Amendment W912WJ24Q0007-0001.pdf

PDF 590 KB Posted

Attached to
Debris Removal, North Hartland Lake, Hartland, VT
Solicitation number
W912WJ24Q0007
Issued by

About this file

This document is an amendment to a solicitation for debris removal services at North Hartland Lake in Hartland, Vermont. The U.S. Army Corps of Engineers Engineering District New England is seeking to award a contract to push debris collected along the shoreline towards the contractor's equipment for off-site removal by October 18, 2023. Responses were provided to eight questions from industry regarding site conditions including confirmation that a crane is no longer on site, steep riprap banks of unknown grade along the shoreline, a silty lake bottom covered in sunken debris where no equipment operation will be permitted, water depths of approximately two to twelve feet, and no requirement or means to remove sunken debris. No security clearances or training are required beyond iWatch training. There is no incumbent for this work.

View the file

Other files

File Type Posted
Attachment_Current Debris Photos.pdf PDF
Attachments.pdf PDF
Solicitation W912WJ24Q0007.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W13G86325669930001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment is necessary to provide responses to questions from industry. Recent photos of debris w ill be posted as a separate attachment as w ell.

Closing remains October 18, 2023 at 2:00 PM Eastern.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Oct-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ24Q0007

X 9B. DATED (SEE ITEM 11)

04-Oct-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Oct-2023

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ24Q0007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

REQUEST FOR INFORMATION

Question 1: Is the crane still in the same spot as in the picture? Or has it been removed?

Response 1: The crane shown in the pictures was on site during previous debris removal activities. It is no longer on site.

Question 2: What is the slope percentage from the top of the bank to the water's edge? 25% 30% ect.

Response 2: The bank between the road and water is riprap stone and cannot be driven on otherwise damage will occur. The is steep, but the exact grade is not known. The rip rap is currently covered in debris, however, can be seen in the photos included as a separate attachment.

Question 3: What is the soil type in the lake bed where the debris are boomed ? Is it silt, small stone, and sand base?

Response 3: The lake bottom is silty and covered with sunken debris. The sunken debris does not have to be removed, however, no equipment will be permitted to operate from the lake bottom.

Question 4: What is the depth at the water's edge out to the farthest part of the boomed material.

Response 4: Water depth is approximately two (2) feet along the shore and approximately twelve (12) feet where the temporary boom joins the permanent log boom.

Question 5: Any idea how much material is on the lake bed in the boomed area?

Response 5: The Government has no estimate of the amount of material on the lake bed. The intent of the work in this solicitation is that the Government will push debris towards the Contractor’s equipment on shore and the Contractor will remove debris. There is no requirement to remove sunken debris.

Question 6: Is the soil stabile enough that a tracked machine can move about without sinking or minimal soil disturbance?

Response 6: No equipment will be permitted to enter the water with tracks. The intent is that the Contractor will operate from the pad on land and remove debris that is pushed by the Government.

Question 7: Do you have a soil disturbance limit?

Response 7: The Contractor’s equipment shall operate from the crane pad that is currently established. There are no set soil disturbance limits.

Question 8: Are there any security clearances or security awareness training certificates needed or TWIC card?

W912WJ24Q0007

Response 8: The awarded Contractor will be required to complete iWatch training (review of one slide). No other security clearances/training are required.

Question 9: Is there any access for a barge?

Response: There is no access for a barge. The existing boat ramp is only suitable for smaller (less than 18’) for boats.

Question 10: Is there an incumbent for this work?

Response 10: There is not an incumbent. While previous contracts have been awarded for similar work, the Government has not previously awarded a contract with the same scope of work.

(End of Summary of Changes)