This document outlines a federal contract opportunity for repairs to a breakwater located in the Isles of Shoals between New Hampshire and Maine. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District New England, and seeks bids to repair the breakwater, as described on the Project in Europe and Eurasia website. Interested parties can review the project specifications and requirements on the website, with a solicitation number of W912WJ23B0001. The opportunity type is listed as a solicitation. No further details are provided on response dates, pricing terms, or other requirements for the breakwater repair contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract.pdf | ||
| W912WJ23B0001.pdf | ||
| Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No.:
W912WJ23B0001
REPAIRS TO BREAKWATERS
Isles of Shoals New Hampshire and Maine
Construction Solicitation and Specifications
December 2022
REPAIRS TO BREAKWATERS SOLICITATION COPY
ISLES OF SHOALS, NH AND ME
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 54 50 MARINE PLANT AND EQUIPMENT
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 71 23 FIELD ENGINEERING
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 31 19 BREAKWATER REPAIRS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 PROJECT LOCATION AND DESCRIPTION
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.3 WARNING SIGN
1.4 SPECIAL USE PERMIT
1.5 MOORINGS IN GOSPORT HARBOR
1.6 UNDERWATER DIVING OPERATIONS
1.7 QUALIFICATIONS
1.8 REFERENCES
1.9 SUBMITTALS
1.10 PRECONSTRUCTION CONFERENCE
1.11 EXISTING CONDITIONS PHOTOGRAPHS
1.12 PRE-SITEWORK PHOTOGRAPHIC AND VIDEO SURVEY
1.13 PRE-CONSTRUCTION CROSS-SECTIONS
1.14 SITE CONDITIONS
1.15 ORDER OF WORK
1.16 WORK SEQUENCING AND SCHEDULING
1.16.1 Work Sequence
1.16.2 Hours of Operations
1.16.3 Work Outside Normal Hours of Operations
1.16.4 Scheduling
1.16.4.1 Two-Week Schedule of Work Activities
1.16.4.2 Initial Project Schedule
1.16.4.3 Periodic Schedule Updates
1.16.5 Rate of Progress
1.17 SUPERINTENDENCE BY THE CONTRACTOR
1.18 CONTRACTOR'S USE OF UPLAND FACILITIES AND HAULING ROUTES
1.19 WORK SITE AND CONTRACTOR'S USE OF PREMISES
1.19.1 General
1.19.2 Access to the Site
1.19.3 Temporary Facilities and Utilities, and Staging and Storage
Areas
1.19.4 Work Limits
1.19.5 Protection and Security
1.19.6 Emergency Contacts
1.19.7 Damaged Property
1.19.8 Contractor's Receipt of Supplies
1.19.9 Daily Clean Up
1.19.10 Government Sanitary Facilities
1.20 QUALITY ASSURANCE
1.21 COORDINATION
1.21.1 Notice to Mariners
1.21.2 Aids to Navigation
1.21.3 Points of Contact
1.22 GENERAL SAFETY REQUIREMENTS
1.22.1 General
1.22.2 Contractor's Project Superintendent
1.23 ENVIRONMENTAL PROTECTION
1.24 DIRECTION AND INSTRUCTIONS DURING CONSTRUCTION
SECTION 01 11 00 Page 1
1.25 Payment
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 PROJECT LOCATION AND DESCRIPTION
The Isles of Shoals is a three-mile-long cluster of eight rocky islands and ledges located off the coast of New Hampshire and Maine approximately six nautical miles (nmi) southeast from the entrance to Portsmouth Harbor, New Hampshire. Four of the islands, Star, Cedar, Smuttynose, and Malaga, are situated such that they create a small harbor, known as Gosport Harbor. The harbor is 32 acres in area and is used by commercial and charter fishing boats, recreational vessels, the U.S. Coast Guard during search and rescue operations, and excursion boats from Portsmouth, New Hampshire.
Work in the Isles of Shoals began as early as 1821, when private interests constructed a stone breakwater between Malaga and Smuttynose islands. In 1904, the Corps repaired and strengthened the breakwater to a length of 240 feet and constructed a second stone breakwater, 700 feet long, between Smuttynose and Cedar islands. In 1913, the Corps repaired and strengthened the existing breakwaters and constructed a third stone breakwater, 530 feet long, between Cedar and Star islands. The breakwaters provide vessels with a safe refuge in Gosport Harbor.
However, the Contractor shall be aware that since the work is in the Northeast, and 6 nautical miles from the coast of New Hampshire's Portsmouth Harbor unprotected in the Atlantic Ocean, that the area is prone to severe storms or Nor'Easters throughout the year. These storms have the potential to cause high winds and ocean swells (extreme storm waves), and could make for potentially dangerous situations. The Contractor shall monitor the weather at all times during the period of performance (refer below to subpart titled "Weather Conditions").
The project will consist of repairing three stone rubble mounded breakwaters located between the four islands of Star, Cedar, Smuttynose, and Malaga. Over the years, the rock structures were damaged in particular areas along the length of each structure by intense wave action during storm events. In some areas along Breakwaters 1 and 2 the armor stones were loosened and are no longer stable, and in other areas the armor stones were displaced leaving small to large voids either along the side slopes or completely through the structures. The armor stones for Breakwater 3 were completely displaced leaving no formed structure.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
a. The Contractor shall perform the work in strict accordance with the Contract Drawings and Specifications and provide all supervision, plant, labor, materials, equipment, safety, and quality control necessary to perform all operations as necessary to complete the contract work. The Contractor is responsible for providing and utilizing appropriate plant and equipment as needed to handle, remove and reset, and rehandle existing armor stones and the furnishing, handling, and placement of new armor stones. For intent of the repairs refer to Section 35 31 19 BREAKWATER REPAIRS under paragraph
SECTION 01 11 00 Page 3 titled "INTENT OF BREAKWATER REPAIRS".
b. The general description of the work described below is general in nature and is only given to indicate the approximate scope of work under this contract. It does not limit the work required under the project Contract Drawings and Specifications.
c. General Description of the Work:
BASE BID ITEM WORK:
(1) In accordance with the Contract Drawings and Specifications perform all necessary base bid item work to complete the following:
(a) Perform mobilization and demobilization as necessary to complete all work as specified in the Contract Drawings and Specifications.
(b) Repair damaged Breakwater 1, from Star Island to Station 7+25 (top of crest end), by dismantling and removing existing armor stones to specified elevation as shown on the Contract Drawings, to include crest and side slopes. Using existing and new armor stones rebuild breakwater as specified in Section 35 31 19 BREAKWATER REPAIRS and the Contract Drawings. The Contractor shall be aware that eelgrass exists along the harbor side of Breakwater 1 and that restrictions shall apply when working from the water in areas of eelgrass; refer to paragraph titled BIOLOGICAL RESOURCES in Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS. See Contract Drawing sheet G-003 for location of eelgrass.
(c) Harvest displaced existing armor stones along the harbor side of Breakwater 1 and reuse in the repairing of Breakwater 1. Refer to Section 35 31 19 BREAKWATER REPAIRS for requirements pertaining to reuse of existing armor stones.
OPTION ITEM WORK:
(2) In accordance with the Contract Drawings and Specifications perform all necessary option item work to complete the following:
(a) Repair damaged Breakwater 2 by dismantling and removing existing armor stones to specified elevation as shown on the Contract Drawings, to include crest and side slopes. Using existing and new armor stones rebuild breakwater as specified in Section 35 31 19 BREAKWATER REPAIRS and the Contract Drawings.
(a) Repair damaged Breakwater 3 by dismantling and removing existing armor stones to specified elevation as shown on the Contract Drawings, to include crest and side slopes. Using existing and new armor stones rebuild breakwater as specified in Section 35 31 19 BREAKWATER REPAIRS and the Contract Drawings.
(c) If either option item, or both, are exercised for Breakwaters 2 and 3, perform mobilization and demobilization as necessary to complete option item work.
d. The project description and requirements are further defined in the Contract Drawings and Specifications.
SECTION 01 11 00 Page 4
1.3 WARNING SIGN
a. The Contractor shall construct, erect, and maintain a warning sign at each breakwater. The warning sign shall be 36 inches by 48 inches in dimension. The following words shall appear on the sign:
"Breakwater Under Construction - Keep Off"
b. The warning sign shall be erected at least 30 calendar days prior to the start of construction.
1.4 SPECIAL USE PERMIT
Prior to the start of construction, the Contractor shall fill out Form 3-1383-G, GENERAL ACTIVITIES SPECIAL USE PERMIT APPLICATION and submit the completed form to the local US Fish and Wildlife Service representative to obtain a Special Use Permit. A copy of the form is attached at the end of this specification section. Contact information for the local representative can be found below under subpart titled "Points of Contact". As part of the special use permit, the Contractor shall comply with the following:
1. To avoid disruption and disturbance to seabird nesting, no work shall be performed on Smuttynose or Malaga Islands between the dates of 15 April and 31 May, of any given year.
2. All work shall be confined to the construction limits of work shown on sheets G-003 and G-004. All areas within the construction limits of work shall be returned to pre-construction conditions.
1.5 MOORINGS IN GOSPORT HARBOR
The Contractor shall be aware that there are active private moorings scattered throughout in Gosport Harbor. All moorings are private and belong to local yacht clubs, individuals, and the islanders themselves who use them regularly throughout the summer.
1.6 UNDERWATER DIVING OPERATIONS
In the event that the Contractor requires underwater diving operations that may be necessary due to equipment failure or loss of equipment below water, such operations shall be conducted in accordance with EM 385-1-1 , Section 30.
1.7 QUALIFICATIONS
Refer to part 1.3 in Section 35 31 19 BREAKWATER REPAIRS.
1.8 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
SECTION 01 11 00 Page 5
1.9 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Pre-Sitework Photographic and Video Survey ; G, RO
Pre-Construction Cross-Sections ; G, RO
Initial Project Schedule ; G, RO
In accordance with the contract clauses, the Contractor shall, within 5 days after receipt of Notice to Proceed (NTP) or as otherwise determined by the Contracting Officer, submit for approval a practicable project schedule. When changes are authorized that result in contract time extensions, the Contractor shall submit a revised project schedule for approval by the Contracting Officer.
Two-Week Schedule of Work Activities
In addition to the scheduling and notification requirements specified elsewhere in the contract, the Contractor shall provide to the Contracting Officer a detailed schedule of work activities, which the Contractor intends to perform over the following two week period (Monday thru Friday for two weeks).
Notice to Mariners
Submit a copy of Notice to Mariners to the Contracting Officer.
Safe Harbor Plan ; G, RO
The Contractor shall submit a Safe Harbor Plan to the Contracting Officer for approval prior to the start of on-site work. The Safe Harbor Plan shall include a written description of the Contractor's plan to provide for the safety and security of floating plant, equipment, and personnel in the event of a storm or other site emergency. The location for the docking of floating plant and the off-loading of equipment and crews shall be clearly indicated.
SD-07 Certificates
Request Application ; G, RO
Request Application to work outside the hours of operation.
Periodic Schedule Updates ; G, RO
SD-11 Closeout Submittals
Final As-Built Drawings ; G, DO
SECTION 01 11 00 Page 6
Final As-Built Drawings containing site plan for final layout of each breakwater, to include northing and easting coordinates at all beginning and ending points, and points of intersection along each centerline shall be submitted to the Contracting Officer.
As-built drawings shall be produced in CAD software (".dgn" or ".dwg" format) and submitted electronically prior to or along with final payment. Also refer to Section 01 71 23 FIELD ENGINEERING for requirements pertaining to as-built cross-sections.
1.10 PRECONSTRUCTION CONFERENCE
The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the U.S. Army Corps of Engineers (USACE) personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning topics such as, but not limited to, job safety, quality control, temporary facilities and storage areas, labor relations, and environmental protection. The Contractor's Project Superintendent, Quality Control Representative, and Site Safety and Health Officer (SSHO) shall attend this conference.
1.11 EXISTING CONDITIONS PHOTOGRAPHS
Photographs showing the existing conditions of the project area are attached at the end of this specification section. The photographs represent the condition of breakwaters at that time the photos were taken and are attached for informational purposes only. The Contractor shall make its own investigations of existing conditions in the field prior to the start of work.
1.12 PRE-SITEWORK PHOTOGRAPHIC AND VIDEO SURVEY
The Contractor shall perform a pre-sitework photographic and video survey at the project site to document existing conditions with the Contracting Officer. This pre-sitework photographic and video survey shall include still photographs and videos in sufficient quantity to fully document the existing condition of all three breakwaters affected by the work of this contract. The survey shall provide full coverage of all access and staging areas and material placement areas. A written narrative shall be prepared by the Contractor which organizes and summarizes the findings of the pre-sitework survey photographs and videos. The report shall include a written narrative on the condition of each breakwater. The written narrative, together with the photographs and videos, shall constitute a "Pre-Sitework Photographic and Video Survey Report", which shall be submitted to the Contracting Officer for approval. No work shall be performed until this "Pre-Sitework Photographic and Video Survey Report" has been approved. Damage to features caused by the Contractor's operations shall be repaired by the Contractor at no additional expense to the Government.
1.13 PRE-CONSTRUCTION CROSS-SECTIONS
a. Prior to the start of construction, the Contractor shall perform a pre-construction survey of each breakwater to collect cross-sections at 5-foot intervals along the established control lines. The control line stationing shall be marked on the breakwaters prior to the start of the survey work.
SECTION 01 11 00 Page 7
b. The survey data collected for the pre-construction cross-sections shall meet the same requirements as for "As-Built Cross-Sections" found in Section 01 71 23 FIELD ENGINEERING.
c. The Contractor shall process the survey data and prepare and submit drawings to the Contracting Officer showing each cross-section at each 5-foot interval.
d. After the Contracting Officer has received and reviewed the submittal of the cross-section drawings, the Contractor and the Contracting Officer will walk the breakwaters to compare the pre-construction cross-sections with the extent of the repair work as shown on the construction drawings. If it is found that areas of the breakwaters have deteriorated beyond the extents of the repair work, and the added work to repair the deteriorated areas outside the extents of the repair work in needed, the Contracting Officer will change the extents of the repair work under CONTRACT CLAUSE titled "Changes".
1.14 SITE CONDITIONS
Data and information provided or referred to below is for the CONTRACTOR's information. The Government will not be responsible for any interpretation of or conclusion drawn from the data or information by the
CONTRACTOR.
a. Site Conditions: The indications of physical conditions on the drawings and in the specifications are the result of site investigations and surveys. The conditions represented prevailed at the time the investigations and surveys were made. Before commencing work at the site, the CONTRACTOR shall verify the existing conditions indicated on the drawings and in the specifications. See CONTRACT CLAUSE entitled "SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK".
b. Weather Conditions: Weather conditions for the site may be obtained by the Contractor from the National Oceanic and Atmospheric Administration's National Weather Service; www.NOAA.gov.
c. Water-bourne Traffic: Marine traffic may cause significant interference with contract operations. The Government will not undertake to keep the area free from vessels or other obstructions, except to the extent of applicable regulations. The Contractor shall conduct the work in such a manner as to obstruct navigation as little as possible, and in the event the Contractor's plant so obstructs the area as to make difficult or endanger the passage of any vessels, the plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage.
1.15 ORDER OF WORK
a. The Contractor shall prepare and submit to the Contracting Officer for review and approval an outline for the Contractor's intended work sequence and progress schedule as specified below under Part titled "Work Sequencing and Scheduling".
b. Breakwater 1 shall be repaired first starting at the Star Island end of the breakwater. If Option Items 0004 and 0005 are both executed and awarded at the same time, the order in which Breakwaters 2 and 3 shall be of the Contractor's choosing. The order for Breakwaters 2
SECTION 01 11 00 Page 8 and 3 shall take into account the health, safety, impending weather conditions for the time of year, and welfare of the public, Contractor, and Government.
1.16 WORK SEQUENCING AND SCHEDULING
1.16.1 Work Sequence
a. There are certain essential criteria relative to the preparation of a work sequence and time schedule which the Contractor will be required to implement and follow during the prosecution of the work. Minor variations in the sequence of the items of work as approved may be made by the Contractor, provided such variations do not conflict with critical elements of the schedule. Proposed minor variations shall be noted on the progress charts submittal required by CONTRACT CLAUSE, entitled "SCHEDULES FOR CONSTRUCTION CONTRACTS." Variations shall be approved by the Contracting Officer prior to implementation.
b. Between 15 June and 15 October, of any given year, the Contractor shall be prohibited from accessing and using the cross-hatched area on Star Island as shown on Contract Drawing sheet G-003. This area may be used at any other time of year.
1.16.2 Hours of Operations
a. For any work within the period of performance that occurs during the islands' "summer season", that is, from the weekend prior to the Memorial Day weekend to the weekend following Columbus Day weekend, of any given year, the Contractor will only be allowed to perform work from 7:00 a.m. to 7:00 p.m. (12 hours per day), Monday through Friday.
(1) The Contractor will not be permitted to work on Saturday, Sunday, or legal holidays unless otherwise authorized by the Contracting Officer. The exclusion of work on Saturday, Sunday, and legal holidays has been considered in computing the performance time of this contract. Legal holidays are observed on the following days:
January 1st Third Monday in January Third Monday in February Last Monday of May June 19th July 4th 1st Monday of September 2nd Monday of October November 11th Fourth Thursday of November December 25th
(2) When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.
b. For any work within the period of performance that occurs between weekend following Columbus Day weekend to the weekend prior to the Memorial Day weekend, of any given year, the Contractor may work up to 24 hours per day, Monday through Sunday. The Contractor will not be permitted to work on legal holidays unless otherwise authorized by the
SECTION 01 11 00 Page 9
Contracting Officer. See above under subparts a(1) and a(2) for information regarding legal holidays. During periods of darkness, the work shall be lighted in a manner approved by the Contracting Officer.
c. The hours of operation will be further discussed at the Pre-Construction Conference.
1.16.3 Work Outside Normal Hours of Operations
Work outside the hours of operation requires Contracting Officer approval. The request to work outside the hours of operation shall be made in writing to the Contracting Officer at least 15 calendar days prior to such work to allow arrangements to be made by the Government. The request application shall include specific dates, hours, location, type of work to be performed, contract number and project title, and names of all individuals who will be working outside the hours of operations.
1.16.4 Scheduling
1.16.4.1 Two-Week Schedule of Work Activities
In addition to the scheduling and notification requirements specified elsewhere in this section, the Contractor shall provide to the Contracting Officer a detailed schedule of work activities, which the Contractor intends to perform over the following two week period (Monday thru Sunday for two weeks). Refer above to subpart titled "Hours of Operations" for details pertaining to when working on Saturday and Sunday are prohibited.
The schedule of work activities shall be updated and submitted by the Contractor to the Contracting Officer on a weekly basis, by noon on every Thursday during the prosecution of work period.
1.16.4.2 Initial Project Schedule
The initial project schedule shall be in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation pursuant to FAR Clause 52.236-15 "Schedules for Construction Contracts". The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed and indicating calendar days to completion. The Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion of the project. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the chart. This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised. Anticipated adverse weather delay days shall be included and clearly indicated in the schedule. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval.
All work shall be carefully scheduled to prevent delays and any excessive interruptions with channel traffic.
1.16.4.3 Periodic Schedule Updates
An updated schedule showing actual progress shall be submitted monthly and with each pay request. Changes to the base-line schedule shall be outlined in a narrative describing the reason for the change.
SECTION 01 11 00 Page 10
1.16.5 Rate of Progress
a. The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in SPECIAL CONTRACT REQUIREMENTS, Clause COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
(APR 1984) FAR 52.211-10.
b. Should the Contractor fail to maintain a satisfactory rate of progress in accordance with the Contractor's approved progress schedule, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought up to schedule and maintained.
1.17 SUPERINTENDENCE BY THE CONTRACTOR
a. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.
b. The qualified superintendent, and competent alternate, shall be capable of reading, writing, and conversing fluently in the English language.
c. The project superintendent must have a minimum of 10 years experience in marine work with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
d. The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend all partnering meetings and quality control meetings.
e. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
f. The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
g. The project superintendent shall not serve as either the Site Safety
SECTION 01 11 00 Page 11 and Health Officer (SSHO) or the Contractor Quality Control (CQC) System Manager.
1.18 CONTRACTOR'S USE OF UPLAND FACILITIES AND HAULING ROUTES
a. Unless obtained by the Government or specified otherwise in the contract documents, the Contractor shall be responsible for the following:
(1) Locating, coordinating, and obtaining permission to use any land-based water access (docks, piers, ramps, etc.) that the Contractor deems necessary to complete the work.
(2) Determining, if necessary, the trucking and hauling routes and associated restrictions to and from the work, to include the coordination for the use of such routes with local, state, and federal authorities.
(3) Complying with all local, state, and federal regulations and restrictions when using any upland facilities or hauling routes.
b. The Government and its representatives will be allowed the use of the same land-based water access obtained by the Contractor.
1.19 WORK SITE AND CONTRACTOR'S USE OF PREMISES
1.19.1 General
a. Prior to the start of construction, the Contractor shall arrange with the Contracting Officer a sequence of procedures, means of access to work areas, space utilization for staging and storage of materials and equipment, and the use of approaches to the work areas.
b. All rules, regulations, and requirements covering such items as, but not limited to, general safety, security, sanitary requirements, environmental protection, pollution control, and traffic regulations shall be observed by the Contractor.
1.19.2 Access to the Site
The Contractor is responsible for maintaining access necessary for its equipment, material, and plant to and from the work site(s).
1.19.3 Temporary Facilities and Utilities, and Staging and Storage Areas
Refer to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.
1.19.4 Work Limits
Work shall be restricted to the limits of work as shown on the Contract Drawings.
1.19.5 Protection and Security
a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.
b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.
SECTION 01 11 00 Page 12
c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.
d. The Contractor shall report any vandalism, suspicious activities, or devices to the Contracting Officer and local police as soon as possible.
1.19.6 Emergency Contacts
The Contractor shall provide a list of emergency contacts in the event of an emergency. The list shall include the contact names, addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.19.7 Damaged Property
Work shall proceed in a manner which will minimize disturbance or risk of damage to boats, structures, and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.
1.19.8 Contractor's Receipt of Supplies
The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.
1.19.9 Daily Clean Up
The Contractor shall at all times keep rubbish, litter, and tobacco materials from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be removed from the premises daily.
1.19.10 Government Sanitary Facilities
Toilet facilities are not available on site for Contractor's use. The Contractor shall provide portable toilets for its personnel and subcontractors as specified in EM 385-1-1 under Section 2, Sanitation.
1.20 QUALITY ASSURANCE
a. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.
b. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work.
Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government. Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.
c. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.
SECTION 01 11 00 Page 13
d. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.
e. The Contractor shall submit all requests for changes in writing to the Contracting Officer. Do not proceed with changes without possession of written authorization of the Contracting Officer.
f. The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.
1.21 COORDINATION
1.21.1 Notice to Mariners
a. Prior to the start of mobilization and construction, the Contractor shall coordinate with the U.S. Coast Guard (USCG) to issue a "Notice to Mariners" regarding the work to be performed and the Contractor's proposed operations. The Contractor shall fill out a Local Notice to Mariners (LNM) Information Form (Form can be found at the following website: http://www.navcen.uscg.gov ). The contractor shall complete an LNM Information Form and email it to D01-SMB-LNM@uscg.mil (or fax it to 617-223-8094) at least two weeks before the work is to begin.
b. The Corps of Engineers and the USCG have agreed to phraseology when issuing navigational bulletins and notices. The information furnished shall be consistent with USCG Broadcast Notice to Mariners and Local Notice to Mariners. When requesting local USCG offices to issue navigational information for Corps of Engineers work involving marine construction, the following terminology shall be used, as applicable:
(1) For cautionary areas: "Mariners are urged to use extreme caution in the area."
(2) For work operations: "Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made."
1.21.2 Aids to Navigation
a. Aids to navigation (beacons, buoys, markers, etc.) have been placed by the USCG in the vicinity of the project area. The CONTRACTOR shall not interfere with these aids to navigation. If the work of this project requires the temporary movement or relocation of any aid to navigation, the CONTRACTOR shall notify the USCG and the Contracting Officer of the requirement 30 days in advance. USCG personnel will then move or relocate the aid to navigation as appropriate for the progress of the work. Under no circumstances shall the CONTRACTOR move or relocate an aid to navigation under his own authority with his own personnel. The CONTRACTOR shall also contact the USCG at the completion of all work and the removal of all marine plant.
b. The Contractor should be aware that there is a navigation aid (RW "IS" BELL) on the state line outside of Gosport Harbor and shall stay clear of during ingress and egress of the harbor. See attached NOAA chart
SECTION 01 11 00 Page 14
13283 for location of navigation aide.
1.21.3 Points of Contact
a. Coast Guard:
(1) Aids to Navigation:
Mr. John Mauro Office Telephone: 617-223-8355 email: john.j.mauro@uscg.mil
Mr. Matthew Stuck Office Telephone: 617-223-8365 email: matthew.b.stuck@uscg.mil
(2) Notice to Mariners:
D01-SMB-LNM@uscg.mil Contact Telephone Number: 617-223-8356
b. New Hampshire Port Authority 555 Market Street, Portsmouth, NH 03801 Office Telephone: 603-436-8500
Mr. Tracy Shattuck Chief Harbormaster, FSO Mobile Telephone: 603-365-0505 email: t.shattuck@peasedev.org
c. Town of Rye, New Hampshire 10 Central Road, Rye, NH 03820-2522 Town Office Telephone: 603-964-5523
Mr. Leo Axtin Rye Harbormaster Telephone: 603-502-8740 email: l.axtin@comcast.net
d. Town of Kittery, Maine 200 Rogers Road, Kittery, ME 03904 Office Telephone: 207-332-2656 Kittery Port Authority Email: kpa@kitteryme.org
Mr. John Brosnihan Kittery Harbormaster Telephone: 207-451-0829 https://www.kitteryme.gov/user/61/contact
Mr. Chuck Moran Kittery Deputy Harbormaster & Shellfish Warden Mobile Telephone: 207-703-4415 https://www.kitteryme.gov/user/2904/contact
e. Star Island Corporation 30 Middle Street, Portsmouth, NH 03801 Office Telephone: 603-430-6272 Web Site: www.starisland.org
SECTION 01 11 00 Page 15
Mr. Joe Watts Chief Executive Officer email: jwatts@starisland.org
Mr. Jack Farrell Island Manager and Facilities Director email: jfarrell@starisland.org
f. US Fish and Wildlife Services Maine Coastal Islands National Wildlife Refuge Complex 9 Water Street, P.O. Box 1735 Rockland, Maine 04841
Mr. Brian Benedict Refuge Manager Phone: 207-594-0600 x5111 email: brian_benedict@fws.gov
1.22 GENERAL SAFETY REQUIREMENTS
1.22.1 General
a. The Contractor shall take all necessary precautions in observing safety regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and egress. Temporary closures shall not compromise life safety, security or fire safety.
1.22.2 Contractor's Project Superintendent
The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of violations, etc., and including that of any subcontractor's work.
1.23 ENVIRONMENTAL PROTECTION
To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS, and all applicable federal, state, and local laws and regulations concerning environmental protection pollution control and abatement.
1.24 DIRECTION AND INSTRUCTIONS DURING CONSTRUCTION
a. The Contractor shall not take or accept any direction or instructions issued by any person, employed by the Government or otherwise, other than the Contracting Officer that changes the terms and conditions of contract actions, the scope, or any change that impacts the cost, price, or schedule. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action received by the Contractor before the Contractor will act upon those changes. The Contractor will comply with the changes clause of this contract when the Contractor believes direction has been given from persons other than the Government Contracting Officer
SECTION 01 11 00 Page 16 that equate to a change by notifying the Contracting Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority must be reported to the Contracting Officer.
b. The Contracting Officer Representative (COR) is limited to the authorities stated in the COR appointment letter. If a COR is appointed under this contract, they will be appointed by written letter from the Contracting Officer to the Contractor and COR specific to this contract only. COR appointment letters from previous contracts are not valid for this contract. See the Contracting Officer’s Representative clause of this contract.
1.25 Payment
No separate payment will be made for as-built drawings required under this contract, and all costs accrued in connection with such drawings are considered a subsidiary obligation of the Contractor.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 11 00 Page 17
EXISTING CONDITION PHOTOS
BREAKWATERS AT ISLES OF SHOALS
BREAKWATER 1 (BW-1), ISLES OF SHOALS, NH/ME
PHOTO 1.1 – IN GOSPORT HARBOR LOOKING SOUTH AT SOUTHWEST END OF BW-1 AT STAR ISLAND PHOTO 1.2 – IN GOSPORT HARBOR LOOKING SOUTH AT SOUTHWEST END OF BW-1 AT STAR ISLAND
PHOTO 1.3 – IN GOSPORT HARBOR FACING SOUTHEAST JUST NORTHEAST OF PHOTO 1.2 PHOTO 1.4 – IN GOSPORT HARBOR FACING SOUTHEAST JUST NORTHEAST OF PHOTO 1.3
PHOTO 1.5 – IN GOSPORT HARBOR FACING SOUTHEAST JUST NORTHEAST OF PHOTO 1.4 PHOTO 1.6 – IN GOSPORT HARBOR FACING NORTHEAST TOWARDS NORTHEAST END OF BW-1 AT CEDAR ISL
PHOTO 1.7 – AT SOUTHWEST END OF BW-1 FACING NORTHEAST TOWARDS CEDAR ISL PHOTO 1.8 – AT NORTHWEST END OF BW-1 FACING SOUTHWEST TOWARDS STAR ISL
PHOTO 1.9 – ON BW-1 AT APPROX. STA 7+20 FACING NORTHEAST TOWARDS CEDAR ISLAND PHOTO 1.10 – AT SOUTHWEST END OF BW-1 ON SEAWARD SIDE FACING SOUTHWEST TOWARDS STAR ISL
PHOTO 1.11 – AT NORTHEAST END OF BW-1 ON GOSPORT HRB SIDE FACING NORTHEAST TOWARDS CEDAR ISL PHOTO 1.12 – ON SEAWARD SIDE OF BW-1 FACING SOUTHWEST TOWARDS STAR ISLAND
BREAKWATER 2 (BW-2), ISLES OF SHOALS, NH/ME
PHOTO 2.1 – IN GOSPORT HARBOR LOOKING EAST AT SOUTHEAST END OF BW-2 AT CEDAR ISL PHOTO 2.2 – IN GOSPORT HARBOR FACING EAST JUST NORTHWEST OF PHOTO 2.1
PHOTO 2.3 – IN GOSPORT HARBOR FACING EAST JUST NORTHWEST OF PHOTO 2.2 PHOTO 2.4 – IN GOSPORT HARBOR FACING EAST JUST NORTHWEST OF PHOTO 2.3
PHOTO 2.5 – IN GOSPORT HARBOR FACING EAST JUST NORTHWEST OF PHOTO 2.4 PHOTO 2.6 – IN GOSPORT HARBOR FACING EAST JUST NORTHWEST OF PHOTO 2.5
PHOTO 2.7 – IN GOSPORT HARBOR FACING EAST JUST NORTHWEST OF PHOTO 2.6 PHOTO 2.8 – IN GOSPORT HARBOR FACING EAST JUST NORTHWEST OF PHOTO 2.7
PHOTO 2.9 – IN GOSPORT HARBOR FACING NORTHEAST JUST NORTHWEST OF PHOTO 2.8 PHOTO 2.10 – IN GOSPORT HARBOR LOOKING NORTHEAST AT NORTHWEST END OF BW-2 AT SMUTTYNOSE ISL
PHOTO 2.11 – IN GOSPORT HARBOR LOOKING NORTHEAST AT NORTHWEST END OF BW-2 AT SMUTTYNOSE ISL PHOTO 2.12 – ON CEDAR ISL AT SOUTHEAST END OF BW-2 FACING NORTH TOWARDS SMUTTYNOSE ISL
PHOTO 2.13 – ON CEDAR ISL AT SOUTHEAST END OF BW-2 FACING NORTHWEST TOWARDS SMUTTYNOSE ISL PHOTO 2.14 – ON BW-2 AT APPROX. STA 5+00 FACING SOUTHEAST TOWARDS CEDAR ISL
PHOTO 2.15 – ON BW-2 AT APPROX. STA 5+10 FACING NORTHWEST TOWARDS SMUTTYNOSE ISL PHOTO 2.16 – AT SOUTHEAST END OF BW-2 FACING NORTHWEST TOWARDS SMUTTYNOSE ISL
BREAKWATER 3 (BW-3), ISLES OF SHOALS, NH/ME
PHOTO 3.1 – IN GOSPORT HARBOR FACING NORTHEAST TOWARDS HALEY COVE AND BW-3 PHOTO 3.2 – ON SMUTTYNOSE ISL FACING SOUTHEAST TOWARDS HALEY COVE’S ENTRANCE
PHOTO 3.3 – ON SMUTTYNOSE ISL AT EAST END OF BW-3 FACING HALEY COVE’S ENTRANCE PHOTO 3.4 – ON SMUTTYNOSE ISL AT EAST END OF BW-3 FACING NORTHWEST TOWARDS MALAGA ISL
BREAKWATER 3 (BW-3), ISLES OF SHOALS, NH/ME
PHOTO 3.5 – ON SMUTTYNOSE ISL AT EAST END OF BW-3 FACING NORTHWEST TOWARDS MALAGA ISL PHOTO 3.6 – ON MALAGA ISL AT WEST END OF BW-3 FACING EAST TOWARDS SMUTTYNOSE ISL
PHOTO 3.7 – ON MALAGA ISL AT WEST END OF BW-3 FACING NORTHEAST TOWARDS GULF OF MAINE PHOTO 3.8 – ON MALAGA ISL AT WEST END OF BW-3 FACING EAST TOWARDS SMUTTYNOSE ISL
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
1.2 JOB PAYMENT ITEMS
1.3 UNIT PRICE PAYMENT ITEMS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-07 Certificates
Weight Scales ; G, RO
For all weight scales used to weigh materials brought to the site for incorporation in this project, Certificates of Calibration Testing shall be provided by the Contractor.
SD-11 Closeout Submittals
Weight Slips ; G, RO
The Contractor shall submit the original weight slips signed by the stone supplier's representative for each load of stone brought to the site for use on the project.
1.2 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items. Submit originals of all field notes and all other records relating to Quantity Surveys.
1.3 BIDDING SCHEDULE - PAYMENT ITEMS
Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are
SECTION 01 22 00 Page 2 described below. All costs for items of work, which are not specifically mentioned to be included in a particular Bidding Schedule job or unit price payment item, shall be included in the listed item most closely associated with the work involved.
BASE BID ITEMS:
a. Item Number 0001, "Mobilization and Demobilization".
All costs for labor, equipment, and materials for mobilization and demobilization, as defined in Special Contract Requirements clause "
PAYMENT FOR MOBILIZATION AND PREPARATORY WORK (JAN 1997) DFARS
252.236-7004".
Unit of Measure: Job.
b. Item Number 0002, "Breakwater 1 - Furnish and Install New Armor Stone (Star Island to Station 7+25)".
The work required under Item Number 0002 will be paid for at the contract price per ton to furnish, deliver, and install new armor stone of the specified size along the breakwater to obtain the required interlocking placement, crest elevations and grades, and side slopes as shown on the Contract Drawings, and as specified in Section 35 31 19 BREAKWATER REPAIRS and other appropriate sections of the specifications. The price shall include all plant, supervision, labor, materials, quality control, safety, and equipment incidental to the completion of this item. Significant excavation, removing, stockpiling, and resetting of existing armor stone will be required to install new armor stone and repair the breakwater. Work under these items also includes incidental work as specified in Section 35 31 19 BREAKWATER REPAIRS under paragraph titled "REHANDLING OF STONE." The price shall include all plant, supervision, labor, materials, quality control, safety, and equipment incidental to the completion of this item.
The total amount of material to be paid for under this item shall be measured by the installed ton as indicated by weight slips from the quarry or other source of the stone and shown to be installed within allowable construction tolerances on the as-built cross sections as per Section 01 71 23 FIELD ENGINEERING, paragraph "AS-BUILT CROSS-SECTIONS." Certificates of calibration for weight scales used to weigh armor stone brought to the site for incorporation in this project shall be provided by the Contractor. The Contractor shall weigh each load of armor stone brought to the site, using certified weight scales at the stone supplier's facility, and shall provide to the Contracting Officer the original weight slips signed by the armor stone supplier's representative for each load. These signed weight slips and as-built cross-sections shall be used as a basis of payment for this item.
Armor stone rejected for use shall be removed from the site by the Contractor at the Contractor's expense. Rejected armor stone shall be weighed using the certified weight scales at the stone supplier's facility. Original weight slips, signed by the stone supplier's representative, for the rejected armor stone shall be submitted for each load of rejected armor stone. The weight of rejected armor stone shall be deducted from payment due the Contractor.
SECTION 01 22 00 Page 3
Once production of the breakwater repairs begin, the Contractor shall submit as-built cross-sections in accordance with Section 01 71 23 FIELD ENGINEERING, paragraph "AS-BUILT CROSS-SECTIONS." The as-built cross-sections will be used as a method for verifying armor stone is placed within required tolerances prior to payment. Stones located outside of the pay limits and construction tolerances will not be paid for. As-built sections shall include estimated tonnage installed within the reach of work the sections represent.
Unit of Measure: Ton.
c. Item No. 0003, "Retrieve and Install Existing Displaced Armor Stone at Breakwater 1."
The work required under Item Number 0003 will be paid for at the contract unit price for retrieving existing armor stone located on the harbor side of Breakwater 1 and installing them within the repair areas for Breakwater 1 as shown on the Contract Drawings, and as specified in Section 35 31 19 BREAKWATER REPAIRS and other appropriate sections of the specifications. The price shall include all plant, supervision, labor, materials, quality control, safety, and equipment incidental to the completion of this item.
Unit of measure: EA.
OPTION ITEMS:
d. Item Number 0004, "Breakwater 2 - Furnish and Install New Armor Stone".
e. Item Number 0005, "Breakwater 3 - Furnish and Install New Armor Stone".
The work required under Item Numbers 0004 and 0005 will be paid for at the contract price per ton to furnish, deliver, and install new armor stone of the specified size along the breakwater to obtain the required interlocking placement, crest elevations and grades, and side slopes as shown on the Contract Drawings, and as specified in Section 35 31 19 BREAKWATER REPAIRS and other appropriate sections of the specifications. The price shall include all plant, supervision, labor, materials, quality control, safety, and equipment incidental to the completion of this item.