This is Amendment 0003 to solicitation W912WJ25Q0032, issued by the U.S. Army Corps of Engineers New England District, providing responses to industry questions about dumpster services at Cape Cod Canal in Buzzards Bay, MA. The solicitation closing remains February 7, 2025 at 2:00 PM Eastern.

Key details from the Q&A include: The previous contract was awarded to Cavossa Disposal Corp for $79,520. The contractor must provide 30-yard dumpsters (28-yard not acceptable) for both metal and construction debris - with metal debris going only in the designated metal dumpster while the construction dumpster will accept mixed construction/demolition debris. The government will remove existing dumpsters before contractor placement. The contractor is responsible for disposal and recycling of all debris in accordance with regulations. Services will be provided on an on-call basis as requested by the Technical Point of Contact, with a maximum of 15 total removals in the first year. The contractor must handle all recycling and disposal in accordance with federal, state and local requirements.

View the file

Other files

File Type Posted
Amendment W912WJ25Q0032-0002.pdf PDF
Amendment W912WJ25Q0032-0002 Map.pdf PDF
Amendment W912WJ25Q0032-0001.pdf PDF
Solicitation W912WJ25Q0032.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment is necessary to provide responses to questions from industry. Question #8 is applicable to this amendment.

Solicitation closing remains February 7, 2025 at 2:00 PM Eastern.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 03-Feb-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ25Q0032

X 9B. DATED (SEE ITEM 11)

15-Jan-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

03-Feb-2025

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ25Q0032

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been modified:

REQUEST FOR INFORMATION

QUESTION 1: Can you please provide the incumbents info, if there is one along with the previously awarded contract number and the total awarded amount?

RESPONSE 1: The Government is permitted to provide only the previous contract awardee and total awarded contract amount. The previous awardee for these services was Cavossa Disposal Corp for a total contract amount of $79,520. Interested vendors should note that service requirements may differ from previous awards.

QUESTION 2: Are there dumpsters on site that will need to be replaced?

RESPONSE 2: The Contractor is not responsible for removing any existing dumpsters on site.

The Government will remove all dumpsters from site prior to the Contractor providing the required dumpster as stated in Section II.3 & Section II.4 of the Performance Work Statement.

QUESTION 3: Who will be keeping the metal debris? Will the USACE be keeping it and recycling or will the contractor be keeping it?

RESPONSE 3: The Contractor is responsible for disposal and recycling of all metal and construction debris in accordance with all Federal, State, and local laws and regulations, as stated in Section II.3 & Section II.4 of the Performance Work Statement.

QUESTION 4: I want to confirm that no actual dumpsters are needed, they are already in place?

This is just for the haul off services?

RESPONSE 4: The Contractor shall provide dumpster containers as stated in Section II.3 & Section II.4 of the Performance Work Statement. Please see the attachment with a map of the dumpster placement locations.

QUESTION 5: Confirming that this contract dictates a combined total of 15 removals for the first year? Will additional removals be a possibility and if so will the TPOC notify us of that?

RESPONSE 5: The quantity of services to remove and dipose of debris will not exceed the maximum totals stated in the Bid Schedule and the Performance Work Statement.

QUESTION 6: Each time there is a removal request will both dumpsters need to be cleaned out of debris or will the TPOC notify us at that time which one will be required to be emptied?

W912WJ25Q0032

RESPONSE 6: A request from the Technical Point of Contact will be submitted to the Contractor to empty each dumpster on an on call, as needed basis.

QUESTION 7: Is a 28-yard dumpster okay to provide instead of a 30-yard dumpster?

RESPONSE 7: No, the Contractor must provide a 30-yard dumpster as stated in the Performance Work Statement.

QUESTION 8: For the metal debris dumpster, will there only be metal in that container or will it be mixed debris?

RESPONSE 8: The metal dumpster will be for metal debris only. The construction dumpster is for general construction and demolition debris which is mixed and may contain some metal debris.

(End of Summary of Changes)