding giving rise to such rights and disclose the action, if any, taken in the proceeding to comply with the requirements of said Acts.
15. Each Preliminary Commitment shall be executed by a duly authorized officer of the issuing corporation, shall bear the corporate seal of such corporation, and shall be countersigned by the proper officer of the corporation, where necessary. The Final Title Policies, as amended by the final Continuation to the commitment, shall not except from the corporation's liability, any defects, liens, encumbrances, or other matters of record set forth in the original commitment which are waived by the corporation or its duly authorized representative before closing of the acquisition, nor shall amended commitment contain any exception with respect to any matter affecting the title as of the date of the original commitment, or its Continuation, which was not disclosed in the original commitment, or its Continuation.
16. The Contractor also agrees, if requested by the Government technical representative, to review the proposed temporary work area easement (TWAE) of the property to the United States and advise as to the sufficiency of the TWAE to vest valid title to the property described in Schedule "A" of the
Preliminary Commitment, Interim Binder, or Final Title Policy. For these purposes the Contractor shall designate a local representative authorized by it to pass upon the form and sufficiency of the curative material, to waive objections, in the Preliminary Commitment, Interim Binder, or Final Title Policy and approve the proposed easement deed to the United States. The Contractor shall, if so requested, have its representative present at the closing of the purchase transaction to determine the current status of the affected titles.
17. The Contractor agrees to report changes in ownership and/or to eliminate or cause to be eliminated from the Final Title Policy by intermediate Continuations to the Preliminary Commitments, objections disclosed in the Final Title Policies issued hereunder when ownership changes occur and when curative material obtained by representatives of the United States or others is acceptable to the title company issuing the Final Title Policies hereunder.
18. "Continuation" is defined as a printed or typed amendment to the Preliminary Commitment previously issued by the title company, which extends the effective date of the original policy, and executed in the same manner as the original policy, and may be either an intermediate or final Continuation. The intermediate Continuation shall reflect the condition of title subsequent to the date of the original Preliminary Title Commitment and prior to the date of closing of the acquisition; the final Continuation shall reflect the vesting of title in the United States. The Continuations shall be issued only upon written order of the Contracting Officer or duly authorized representative. Endorsements which merely delete exceptions from the original policy due to presentation to the title company or the contractor of satisfactory curative matter and which do not require any search of courthouse records are not Continuations within the meaning of this contract.
19. If the corporation which is to issue Final Title Policy hereunder customarily insures marketability of title in the locality where the land is situated, the Policies to be issued hereunder shall not contain the paragraph headed "Refusal to Purchase" under "General Exceptions" of the aforesaid approved Title Policy, but shall insure the marketability of the title.
20. Liability of the company under the Final Title Policy, issued pursuant to the specifications, shall not be less than the monetary consideration paid for the real property; or if the acquisition is by gift or donation the estimated value of the real property; or in the case of acquisition by condemnation, shall not be less than the sum deposited in the registry of the Court as the estimated just compensation for the taking.
PART III - DELIVERIES/PERFORMANCE
1. Preliminary title evidence document--a Preliminary Commitment, which commits the title company to issue a final ALTA U.S. Policy - 9/28/91 (revised 12/03/12). Title evidence must be in accordance with the Regulations of the Attorney General Governing the Review and Approval of Title for Federal Land Acquisitions (2016) or as further updated, and must conform to the Performance Work Statement. As part of the title evidence, the contractor will determine the sufficiency of tax takings and foreclosures under Massachusetts State law. The contractor must submit preliminary title commitment within 30 calendar days of contract award. The Government shall have 30 calendar days to review the submittal to ensure it complies with the request. If it does not, the Government shall provide comments on the deficiencies to the Contractor and the Contractor will resubmit the preliminary title evidence without deficiencies within 7 calendar days of the Government's comments.
2. (OPTION) Continuation of most recent Preliminary Commitment for title insurance. The price quoted should include all time and costs involving discussions on issues relating to title and closing (such as preliminary title evidence and items needed to clear encumbrances). The price quoted should include the title company's advice and review of drafts of easement deeds and title curative material. Title evidence must conform to the Performance Work Statement. The contractor must submit Continuation within 14 calendar days of the exercise of option tasks. The Government shall have 7 calendar days to review the submittal to ensure it complies with the request. If it does not, the Government shall provide comments on the deficiencies to the Contractor and the Contractor will resubmit the Continuation without deficiencies within 5 calendar days of the Government's comments.
3. (OPTION) Closing Services for an acquisition in Plymouth, Massachusetts. Real estate Closing Services include obtaining municipal lien certificates; obtaining and notarizing the signature of landowners on documents associated with the closing, delivering a Government check; running down title before documents are recorded to ensure no change in title status; and recording documents in the appropriate County Registry of Deeds. The price quoted should include all costs not specified in item III.
5 below. If the title run down shows a change in title status, the Contractor must immediately notify the Government and wait for further direction before recording the temporary work area easement(s). The Government will require the closing agent to obtain the landowner's signature on the government form "Payment and Closing Sheet". The closing services must be provided in a timely manner so that closing will occur on the date scheduled. The Government will notify the Contractor at least 14 calendar days prior to the desired closing date and the Contractor must coordinate with the landowner and use best efforts to meet the desired closing date.
4. (OPTION) Final title policy with title insurance. The Contractor must provide a final policy with title insurance within 14 calendar days after a conveyance to the United States has been recorded. The policy must reflect the condition of title through the date of closing of the Government acquisition and show that the acquisition appears on the title. Title evidence must conform to the Performance Work Statement. The cost of the insurance coverage shall be the most favorable rate offered by the Contractor.
5. If the Government elects to exercise the option task(s) for closing services, the Government will issue a Request for Proposal for costs associated with closing the transaction, namely, (A) fees charged Plymouth County Registry of Deeds and/or the Plymouth County Registry District of the Land Court to record the temporary work area easement(s); and (B) any applicable property conveyance tax (while the grantee United States of America is exempt, the contractor must pay the grantor's portion of the tax). The Contractor shall submit these costs in the form of a response to the Request for Proposal. If acceptable, the Government will issue a modification to the Contract.
6. Affirmative title coverage. While not likely, it is possible the Government may require affirmative coverage insurance over exceptions. If coverage is required, the Government will issue a Request for Proposal and the Government and Contractor will negotiate a fair and reasonable rate.
WAGE DETERMINATIONS:
WAGE DETERMINATION WILL BE INCLUDED AT CONTRACT AWARD AND WILL BE
BASED ON THE AWARDED CONTRACTOR'S PLACE OF OPERATION TO INCLUDE STATE
AND COUNTY.
| IDCode: J |
| Page: 1 |
| Pages: 17 |
| AmendNo: 0002 |
| EffDate: 27 AUG 2025 |
| ReqNo: |
| ProjNo: |
| IssCode: W912WJ |
| AdmCode: |
| IssuedBy: W2SD ENDIST NEW ENGLAND |
KO CONTRACTING DIVISION, 696 VIRGINIA ROAD
CONCORD, MA 01742-2751
UNITED STATES
ALICIA LACROSSE, EMAIL: ALICIA.N.LACROSSE@USACE.ARMY.MIL TELEPHONE: 978-318-8902
AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W912WJ25QA082 |
| SolDate: 07 AUG 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: 1 |
| OffrNoEx: Off |
| NoCopies: 1 |
| ApprData: SEE CONTINUATION |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: AMENDMENT IS NECESSARY TO PROVIDE RESPONSES TO QUESTIONS FROM INDUSTRY AND PROVIDE A REVISED PERFORMANCE WORK STATEMENT. |
SOLICITATION CLOSING IS EXTENDED UNTIL SEPTEMBER 2, 2025 AT 2:00 PM EASTERN.
ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
| ContNameTitle: |
| CoNameTitle: JENNIFER SAMELA |
| ContDate: |
| CODate: 28 AUG 2025 |
File details come from the government source that posted it. Updated .