About this file

This document is an Amendment to Solicitation W912WJ24Q0146 for Carpet & Drop Ceiling Replacement at the Quechee Gorge Visitor Center and North Hartland Lake Project Office in Vermont.

The amendment provides responses to industry questions and revises the Statement of Work. The work consists of removing and replacing approximately 850 square feet of carpet and 500 square feet of drop ceiling at the North Hartland Lake project office, as well as 800 square feet of carpet at the Quechee Gorge Visitor Center's lower level. The solicitation closing date remains August 16, 2024 at 5:00 PM Eastern. The procurement is set-aside for small businesses under NAICS code 238330, with a size standard of $19 million. All vendors must have an active SAM.gov registration to be considered.

View the file

Other files

File Type Posted
Attachments.pdf PDF
Solicitation W912WJ24Q0146.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment is necessary to provide responses to questions from industry and revise the Statement of Work.

Solicitation closing remains August 16, 2024 at 5:00 PM Eastern.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 12

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Aug-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ24Q0146

X 9B. DATED (SEE ITEM 11)

01-Aug-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Aug-2024

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

jennifer.m.samela@usace.army.milEMAIL:978-318-8324TEL:

JENNIFER M SAMELA / ADDED BY UPASS

W912WJ24Q0146

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

REQUEST FOR INFORMATION

QUESTION 1: Does the size of the carpet tile have to be 12” x 12” exactly?

RESPONSE 1: No, the requirement has been revised to a minimum carpet tile size of 12” x 12”. Please see revised Statement of Work for additional information.

QUESTION 2: Does the ceiling tile framing need to be replaced?

RESPONSE 2: Yes, as indicated in Part 2.2. and revised Part 3.1.b. of the Performance Work Statement, the ceiling tile framing needs to be replaced. Please see revised Statement of Work for additional information.

QUESTION 3: Do the ceiling tiles need to be fire rated?

RESPONSE 3: No, the ceiling tiles do not need to be fire rated.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

STATEMENT OF WORK

PROJECT OFFICE CARPET & DROP CEILING REPLACEMENT

QUECHEE GORGE VISITOR CENTER CARPET REPLACEMENT

U.S. ARMY CORPS OF ENGINEERS

NORTH HARTLAND LAKE

NORTH HARTLAND & QUECHEE, VERMONT

STATEMENT OF WORK

REVISED

I. General:

1. Scope – Contractor shall furnish all labor, materials, and equipment necessary for removal and replacement of:

a. Eight hundred fifty square feet (850 sqft) of carpet and five hundred square feet (500 sqft) of drop ceiling at the North Hartland Lake project office.

b. Eight hundred square feet (800 sqft) of carpet at the Quechee Gorge Visitor Center’s lower level.

c. All work shall be completed in accordance with the following Statement of Work.

2. Location –

a. North Hartland Lake is located at 112 Clay Hill Road, North Hartland, VT 05052.

b. Quechee Gorge Visitor Center is located at 5966 Woodstock Road, Quechee, VT 05059.

3. Site Visit – Contact the Technical Point of Contact to arrange a site visit. The Technical Point of Contact (TPOC) for the project is Park Ranger, Matthew R. Regis 802-295-2855 or Matthew.R.Regis@usace.army.mil .

4. Schedule – The work shall be completed 60 days from contract award or Notice to Proceed.

The Contractor will coordinate with the Government for the estimated start date. Work shall be performed Monday through Friday 7:00 AM to 3:30 PM unless otherwise approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.

The Pre-Construction Conference shall be completed with fourteen (14) days of contract award.

All pre-construction submittals shall be submitted within fourteen (14) days of contract award or Notice to Proceed. The Government reserves up to fourteen (14) days for review and acceptance on each submittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall be resubmitted to the Government in an acceptable form within seven (7) days of the Government’s response, unless additional time is granted by the Government in writing. No field work may proceed prior to the acceptance of pre-construction submittals.

5. Safety Requirements-

a. General:

All work shall be conducted in accordance with the U.S. Army Corps of Engineers (USACE) Safety and Occupational Health Requirements (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), Federal, State, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at the following link:

https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf

Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.

b. Accident Prevention Plan (APP):

The Contractor shall prepare a site-specific Accident Prevention Plan. The APP must be written by a Competent Person (CP) and document the specific work processes, equipment, materials to be used, hazards and applicable control measures.

The mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) must be submitted and accepted prior to beginning on site work:

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_2023Aug31.pdf

A preparatory meeting shall be conducted by the Prime Contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

Daily safety meetings shall be held and documented. Records shall be available to the Technical Point of Contact upon request.

c. Activity Hazard Analysis (AHA):

An AHA shall be submitted and accepted for each definable feature of work (DFOW) in accordance with EM 385-1-1, Chapter 2-6. A DFOW is defined as any task, which is separate and distinct from other tasks, has separate control requirements, or is identified as different trades or disciplines. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

For a non-mandatory formatted outline of an AHA, see ENG Form 6206 (Activity Hazard Analysis) https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf

d. Site Safety and Health Officer (SSHO) Requirements:

The Contractor shall employ a minimum of one person to function as a Level 3, SSHO. A Level 3 SSHO is a designated Qualified Person (QP) or Competent Person (CP) with Safety and Occupational Health (SOH) responsibility that meets the requirements of EM 385-1-1, Chapter 2-3.b and 2-4.b.

Level 3 SSHOs must have training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.

The SSHO shall be present at the project site and be responsible for overseeing the implementation of the Prime Contractor’s SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf

e. First-Aid and CPR Personnel Requirements:

For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR. When employees work alone, they must be certified in First Aid and be provided an effective means of communication to call for assistance in the event of an emergency. Minimum First Aid and CPR qualifications are outlined in EM 385-1-1, Chapter 3-3.

f. Additional Personnel Requirements:

Other Competent Person (CP) or Qualified Persons (QP) may be required per EM 385-1- 1 and/or other sections of this Scope of Work, based on the definable features of work for this project.

g. Accident Reporting:

All accidents and near misses shall be investigated by the Contractor and reported to the Technical Point of Contact in accordance with EM 385-1-1, Table 2-1.

The mandatory ENG Form 3394 shall be completed and submitted to the Technical Point of Contact within seven (7) days of an incident:

https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Fo rm_3394_2021Aug.pdf

h. Employee Exposure Data:

The Contractor shall electronically report total employee work hours (including subcontractors) to the Technical Point of Contact by close of business on the 10th calendar day of the following month.

6. Pre-Construction Conference – Prior to the start of any work, the Technical Point of

Contact will schedule and conduct a “Pre-Construction Conference”. The Contractor’s Project Manager and Quality Control Personnel will be physically present to attend this meeting. The Contractor shall directly oversee all work on the project and the Project Manager and Quality Control Personnel shall have the authority to act on behalf of the Contractor. This conference will be held at the time and location agreeable to the Government and Contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Pre-Construction conference the Contractor shall provide the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Pre-Construction Conference:

i. Authority of the Technical Point of Contact and Quality Assurance Inspectors.

ii. Contractor’s Safety Program (including sub-contractors).

iii. Accident Prevention Plan and Activity Hazard Analysis

iv. Accident Reporting (ENG Form 3394)

v. Safety Data Sheet (SDS) requirements

vi. Contractor’s Equipment

vii. Correspondence, Communication, Security and Administrative Procedures.

viii. Invoice and payment.

NOTE: Work cannot begin until all safety paperwork is submitted and accepted by the Government.

7. Permits – The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, county, and municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

8. Security – The Contractor will comply with all established security policies at North Hartland Lake. Due to periods of heightened security that may affect the access to the areas covered under this contract, the Government reserves the right to close any property or portion of property and reschedule and/or cancel any subsequent work. The Contractor shall be given at least twenty-four (24) hours’ notice of any such closure.

9. Payment – After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of work, description of work, quantities, process, and total amount due per line item. The invoice must also include the company letterhead, and this must match the data that is registered in the System for Award Management (SAM) registry.

For jobs greater than 30 days the Contractor may request multiple payments.

All invoices may be mailed to:

U.S. Army Corps of Engineers North Hartland Lake P.O. Box 55 North Hartland, VT 05052

Or Emailed to matthew.r.regis@usace.army.mil

II. Technical Requirements:

Part 1 General:

1. Summary – Contractor shall furnish all labor, materials, and equipment necessary for removal and replacement of:

a. Eight hundred fifty square feet (850 sqft) of carpet and five hundred square feet (500 sqft) of drop ceiling at the North Hartland Lake project office.

b. Eight hundred square feet (800 sqft) of carpet at the Quechee Gorge Visitor Center’s lower level.

2. Submittals – Although the Government reviews submissions required by this Statement of Work, it is emphasized that the Contractor’s work must be completed using proper internal controls and review procedures. The Government reserves up to fourteen (14) days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall resubmit to the Government within seven (7) days of the Government’s response, unless additional time is granted by the Government in writing.

The documents identified below must be prepared in accordance with the applicable standards, submitted to the TPOC for review and accepted by the Government.

a. Pre-Construction: Submitted within fourteen (14) days of contract award. Submittals must be accepted prior to the commencement of any field work activities.

i. Accident Prevention Plan (ENG Form 6293)

ii. Activity Hazard Analysis

iii. Site Safety and Health Officer Designation Letter (ENG Form 6282)

iv. Safety Data Sheets

v. First-Aid, CPR Certifications

vi. Manufacturer Warranty for applicable products prior to final payment.

vii. Carpet Tile style/colors samples and product submittals for pre-approval.

b. Post-construction: By the completion of work and before final payment.

i. Report of solid waste and recycling quantities prior to final payment.

3. References – All work shall be in conformance with:

a. International Code Council (ICC)

i. International Building Code (IBC) 2021 Edition

b. Other appropriate Federal, State, and local codes for such an installation.

4. Existing Conditions -

a. Project Office Carpet - The Project Office at North Hartland Lake currently has approximately eight hundred fifty (850sqft) of carpet spanning the two main office areas and three (3) adjoining offices. The existing floor treatment in the office is wall to wall carpeting minus the furnace room and bathroom.

b. Quechee Gorge Visitor Center Carpet – The Quechee Gorge Visitor Center currently has approximately eight hundred (800sqft) of carpet spanning the lower level of the building.

c. Ceiling – The Project Office at North Hartland Lake currently has two main offices with approximately five hundred square feet (500 sqft) of drop ceiling suspended above the office area. Drop ceilings are comprised of T-bar channel and four-foot by two-foot (4’x2’) ceiling tiles. Ceiling lighting fixtures are four-foot by two-foot (4’x2’) LED.

Incorporated into the wall and ceiling are two (2) hardwired smoke alarms, a security system, a router box, a mini-split indoor unit (evaporator), as well as piping. A wall-mounted water filtration system is mounted to the wall in between the bathroom and furnace room.

Note: The Contractor is responsible for moving all office furniture, filing cabinets and obstructions from carpeted surfaces. Upon completion of carpet work, the Contractor is required to return all office furniture, filing cabinets and objects back to original placement.

5. Other Contracts - The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The Contractor shall not commit or permit any act which will interfere with the performance of work by another Contractor or by Government employees.

6. Clean Up and Waste Disposal – The Contractor shall practice good housekeeping to maintain a safe job site. The Contractor shall keep the work area, including any designated storage areas free from accumulation of waste materials. Upon completing work in an area, the Contractor shall remove any tools, equipment, and materials that are not the property of the Government. Any and all disturbed areas resulting from Contractor activities shall be restored by the Contractor to the satisfaction of the Technical Point of Contact. All waste material will be disposed of offsite in accordance with all Federal, State, and local regulations.

7. Environmental Protection – Containers for excess and/ or waste materials, rubbish, etc.

shall be provided by the Contractor at the site, and the site will be inspected/ cleaned on a daily basis. No burning is permissible. Water, air, and land resources shall not be adversely impacted during the course of the work. Contractor will take necessary steps to ensure all Federal, State, and local environmental regulatory requirements are met.

8. Sustainability & Environmentally Preferred Products – Under the Comprehensive

Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels. Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.

The United States Department of Agriculture (USDA) designates certain bio-based products for Federal procurement and specifies minimum bio-based content levels for those products.

Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio-based content level. Visit the BioPreferred web site https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml for the complete list of designated products and the associated minimum bio-based content level requirements.

9. Building Protection – Any involved building or structure, and all of its contents shall be protected from the elements during the duration of this contract. The Contractor shall keep on site the means to quickly cover and protect all areas open to the elements during an unforeseen weather-related event that could cause damage to the building and or any of its contents during all phases of this contract.

10. Personal Protective Equipment - It is the Contractor’s responsibility to furnish and supply personnel with the proper personal protective equipment necessary for performing the work.

11. Government Resources – The Government will supply any electricity necessary for the project work from points of existing outlets when available. The Contractor shall carefully conserve the use of electricity provided. The Contractor shall supply his own means of communication (telephone). There is a restroom available at the contract site.

12. Damage to Government and Private Property – The Contractor shall be responsible for restoring all Government facilities or structures damaged as a result of the Contractor’s operation. The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the Contractor’s operation. The Contractor shall notify the Project Manager immediately of damage to Government and private property and injury to any person resulting from the Contractor’s operation. Also, the Contractor shall notify the Technical Point of Contact of damage to Government facilities due to vandalism or other causes on the day such damage is first noticed. Trucks and/or trailers will be driven on existing roads only and not across or through park areas to facilities. The Contractor shall also restore landscape features (shrubs, flowers, grasses, etc.), which are damaged or destroyed by the Contractor’s operation. Damaged or destroyed grass areas shall be re-planted as directed by the Technical Point of Contact, and shrubs and flowers which are damaged or destroyed shall be replaced from nursery stock of like size and kind.

13. Contractor’s Personnel –

a. Minimum Personnel Requirements - The Contractor shall provide an adequate number of fully qualified personnel to perform the specified work properly and efficiently within the time limits specified. The Contractor shall provide a list of the names and contact phone numbers for all employees prior to them working on Government Property.

b. Employee Conduct - The Contractor shall be responsible for seeing that the firm’s employees strictly comply with the Code of Federal Regulations Title 36, Chapter III, Part 327, and all, Federal, State, and municipal laws. Any personnel activity, which, in the opinion of the Government, is deemed detrimental to the performance of the contract may result in the removal of Contractor employee/employees.

Examples of unbecoming actions or conduct include but are not limited to the following:

i. Cursing, harassment, or discrimination of and/or unwarranted physical contact with visitors, USACE personnel, or other Contractors

ii. Recurring written and/or verbal complaints from visitors, USACE personnel, or other Contractors.

iii. Unsafe operation of vehicles while on USACE property.

c. Removal of Contractor’s Employees - The Technical Point of Contact may require the

Contractor to immediately remove from the work site any employee of the Contractor or subcontractor, who, in the opinion of the Technical Point of Contact, is incompetent, who endangers persons or property, or whose physical or mental condition is such that it would impair the employee’s ability to satisfactorily perform assigned work. Notification to the Contractor shall be promptly made in writing if time and circumstances permit.

Otherwise, notification shall be verbal or by telephone, and shall be confirmed in writing as soon as possible. No such removal, however, will reduce the Contractor’s obligation to perform all work required under this contract, and immediate replacement will be made as required. This requirement shall not be made the basis of any claim for compensation or damages against the United States or any of its officers or agents.

14. Omissions – This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, State, or Federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

15. Quality Assurance – The Contractor is responsible for the quality control of the contract work. The Contractor shall establish and maintain a quality control system to assure compliance with the contract requirements. The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

16. Receiving and Storing Materials – The Contractor is responsible for protecting any stored material until it is placed in service. The Contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive materials or supplies for the Contractor and will not be responsible for damage to the Contractor’s equipment or materials.

Part 2 Products:

All products shall be new, unused and to the satisfaction of the Technical Point of Contact.

Products shall be approved by the Technical Point of Contact prior to installation.

1. Carpet -

a. Flooring shall be a minimum of twelve-inch by twelve-inch (12” x 12”) nylon loop carpet tiles. All new carpet tile must be the same size and mixing of tile sizes shall not be permitted.

i. Pressure sensitive adhesive to adhere to carpet floor.

ii. 100% solutions dyed nylon/polyester

iii. Nine (9) tufts per inch

iv. Density of seven thousand (7000)

v. 1/10 gauge

vi. Face weight of 26.00 oz

vii. Finished pile thickness of 0.1330

viii. No pattern repetitions.

ix. Class 1 flammability rating

x. Woven polypropylene backing

xi. The color of the carpet will be a light shade of gray to be approved by the technical point of contact.

xii. Fully recyclable.

xiii. Commercial warranty against edge ravel, zippering, delamination, and moisture degradation.

b. Floor transitions shall cover the seam between the carpet tiles and laminate floors into non-carpeted rooms. Pre-existing transitions shall be replaced with black two-inch (2”) vinyl transition strips into non-carpeted rooms.

2. Ceiling -

a. Ceiling frame shall consist of suspended, fifteen sixteenths (15/16”) T-bar channel.

i. White in color

b. Ceiling tiles shall be four-foot by two-foot (4’ x 2’) acoustic tiles.

i. Three quarter inch (¾”) thickness

ii. Tegular edges

iii. Humidity resistant

iv. White in color

v. Tiles are to be approved by the technical point of contact.

Part 3 Execution:

1. Demolition -

a. Carpets:

i. Existing carpet, transition strips, and glue remnants will be removed and disposed of in a way as to not damage the surrounding baseboard heaters, walls, or paint.

ii. Any debris created by the removal of existing carpet will be cleaned up and removed by the Contractor.

iii. Baseboard heaters will be removed in order to allow carpet to be placed tight to the wall. Shall be stored to reinstall back in place.

iv. Damage to surrounding areas created during work must be returned to previous condition.

b. Ceiling:

i. Existing ceiling system and frame wire remnants will be removed and disposed of in a way as to not damage the surrounding walls or paint.

ii. Any debris created by the removal of existing ceiling will be cleaned up and removed by the Contractor.

iii. Damage to surrounding areas created during work must be returned to previous condition.

iv. The existing lighting is to remain and will not be upgraded. Lighting must be protected and reused.

2. Installation -

a. Carpets:

i. Clean, prepare and level subfloor as needed to properly install new adhesive and twelve by twelve-inch (12”x12”) carpet squares.

ii. New tiles shall be installed using a pressure sensitive adhesive.

iii. New tiles shall be installed in a quarter turn pattern.

iv. New transition strip shall be installed in entrances to rooms that are not carpeted.

v. Baseboards and wall panels will be reinstalled back to original position.

vi. Contractor shall provide at minimum five (5) additional carpet squares for future replacements.

b. Ceiling –

i. The suspended ceiling frame and tiles shall be installed at a height of ninety-six inched (96”) or as approved by the technical point of contact.

ii. Ceiling height shall be the same in both main offices.

iii. The existing interior LED lighting fixtures are to be affixed to the new “T-bar” ceiling grid in the same approximate locations as existing.