This is Amendment 0001 to solicitation W912WJ25Q0034, issued by the U.S. Army Corps of Engineers New England District, which extends the solicitation closing date and provides responses to industry questions about the Winhall Brook Stream Bank Stabilization project.
The amendment clarifies several technical aspects: no guardrail installation is required; no surveying is needed as the Government will mark work boundaries; the 210-foot stream bank is to be stabilized in its original location (6-10 feet wide from original bank); the Government will determine the highwater mark; USACE has already obtained Vermont Agency of Natural Resources permits; Cohen Road will be repaired before work begins; and contractors should follow dimensions/slopes in the Statement of Work rather than the Vermont River Manual. The solicitation response deadline is extended from February 20, 2025 to February 21, 2025 at 5:00 PM Eastern.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachments.pdf | ||
| Solicitation W912WJ25Q0034.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment is necessary to provide responses to questions from industry.
Solicitation closing has been extended until February 21, 2025 at 5:00 PM Eastern.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-Feb-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ25Q0034
X 9B. DATED (SEE ITEM 11)
06-Feb-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Feb-2025
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
Sheila.M.Winston@usace.army.milEMAIL:978-318-8159TEL:
SHEILA M WINSTONVINCUILLA / CHIEF, CONTRACTING DIVISION
W912WJ25Q0034
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
REQUEST FOR INFORMATION
QUESTION 1: In the informational photo 2 and photo 4, which are included in the project documents, there is a guardrail detailed at the top of the stream bank. However, I did not find any mention of guardrail installation in the statement of work. Is the installation of a guardrail, as pictured in the informational photos, above the scope of work to be quoted?
RESPONSE 1: No, installation of a guardrail is not included in this work. The informational photos (#2) are from the Vermont Rivers and Roads Field Manual. It is the guide that must be followed per the Government’s permit with the Vermont Agency of Natural Resources and serves as an example.
Please refer to Part 4. Execution, of the Statement of Work.
QUESTION 2: The Statement of Work does not mention surveying or layout for the project. What is the expectation for layout of the proposed stabilized stream bank, including project start and project end location, stream bank width, and high-water elevation?
RESPONSE 2: There is no requirement for surveying. The beginning and end of the work area will be marked by the Government prior to the start of work. Per the Statement of Work and existing conditions subsection, there is 210 feet of stream bank required to be stabilized.
QUESTION 3: Is slope to be stabilized in current location or drawn back into channel (original) width?
RESPONSE 3: As specified in Section II.4. Existing Conditions of the Statement of Work, ‘the area of bank erosion varies from six (6) to ten (10) feet in width from the original bank and river channel location.’ The intent is for the slope to be stabilized in its original location.
QUESTION 4: Who is responsible for determining the "highwater mark"?
RESPONSE 4: The Government will determine the highwater mark based on the definition from 33 CFR 329.11(a)(1), “The term ordinary high water mark on non-tidal rivers is the line on the shore established by the fluctuations of water and indicated by physical characteristics such as clear, natural line impressed on the bank; shelving; changes in the character of soil; destruction of terrestrial vegetation; the presence of litter and debris; or other appropriate means that consider the characteristics of the surrounding areas”.
QUESTION 5: Is USACE (U.S. Army Corps of Engineers) the permitting agency, or will the Contractor have to permit the project through the state of Vermont?
RESPONSE 5: USACE has already permitted this work through the Vermont Agency of Natural Resources.
QUESTION 6: Will any repairs be made to Cohen Rd prior to the start of the project?
W912WJ25Q0034
RESPONSE 6: Cohen Road will be repaired and accessible prior to the stream bank work.
QUESTION 7: The dimension of the toe wall and rip-rap slope listed in the ‘’execution’’ on the solicitation contradicts the Vermont River manual's dimensions. Do the dimensions listed in the solicitation override the Vermont River Manual?
RESPONSE 7: The Vermont River and Roads manual (2016) and Vermont Standard River Management Principles and Practices (2015) provides multiple dimension and slope solutions depending on the site features and hydraulic features present. The Contractor should adhere to the dimensions and slopes listed in the Execution section of the Statement of Work.
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 20-Feb-2025 05:00 PM to 21-Feb-2025 05:00 PM.
(End of Summary of Changes)