Standby Generator Replacement, Colebrook River Lake, Colebrook, CT
Solicitation number
W912WJ24Q0173
Issued by

About this file

This document is a Solicitation for a federal contract opportunity to replace the automatic standby generator at the Colebrook River Lake Project Office in Colebrook, Connecticut. The work includes removing and disposing of the existing 25 kW generator, furnishing and installing a new 20 kW/20 kVA automatic standby generator with an all-weather enclosure and a 250-gallon liquid propane fuel tank. The Government may also exercise an option to replace the existing automatic transfer switch if it is incompatible with the new generator. The magnitude of the construction is between $25,000 and $100,000, and the procurement is set-aside for small business vendors under NAICS code 238210. Responses are due by September 5, 2024, and award will be based on price alone. Vendors must have an active SAM.gov registration to be considered.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COLEBROOK RIVER PROJ OFC

JOHN HALUCHAK

426A COLEBROOK RIVER ROAD

RIVERTON CT 06021

TEL: 978-318-8439 FAX:

W13G86418395160001

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W912WJ24Q0173 21-Aug-2024 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

05-Sep-2024(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

978-318-8324JENNIFER M SAMELA

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

W912WJ24Q0173

Section B - Supplies or Services and Prices

INSTRUCTIONS TO VENDORS

*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE 52.236-27

FOR ADDITIONAL INFORMATION.

*PLEASE DIRECT QUESTIONS TO JENNIFER M. SAMELA AT (978) 318-8324 or

JENNIFER.M.SAMELA@USACE.ARMY.MIL. ANY INFORMATION RECEIVED AT THE SITE VISIT

WHICH CONFLICTS WITH THIS SOLICITATION SHOULD BE BROUGHT TO THE ATTENTION OF

JENNIFER M. SAMELA. THE SOLICITATION AND RESULTING CONTRACT SHALL BE THE

GOVERNING DOCUMENT IN ALL CASES.

**QUOTES CAN BE E-MAILED TO JENNIFER M. SAMELA AT

JENNIFER.M.SAMELA@USACE.ARMY.MIL.

NOTE 1: In accordance with FAR Part 28.102-2(b), the Contractor will be required to provide the following payment protections for all construction contracts at or above$150,000.00.

(i) Payment Bond or

(ii) Irrevocable Letter of Credit and

(iii) Performance Bond

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

A Performance Bond shall be required if the total price of the quote is $150,000.00 or above. The penal amount of the Performance Bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall also be submitted to the Contracting Officer within 10 days after receipt of award.

NOTE 2: In accordance with FAR Part 28.102-2(c), the Contractor will be required to provide one of the following payment protections for all construction contracts $35,000.00 or above, but not exceeding $150,000.00.

(i) Payment bond or

(ii) Irrevocable letter of credit

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

**No Payment Protections Required for construction contracts less than $35,000**

NOTE 3:

QUOTATION INSTRUCTIONS:

1. If subcontractor will be used for this work, please provide company names:

2. In accordance with FAR Part 52.204-7(b)(1) Contractors must be registered in the System for Award Management (SAM) database (www.SAM.gov) to submit a quote (formerly the Central Contractor Registration

(CCR) database and the On-Line Representations and Certifications (ORCA)). Any reference to CCR or ORCA in any clause or provision is referring to the www.sam.gov website.

NOTE: SAM.gov registration takes approximately 3 weeks (DUNS registration 1-2 business days; CAGE code validation up to 10 business days; IRS validation and overall submission 7-10 business days). It is the contractor’s responsibility to track SAM.gov registration and follow-up with required tasks.

In addition, if you are registering a new entity in SAM.gov, you must provide an original, signed notarized letter stating that you are the authorized Entity Administrator. The Entity Administrator must establish a LOGIN.GOV account using the e-mail address that will be associated with the SAM registration. See https://www.gsa.gov/about-us/organization/federal-acquisition-service/office-of-systems-management/integrated-award-environment-iae/sam-update for additional information.

3. Provide business Unique Entity Identifier (UEI): _______________________________

4. Provide business CAGE code: __________________________________

5. Tax Identification Number: ___________________________________

6. Contractors shall provide completed FAR clause 52.204-8 (Annual Representations and Certifications) found in Section K of this solicitation with their quote if the Contractors have not completed their annual representations and certifications electronically via the SAM website at www.sam.gov. (See Paragraph 2 above).

7. Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful Contractor will be required to submit this document at the direction of the Technical Point of Contact. The APP must be accepted by the Government Designated Authority prior to the commencement of work.

POTENTIAL QUOTERS ARE NOTIFIED THAT THE BASIS ON WHICH AWARD WILL BE MADE IS PRICE

ALONE.

ALL RESPONSIBLE SOURCES MAY SUBMIT A RESPONSE WHICH, IF TIMELY RECEIVED, MUST BE

CONSIDERED BY THE AGENCY.

INVOICES SHALL BE SENT TO TECHNICAL POINT OF CONTACT.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job CRL Generator Installation

FFP

Contractor shall furnish all labor, materials, and equipment to remove and dispose of the existing generator, provide and install a new 20 kWh generator, concrete pad, and LP tanks at Colebrook River Lake, Colebrook, CT in accordance with the Statement of Work.

FOB: Destination

PURCHASE REQUEST NUMBER: W13G86418395160001

PSC CD: N061

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job OPTION CRL ATS Installation

FFP

Contractor shall furnish all labor, materials, and equipment to replace the Automatic Transfer Switch at Colebrook River Lake, Colebrook, CT in accordance with the Statement of Work.

FOB: Destination

PSC CD: N061

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

REPLACE AUTOMATIC STANDBY GENERATOR

COLEBROOK RIVER LAKE

426 A COLEBROOK RIVER RD

COLEBROOK, CT. 06021

I. General

1. Scope - Furnish all necessary labor, equipment, and supplies and materials necessary to perform the following work at the Colebrook River Lake Project Office. This is a US Army Corps of Engineers Flood Control Facility:

- Disconnect, remove, and completely dispose of existing Cummins/Onan generator;

Model C25 D6/ SN 72019975/ BT 3.3 / 4-cylinder engine rated at 25 kW, 120/240 volt, Single Phase, 3 wire, 60 hertz.

- Furnish and install one (1) 20 kW/20 kVa minimum, 120/240volt, 60Hz, Single Phase, Liquid Propane (LP), Automatic Standby Generator with Self-Test capability and all-weather protective enclosure.

- Furnish and install one (1) 250-gallon Liquid Propane (LP) fuel tank, to include all supplies and materials necessary for connection to generator, operational testing, and normal operation/self-testing of generator.

- Should existing Automatic Transfer Switch (ATS) be incompatible with new generator, the Government may exercise the OPTION to replace.

All work will be performed in a timely manner to the satisfaction of the Technical Point of Contact and in accordance with the following Performance Work Statement.

2. Location – Project Office, 426 A Colebrook River Rd, Colebrook, CT. 06021

3. Site Visit – Contact the Technical Point of Contact (TPOC), John Haluchak, 978-318- 8439 john.a.haluchak@usacearmy.mil to arrange a site visit.

4. Schedules - The Contract period of performance will be one hundred eighty (180) days from contract award (if no bonds are required) or Notice to Proceed (if bonds are required). The project area will be open to the Contractor Monday through Friday, 7:00AM to 3:00PM and all work must be done during those hours, unless additional hours are approved by the Technical Point of Contact (TPOC). No work shall be done on weekends or Government Holidays.

All preconstruction submittals shall be submitted within 21 days of contract award or Notice to Proceed. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall be resubmitted to the Government in an acceptable form within 14 days of the Government’s response, unless additional time is granted by the Government in writing. No field work may proceed prior to the acceptance of preconstruction submittals.

5. Safety Requirements

a. General:

All work shall be conducted in accordance with the U.S. Army Corps of Engineers (USACE) Safety and Occupational Health Requirements (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at the following link:

https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf

Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.

b. Accident Prevention Plan (APP):

The Contractor shall prepare a site-specific Accident Prevention Plan. The APP must be written by a Competent Person (CP) and document the specific work processes, equipment, materials to be used, hazards and applicable control measures.

The mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) must be submitted and accepted prior to beginning on site work:

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_2023Aug31.pdf

A preparatory meeting shall be conducted by the Prime Contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

Daily safety meetings shall be held and documented. Records shall be available to the Technical Point of Contact upon request.

c. Activity Hazard Analysis (AHA):

An AHA shall be submitted and accepted for each definable feature of work (DFOW) in accordance with EM 385-1-1, Chapter 2-6. A DFOW is defined as any task, which is separate and distinct from other tasks, has separate control requirements, or is identified as different trades or disciplines. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

For a non-mandatory formatted outline of an AHA, see ENG Form 6206 (Activity Hazard Analysis) https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf

d. Site Safety and Health Officer (SSHO) Requirements:

The Contractor shall employ a minimum of one person to function as a Level 3, SSHO. A Level 3 SSHO is a designated Qualified Person (QP) or Competent Person (CP) with Safety and Occupational Health (SOH) responsibility that meets the requirements of EM 385-1-1, Chapter 2-3.b and 2-4.b.

Level 3 SSHOs must have training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.

The SSHO shall be present at the project site and be responsible for overseeing the implementation of the Prime Contractor’s SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf

e. First-Aid and CPR Personnel Requirements:

For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR. When employees work alone, they must be certified in First Aid and be provided an effective means of communication to call for assistance in the event of an emergency. Minimum First Aid and CPR qualifications are outlined in EM 385-1-1, Chapter 3-3.

f. Additional Personnel Requirements:

Other Competent Person (CP) or Qualified Persons (QP) may be required per EM 385- 1-1 and/or other sections of this Scope of Work, based on the definable features of work for this project.

g. Accident Reporting:

All accidents and near misses shall be investigated by the Contractor and reported to the Technical Point of Contact in accordance with EM 385-1-1, Table 2-1.

The mandatory ENG Form 3394 shall be completed and submitted to the Technical Point of Contact within seven (7) days of an incident:

https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_ Form_3394_2021Aug.pdf

h. Employee Exposure Data:

The Contractor shall electronically report total employee work hours (including subcontractors) to the Technical Point of Contact by close of business on the 10th calendar day of the following month.

i. Electrical

1. General Requirements (EM385-1-1, Ch. 11-8):

All electrical work must comply with EM 385-1-1 (Paragraphs 11 & 12) and applicable American National Standards Institute (ANSI), ASTM International Standards, Electrical and Electronics Engineers Association (IEEE), National Fire Protection Association (NFPA), National Electric Safety Code (NESC), Occupational Health and Safety Administration (OSHA), Underwriters Laboratories (UL), Unified Facilities Criteria (UFC), and those regulations outlined in 29-CFR-1910 and 29-CFR-1926. In the circumstance where a discrepancy between the codes and regulations listed above, or an omission exists, the most stringent regulations shall apply.

All electrical wiring and equipment must be a type listed by a Nationally Recognized Testing Laboratory (NRTL) for the specific application for which it is to be used. For equipment not listed by a NRTL, the Authority Having Jurisdiction (AHJ) must determine if use is allowable.

2. Roles and Responsibilities:

a. Qualified Persons (QPs) Electrical: QPs must demonstrate the skills and knowledge related to the construction, operation, and maintenance of electrical equipment and installations, and receive relevant safety training to recognize, avoid, and control associated hazards that might be present. (EM385-1-1, Para.

11-3.b). QPs will meet requirements in accordance with EM 385-1-1, Para. 11- 3 and 11-4.

Note: A person can be considered qualified with respect to certain equipment and tasks, but still be unqualified for others.

b. Unqualified Persons: Unqualified Persons who may be exposed to shock and arc flash hazards must be trained and familiar with any electrical safety-related practices for their safety. (Ref. EM385-1-1, 11-3.c)

3. Establishing an Electrically Safe Work Condition (ESWC):

All equipment and circuits must be placed into an ESWC by a Qualified Person(QP) before worked is performed, in accordance with EM385-1-1, Para. 11- 8.d.

If work MUST be performed on an energized system, QP must demonstrate that de-energizing introduces additional or increased hazards or is infeasible due to equipment design or operational limitations (ex. testing, troubleshooting).

4. Energized work may never be performed without prior authorization. Once it has been determined that equipment must be worked on in an energized condition, an Energized Electrical Work Permit (EEWP) shall be submitted to the Technical Point of Contact for acceptance.

A non-mandatory ENG Form 6277 (Energized Electrical Work Permit) is provided in EM385-1-1, para. 11-10. Other permit formats may be accepted provided they meet the minimum information requirements in EM385-1-1, Para. 11-8(4).

Energized Electrical Work Permit exemptions are noted in EM385-1-1, Para. 11- 8(5).

5. Minimum Plan Requirements:

a. Electrical Safety Plan (ESP) must meet all requirements set forth in EM385-1-

1, Para. 11-7, and is required when personnel perform work that involves exposure to electrical hazards. The ESP must be developed according to NFPA 70E and when work involves exposure to electrical hazards associated with electric power generation, transformation, transmission, and/or distribution lines and equipment, additional requirements according to 29 CFR 1926.950, 29 CFR 1910.269, and the NESC.

b. Site Specific Energy Control Plan (SSECP): When working on or near any system that produces, uses, or stores hazardous energy, a SSECP is required.

USACE-owned/operated facilities and activities must comply with ER-1-31 and any regional HECP as well as local supplements in lieu of EM385-1-1, Para. 12-4.

The SSECP must be site-specific and developed according to EM385-1-1, Fig.

12-1 and ANSI Z244.4, and when electricity is a potential energy source, the plan must also include the required elements of NFPA 70E. The plan must clearly and specifically outline the scope, purpose, authorization, roles and responsibilities, and techniques to be used to complete the work.

j. Cranes and Load Handling Equipment (LHE), if applicable:

a. General: All load handling equipment (LHE) operations are required to be completed in accordance with EM 385-1-1, Chapter 16. The requirements apply to all LHE with a hoisting or lifting capacity over 2,000 lbs. (907.2 kg).

LHE includes cranes, derricks, hoists, and power-operated equipment (excavators, forklifts, rough terrain equipment) when used with rigging that can raise, lower, and horizontally move a suspended load.

b. Operator Requirements: Only properly trained, certified, and qualified personnel that are designated in writing by the employer may operate LHE.

Prior to designating any LHE operator, the employer must obtain the intended operational functions and proof of qualifications for the operator in accordance with EM 385-1-1, Chapter 16-3.

i. Certification: Crane operators must be trained, tested, and certified by a nationally accredited testing organization. The training must address applicable ASME B30 requirements and include a successful completion of written and practical/operational examinations.

ii. Physical Qualifications/Examination: Class I operators must receive a physical exam, at a minimum of every three years, meeting the requirements of the ASME B30.5.

iii. Designation: The employer is responsible for designating operators and verifying all their required documents are completed in accordance with the applicable requirements.

c. Signal Person Requirements: Signal Persons shall meet the minimum qualifications and requirements of EM 385-1-1, Chapter 16-3.i.

d. Qualified Rigger Requirements: Qualified riggers shall meet the minimum qualifications and requirements of EM 385-1-1, Chapter 15-3 and 15-4.

e. Minimum Plan Requirements: A lift plan is required to be submitted and accepted by the Technical Point of Contact prior to any lifting operations. Non-mandatory, lift plan templates are available for use. However, contractors are permitted to submit their own lift plans, in accordance with EM 385-1-1, Chapter 16-7.

i. ENG Form 6203, Crane Standard Lift Plan (SLP):

https://www.publications.usace.army.mil/LinkClick.aspx?fileticket=qZwL LyJg_bA%3d&tabid=16438&portalid=76&mid=43543

ii. ENG Form 6213, Load-Handling Equipment Crane Operation Critical Lift Plan (CLP):

https://www.publications.usace.army.mil/LinkClick.aspx?fileticket=cdme uIZKLQI%3d&tabid=16438&portalid=76&mid=43543

f. Operational Testing: A QP must conduct operational tests, in accordance with EM 385-1-1, Chapter 16-8.s, the applicable ANSI/ASME standard, and the manufacturer’s instructions.

g. Mandatory Form(s):

i. ENG Form 6209, Certificate of Compliance (CoC) for Load Handling

Equipment (LHE) and Rigging:

https://www.publications.usace.army.mil/LinkClick.aspx?fileticket=kzvU 4YyG1yU%3d&tabid=16438&portalid=76&mid=43543

6. Preconstruction Conference:

Prior to the start of any work, the TPOC will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel will be physically present to attend this meeting. The Contractor shall directly oversee all work on the project and the Project Manager and Quality Control Personnel shall have the authority to act for the Contractor. This conference will be held at the time and location agreeable to the Government and Contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the TPOC to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Preconstruction Conference the Contractor shall provide the name of the project superintendent with a telephone number for project coordination The following is a general list of items for discussion during this Preconstruction Conference:

i. Authority of the Technical Point of Contact and Quality Assurance Inspectors

ii. Contractor’s Safety Program (including sub-contractors)

iii. Mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) and Activity Hazard Analysis for each Definable Feature of Work (DFOW)

iv. Safety Meetings

v. ENG Form 3394 (Mandatory if needed for Accident Reporting)

vi. Safety Data Sheet (SDS) requirements

vii. Correspondence, Communication and Administrative Procedures

viii. Invoice and Payment

NOTE: Work cannot begin until all safety paperwork is submitted and accepted by the Government

7. Permits:

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, state, county, and municipal laws, codes, and regulations in connection with the work specified under this contract.

8. Security:

The Contractor shall comply with all established security policies at Colebrook River Lake.

If applicable, Contractor shall comply with Projects Key Control Management Program.

Due to periods of heightened security, which may affect access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor’s ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The Contractor shall be given at least a 24-hour notice of any such closure.

9. Contractor’s Personnel:

a. Employee Conduct:

The Contractor shall be responsible for seeing that the Contractor’s employees strictly comply with all Federal, state, and municipal laws. Any personnel activity, which, in the opinion of the Government, is deemed detrimental to the performance of the contract may result in the removal of Contractor employee/employees.

Examples of unbecoming actions or conduct include but are not limited to the following:

i. Cursing, harassment, or discrimination of and/or unwarranted physical contact with visitors, USACE personnel, or other contractors

ii. Recurring written and/or verbal complaints from visitors, USACE personnel, or other contractors.

iii. Unsafe operation of vehicles while on USACE property.

b. Removal of Contractor’s Employees:

The Technical Point of Contact may require the Contractor to immediately remove from the work site any employee of the Contractor or subcontractor, who, in the opinion of the Technical Point of Contact, who endangers persons or property, or whose physical or mental condition is such that it would impair the employee’s ability to satisfactorily perform assigned work. Notification to the Contractor shall be promptly made in writing if time and circumstances permit. Otherwise, notification shall be verbal or by telephone, and shall be confirmed in writing as soon as possible.

No such removal, however, will reduce the Contractor’s obligation to perform all work required under this contract, and immediate replacement will be made as required. This requirement shall not be made the basis of any claim for compensation or damages against the United States or any of its officers or agents.

Note: At least one of the Contractor employees on site shall be able to communicate effectively and efficiently with all project staff.

10. Warranty:

The generator set and associated equipment shall be warranted by the manufacturer against defective material for a period of not less than 5 years from the date of commissioning against defects in materials and workmanship. The warranty shall be comprehensive. No deductibles shall be allowed for travel time, service hours, repair parts cost, etc. The warranty period shall commence when the standby power system is first placed into service. Multiple warranties for individual components (engine, alternator, controls, etc.) will not be acceptable. Satisfactory warranty documents must be provided.

11. Payment:

After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact that includes the name of Contractor, invoice date, contract number, description of work completed, total number of haul loads, estimated volume for each haul load, and total amount due. Final payment is made within 30 days. For jobs that are over 30 days, the Contractor may request multiple payments.

All invoices may be mailed to:

U.S. Army Corps of Engineers Colebrook River Lake PO Box 58 Riverton, CT 06065 Or emailed to john.a.haluchak@usace.army.mil

II. Technical Requirements

1. Submittals:

Although the Government reviews submissions required by this Statement of Work, it is emphasized that the Contractor’s work must be completed using proper internal controls and review procedures. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall resubmit to the Government in an acceptable form within 14 days of the Government’s response, unless additional time is granted by the Government in writing.

The documents identified below must be prepared in accordance with the applicable standards, submitted to the TPOC for review and must be accepted by the Government.

Preconstruction Submittals: Submitted within 21 days of Notice to Proceed. Submittals must be accepted prior to the commencement of any field work activities.

a. ENG Form 6293 (Accident Prevention Plan Worksheet)

b. Activity Hazard Analysis; non-mandatory template available: ENG Form 6206

c. ENG Form 6282 (Site Safety and Health Officer Designation Letter)

d. First-Aid and CPR Personnel requirements

e. ENG Form 6209, Certificate of Compliance for Load Handling Equipment and

Rigging (If applicable)

f. ENG Form 6203, Crane Standard Lift Plan (SLP), if applicable.

g. ENG Form 6213, Load-Handling Equipment Crane Operation Critical Lift Plan

(CLP), if applicable.

h. Electrical Safety Plan (ESP)

i. Site Specific Energy Control Plan (SSECP)

j. Safety Data Sheet (SDS) for applicable materials

k. Product submittals for each item to be provided and installed

l. Licenses and Certifications as determined by the scope of work

m. Safety Inspection for all Heavy Equipment: The Contractor shall submit a current written safety inspection for all heavy equipment proposed for use on this contract.

n. Work Site Plan: Prior to the start of on-site work, the Contractor shall submit a site plan.

o. Work Plan and Schedule: The Contractor shall submit a written Work Plan describing the methods and equipment required to accomplish the work and provide the required environmental and worker protection; this plan will include a schedule of work.

p. Environmental Protection Plan: The Contractor shall submit an Environmental Protection Plan for review and approval by the Technical Point of Contact.

2. Clean Up:

The Contractor shall practice good housekeeping to maintain a safe job site. The Contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work in an area, the Contractor shall remove any tools, equipment, and materials that are not the property of the Government.

Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.

3. Government Resources:

The Contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, water, electricity, telephone services or other resources.

4. Omissions:

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable and functional product.

5. Quality Assurance:

The Contractor is responsible for the quality control of the contract work. The Government has the right to inspect and test all items called for by the contract, to the extent practicable always and at all places during the term of the contract.

6. Other Contracts:

The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other contractors and Government employees. The Contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor or by Government employees.

7. Environmental Protection:

Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the Contractor at the site, and the site will be inspected/ cleaned daily. No burning is permissible. Water, air, and land resources shall not be adversely impacted during the work. The Contractor will take necessary steps to ensure all Federal, State, and Local environmental regulatory requirements are met at no additional cost to the Government.

Assurance of compliance with this section by subcontractors shall be the responsibility of the Contractor.

8. Storage Area:

The storage area for use by the Contractor, for work and storage of equipment, materials, and trailers during the life of this contract will be determined at the Preconstruction Conference. The storage area will be located at Colebrook River Lake.

The Contractor shall confine its storage area to the limits as designated or approved by the TPOC and shall be responsible for the security of the area. Upon completion of the contract, and at no additional cost to the Government, remove all equipment and materials, except as otherwise specified, and restore the site to its original condition as approved by the TPOC.

Trailers, equipment, or materials must not be open to public view except for those items which are in support of ongoing work on any given day. Do not stockpile materials outside the storage area in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment within the storage area at the end of each workday.

9. Products:

a. Sustainability

Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels.

Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.

b. Generator

i. (1) 20 kW/20 kVa minimum, 120/240volt, 60Hz, Single Phase, Liquid Propane

(LP), Automatic Standby Generator with Self-Test capability.

ii. All-Weather Protective Enclosure.

c. Automatic Transfer Switch (ATS)

i. The Government may choose to exercise the option for (1) 200 amp Service Rated Automatic Transfer Switch (ATS) if existing ATS cannot be used.

ii. All necessary electrical cables, wiring, conduit, and junction boxes to properly make the electrical connection to the generator to ensure proper operation, regular self-testing, and standby operation.

d. Liquid Propane (LP) Tank

i. 250-gallon Liquid Propane (LP) tank preferred. The Government understands supply chain issues may limit procurement options. Contractor may be permitted to connect multiple smaller tanks to reach minimum 250-gallon storage capacity on site.

ii. All necessary fuel lines, pipping, connections, elbows, and tees to properly make the (LP) connection to the generator.

iii. New Liquid Propane tank shall be placed in the designated area and will comply with all federal, state, and local building codes and regulations.

iv. Tank will be filled to eighty percent (80%) capacity by Contractor prior to testing generator.

e. New Propane Tank Concrete Pad

i. Pad will be placed in the designated area and will comply with all federal, state, and local building codes and regulations.

ii. Be constructed of reinforced concrete to be at least 4 inches in depth and sized to have a footprint that exceeds the length and width dimensions of the tank by a factor of 10 percent.

iii. Soil shall be appropriately compacted.

III. Execution:

1. General:

a. Contractor shall install all products to manufacturer recommendations and in accordance with all electrical codes and federal, state, and local building codes and laws, and safety standards.

b. Only new, unused materials will be installed. Used or damaged materials will not be installed.

c. Activities including - but not limited to - removal and installation work, shall be scheduled so weather-related events will not damage new or existing materials or equipment.

d. Contractor must be able to cover and protect all work areas, materials and equipment that would otherwise be exposed to the elements during a weather event, expected or unexpected.

2. Existing Conditions:

a. Existing generator is inoperable and requires removal and disposal: Manufactured by

Cummins/Onan, Model C25 D6/ SN 72019975/ BT 3.3 / 4-cylinder engine rated at 25 kW, 120/240 volt, Single Phase, 3 wire, 60 hertz.

b. Colebrook River Lake project office is easily accessible via paved road, located off Route

8 in northeastern Connecticut. This is a remote area, but all amenities are available within thirty minutes of the project office.

c. Vehicle access to job site is limited by access gate. Building access is limited. Contractor must coordinate access with Technical Point of Contact.

2. Removal:

a. Contractor will disconnect all connections to the existing 25 kW, 200 amp, Cummins/Onan Single Phase Diesel Generator by a Qualified Person (QP) and in accordance with all most recent electrical codes and federal, state, and local laws and regulations.

b. Contractor will remove any remaining fuel in generator tank, approximately one hundred fifty (150) gallons, and legally dispose of existing generator. All associated debris and remaining fuel resulting from removal work completed under this contract will be done in accordance with all applicable safety standards, federal, state, and local laws and regulations.

c. Contractor will be responsible for ensuring the existing 11’ x 4’ concrete pad is not damaged during the removal work as it will be re-used for the new automatic, standby generator. Any damage to the concrete pad will be repaired to the previous conditions and at the Contractor’s expense.

d. Contractor will recycle waste and demolition materials, when possible, and in accordance with applicable federal, state, and local laws and regulations.

3. Installation:

a. Contractor shall be responsible for providing and installing a new 20 kW/20 kVa minimum, 120/240volt, 60Hz, Single-Phase, Liquid Propane (LP), Automatic, Standby Generator with All-Weather Protective Enclosure. To be placed on existing eleven foot by four foot (11’ x 4’) concrete pad, which may need to be extended to meet the requirements for the new generator (sized to fit new generator plus 10% for both length and width). (Informational Photo #3)

b. Contractor shall be responsible for connecting new generator to the existing Automatic Transfer Switch (ATS). (Informational Photo #5 - #9)

c. Contractor will install new Liquid Propane (LP) tank(s) in the designated location.

(Informational Photo’s #2)

d. Contractor will connect Liquid Propane (LP) lines and piping from the new automatic, standby generator to the new Liquid Propane (LP) tank(s).

e. Contractor will perform a full test of all equipment upon completion of generator and LP tank(s) installation, to the satisfaction of the Technical Point of Contact (TPOC).

f. Contractor shall install all products to manufacturer’s recommendations in accordance with all electrical codes and federal, state, and local building codes and laws.

4. Option Task:

If it is determined that the current automatic transfer switch cannot be used based on documentation from the new generator manufacturer submitted by the Contractor, the Contractor shall be responsible for installing a new 200 amp Service Rated Automatic Transfer Switch and running and connecting all electrical lines. No work identified under the optional task shall be performed until the Contractor receives a formal modification to the Purchase Order signed by the Contracting Officer.

ATTACHMENTS

PLEASE REFER TO THE ATTACHMENTS INLCUDED WITH THIS SOLICITATION FOR ADDITIONAL

INFORMATION

REPLACE AUTOMATIC STANDBY GENERATOR

COLEBROOK RIVER LAKE

426 A COLEBROOK RIVER RD

COLEBROOK, CT. 06021

Information Photo #1

Project Office

Information Photo #1a

Project Office

Information Photo #2

Information Photo #3

Existing Generator and 11‘ x 4’ pad

Information Photo #4

Information Photo #5

Information Photo #6

Information Photo #7

Information Photo #8

Information Photo #9

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 180 dys. ADC 1 COLEBROOK RIVER PROJ OFC

JOHN HALUCHAK

426A COLEBROOK RIVER ROAD

RIVERTON CT 06021

978-318-8439

961108

0002 180 dys. ADC 1 (SAME AS PREVIOUS LOCATION)

961108

Section H - Special Contract Requirements

SECURITY REQUIREMENTS

General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (eg., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures –this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clauses of this contract, should FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

WAGE DETERMINATION

General Decision Number: CT20240019 08/09/2024

Superseded General Decision Number: CT20230019

State: Connecticut

Construction Type: Building

County: Litchfield County in Connecticut.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.20 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2024. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $12.90 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2024. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2024 1 02/09/2024 2 04/19/2024 3 06/07/2024 4 07/12/2024 5 08/09/2024

ASBE0033-002 06/01/2023

Rates Fringes

HEAT & FROST INSULATOR

(Includes Duct, Pipe and Mechanical Systems)..............$ 45.56 32.65

CARP0326-031 05/06/2024

Rates Fringes

CARPENTER (Includes Form Work)...$ 39.54 28.68

ELEC0488-013 06/01/2024

Rates Fringes

ELECTRICIAN......................$ 45.40 3%+33.57

IRON0015-009 06/03/2024

Rates Fringes

IRONWORKER (Reinforcing, Structural)......................$ 45.25 41.27

LABO0665-001 04/07/2024

Rates Fringes

LABORER (Common or General)......$ 34.50 27.26

PAIN0011-021 06/01/2024

Rates Fringes

PAINTER (Brush and Roller).......$ 38.07 25.70

* ROOF0009-001 06/01/2024

Rates Fringes

ROOFER

Composition.................$ 42.50 21.59 Slate and Tile..............$ 43.00 21.59

SHEE0038-007 07/01/2023

Rates Fringes

SHEET METAL WORKER (Including Metal Flashing)..................$ 50.60 45.61

SUCT2016-001 09/19/2018

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 29.36 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .