This is an Abstract of Offers - Construction document for the Old Route 8 Bridge Painting project, solicitation number W912WJ25BA026, issued by the US Army Engineer District, New England. The solicitation is a Small Business Set-Aside with a government estimate of $815,000, and it involves painting and structural work for a bridge, including base bid items for bottom chords, bearings, and gusset plates, as well as optional items for fascia stringers, end posts, and top chords. Seven companies submitted bids, with total base and option bid amounts ranging from $310,350.84 to $815,000, and each offeror providing a 20% bid security. The bid opening date was 9/19/2025, and the document details unit prices and estimated amounts for each line item across multiple contractors, including Titan Construction Management, LLC, The Aulson Company, Inc., Thomas Joseph Solutions, Inc., and others.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES

8/18/2025 9/19/2025 1 3

4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)

SIGNATURE DATE SIGNED

5. PROJECT TITLE (IFB) 8. GOVERNMENT ESTIMATE

(Check A, B, C and complete D, E, and F) A. OFFEROR A. OFFEROR

A. HIRED LABOR

B. REASONABLE CONTRACT B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)

Small Business Set-Aside (Without Profit)

6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED

(Including Profit)

7A. ITEM

NUMBER 7B. DESCRIPTION OF OFFERED ITEM

7C. EST.

QUANTITY

D.

UNIT E. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE

E. ESTIMATED

AMOUNT D. UNIT PRICE

E. ESTIMATED

AMOUNT D. UNIT PRICE

E. ESTIMATED

AMOUNT

0001 Bottom Chords, Below Deck 1 Job Job $64,307.00 Job $215,000.00 Job $198,000.00 Job $153,836.67 0002 Bearings, Below Deck 1 Job Job 0003 Gusset Plate, Below Deck 1 Job Job $123,918.00 Job $125,000.00 Job $150,000.00 Job $96,646.67

Total Amount for Base Bid Items $193,124.00 $375,000.00

Job

$376,000.00

Job

$335,160.01 Option Items

0004 Fascia Stringers, Below Deck 1 Job Job $120,048.00 Job $115,000.00 Job $98,000.00 Job $97,755.00 0005 End Posts, Above Deck 1 Job Job $33,570.00 Job $100,000.00 Job $112,000.00 Job $63,175.00 0006 Top Chords, Above Deck 1 Job Job

Total Amount for Option Bid Items

$4,899.00 Job $35,000.00

Job $189,000.00 Job $95,095.00$52,189.00 Job $225,000.00

$28,000.00

$399,000.00

$84,676.67

$256,025.00$205,807.00 $440,000.00

$398,931.00 $815,000.00 $775,000.00 $591,185.01TOTAL AMOUNT FOR BASE AND OPTION ITEMS:

9. OFFERS

A. OFFEROR

Thomas Joseph Solutions, Inc.

1 2 3

4 4 4 4

X 20% 20% 20%

W912WJ25BA026

US ARMY ENGINEER DISTRICT, NEW ENGLAND

696 VIRGINIA ROAD

CONCORD, MA 01742

Erin E. Bradley Bid Opening Officer

Old Route 8 Bridge Painting Titan Construction Management, LLC. The Aulson Company, Inc.

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

1. SOLICITATION NUMBER

2. PROJECT TITLE (IFB)

A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR

B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)

Small Business Set-Aside C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED

A. ITEM NO.

B. ESTIMATED

QUANTITY C. UNIT E. ESTIMATED AMOUNTD. UNIT PRICE E. ESTIMATED AMOUNTD. UNIT PRICE E. ESTIMATED AMOUNTD. UNIT PRICE E. ESTIMATED AMOUNTD. UNIT PRICE

0001 1 Job Job No Bid Schedule Job $125,000.00 Job $300,000.00 Job $130,206.54 0002 1 Job Job No Bid Schedule Job $69,700.00 Job $20,000.00 Job $19,127.00 0003 1 Job Job No Bid Schedule Job $115,000.00 Job $100,000.00 Job $11,970.00

Total Amount of Base Bid Items No Bid Schedule $309,700.00 $420,000.00 $161,303.54 Option Items

0004 1 Job Job No Bid Schedule Job $157,000.00 Job $50,000.00 Job $12,625.00 0005 1 Job Job No Bid Schedule Job $54,000.00 Job $60,000.00 Job $36,873.60 0006 1 Job Job No Bid Schedule Job $54,000.00 Job $120,000.00 Job $99,548.70

Total Amount of Option Bid Items No Bid Schedule $265,000.00 $230,000.00 $149,047.30

$380,000.00 $574,700.00 $650,000.00 $310,350.84

4. OFFERS (Continued)

ABSTRACT OF OFFERS - CONSTRUCTION

CONTINUATION SHEET

W912WJ25BA026 Page 2 of 3

No Bid Bond 20%

3. CONTRACT ITEMS 4

Old Route 8 Bridge Painting Modern Protective Coatings, Inc.

20%

0 4

Envirologics, Inc.

20%

INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project.

Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.

4 5 6 7

Francisco Multitrade Construction, LLC. Royal Bridge, Inc.

TOTAL AMOUNT FOR BASE AND OPTION ITEMS:

1. SOLICITATION NUMBER

2. PROJECT TITLE (IFB)

A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR

B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)

Unrestricted C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED

A. ITEM NO.

B. ESTIMATED

QUANTITY C. UNIT E. ESTIMATED AMOUNTD. UNIT PRICE E. ESTIMATED AMOUNTD. UNIT PRICE E. ESTIMATED AMOUNTD. UNIT PRICE E. ESTIMATED AMOUNTD. UNIT PRICE

0001 1 Job Job $150,000.00 Job $155,805.00 Job $131,606.00 Job $137,100.00 0002 1 Job Job $50,000.00 Job $9,647.00 Job $18,800.00 Job $45,200.00 0003 1 Job Job $85,000.00 Job $38,589.00 Job $37,600.00 Job $121,320.00

Total Amount of Base Bid Items $285,000.00 $204,041.00 $188,006.00 $303,620.00 Option Items

0004 1 Job Job $25,000.00 Job $112,392.00 Job $59,110.00 Job $74,200.00 0005 1 Job Job $25,000.00 Job $28,942.00 Job $33,400.00 Job $33,500.00 0006 1 Job Job $50,000.00 Job $112,392.00 Job $50,120.00 Job $48,320.00

Total Amount of Option Bid Items $100,000.00 $253,726.00 $142,630.00 $156,020.00

$385,000.00 $457,767.00 $330,636.00 $459,640.00TOTAL AMOUNT FOR BASE AND OPTION ITEMS:

20% 20%

3. CONTRACT ITEMS 4 4

20% 20%

4 4

4. OFFERS (Continued) 8 9 10 11

Old Route 8 Bridge Painting

Amari Painting & Lining, LLC. TBG EE JV II, LLC. Ozark TIC JV, LLC. Scholar Painting, LLC.

ABSTRACT OF OFFERS - CONSTRUCTION

CONTINUATION SHEET

Page 3 of 3W912WJ25BA026

INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project.

Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.

Abstract Page 1
Abstract Continuations
Pages.pdf
Abstract Continuations
2025-09-22T11:32:17-0400
BRADLEY.ERIN.ELIZABETH.1386908440

File details come from the government source that posted it. Updated .