Amendment W912WJ24Q0109-0003.pdf
PDF 633 KB Posted
- Solicitation number
- W912WJ24Q0109
About this file
This document is an amendment to Solicitation W912WJ24Q0109 for Debris Removal at North Hartland Lake in North Hartland, Vermont. The amendment provides responses to industry questions, with key details as follows:
- The solicitation closing date remains May 17, 2024 at 2:00 PM Eastern.
- The contractor is responsible for proper disposal of debris off-site in accordance with regulations, and for obtaining any necessary permits.
- No Government assistance will be provided for debris removal, and the grass will not be mowed prior to the work.
- The Government will not provide budget estimates or assistance with floating devices over the Western Log Boom.
- The options for additional debris removal can be exercised by the Government if deemed appropriate.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ24Q0109-0002.pdf | ||
| Amendment W912WJ24Q0109-0001.pdf | ||
| Solicitation_W912WJ24Q0109.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 0003 is to provide responses to questions from industry, question/response No.11 are applicable to this amendment.
The solicitation closing date remains 17 May 2024 at 2:00 pm Eastern.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-May-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ24Q0109
X 9B. DATED (SEE ITEM 11)
29-Apr-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-May-2024
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912WJ24Q0109
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been modified:
REQUEST FOR INFORMATION
QUESTIONS AND RESPONSES
QUESTION 1: Could you please clarify if there are any restrictions or specific times for site access?
ANSWER 1: Per the PWS, 4. Schedule: Work shall be performed Monday through
Friday 7:00 AM to 3:30 PM unless otherwise approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.
QUESTION 2: We would like to know where the debris should be disposed of, and if there are any associated fees.
ANSWER 2: Contractor is responsible for proper disposal of debris material offsite in accordance with all federal state, and local regulations. The Government will not provide any information on associated fees as it is the Contractor’s responsibility to determine where to dispose of debris and if there are any fees for disposal.
Refer to the PWS, I. General, Section 9. Permits: “The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.”
QUESTION 3: Are there any specific equipment requirements or limitations due to site conditions that we should be aware of?
ANSWER 3: Please refer to the PWS, Part 2 Equipment.
QUESTION 4: We would appreciate more details on the optional items for debris removal.
ANSWER 4: The options are included in the event that the amount of debris removed exceeds the estimates associated with each line item. The Government can exercise the options for additional debris removal if deemed appropriate.
QUESTION 5: To negotiate effectively with our subcontractors and ensure alignment with your expectations, could you please provide us with the estimated budget ranges for this opportunity?
ANSWER 5: The Government is not required to provide budget estimates for service requirements.
QUESTION 6: Are there available funds allocated for this opportunity?
ANSWER 6: Yes, funds are available for this project.
QUESTION 7: Due to restricted access, are we able to float devices over the Western Log
Boom with the Government’s assistance?
ANSWER 7: The debris removal is the responsibility of the contractor. The
Government will not assist the contractor with the debris removal.
Please note, if a boat is used, all EM 385-1-1 Safety Requirements must be met.
QUESTION 8: There is a lot of small diameter flood debris that is difficult to locate in the tall grass. Will the grass be mowed prior to the start of the debris removal?
ANSWER 8: No, the grass will not be mowed on the East side of the log boom. The contractor will need to remove the debris from the grass.
QUESTION 9: Does the flood debris <1” diameter need to be removed?
ANSWER 9: On the East side of the log boom, all debris down to three (3) inch diameter along the log boom shall be removed and properly disposed of.
Debris is located along the log boom on a steep grassy slope. Once the debris is removed, the area shall be returned to a smooth surface free of tire ruts, mounds, or divots.
QUESTION 10: Will the Government clear the access road/trail of all debris?
ANSWER 10: Yes, the road/trail leading to the east side of the log boom will be cleared of fallen trees and debris on the road before the contractor comes on site to perform the work.
QUESTION 11: The description of work specifically points out that all woody debris on the eastern side of the log boom needs to be picked up and removed (grassy slope area). That debris is currently scattered and not in a pile, but it is understood and clear that that debris needs to be piled up and removed as part of the contract. On the western side of the log boom which is referred to as the "field" there is quite a bit of woody debris scattered near the log boom line up high in the field that is not piled up either, but there isn't mention of that debris in the description of work. It is clear that the debris in the water at the log boom as well as the six piles located in the field and parking area are to be removed and disposed of, but could you confirm if the woody debris located up high in the field near the log boom line that is not currently piled up needs to be removed as well, or is it just the debris in the water and the six piles on the western side?
ANSWER 11: Only the material in the field that is piled is to be removed. It is not the contractor’s responsibility to pick up the scattered debris in the field.
(End of Summary of Changes)