AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment is necessary to respond to questions from industry and to provide a revised Statement of Work.
Closing is extended until December 17, 2021 at 5:00 PM Eastern.
1. CONTRACT ID CODE PAGE OF PAGES
1 21
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 02-Dec-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ22Q0015
X 9B. DATED (SEE ITEM 11)
23-Nov-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02-Dec-2021
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
Sheila.M.Winston@usace.army.milEMAIL:978-318-8159TEL:
SHEILA M WINSTONVINCUILLA / CHIEF, CONTRACTING DIVISION
W912WJ22Q0015
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
REQUEST FOR INFORMATION
Question 1: The requested amount of 8ft strip fixtures to be installed is 31, but the existing amount of 8ft strip fixtures is only 9. Where will these additional strip fixtures be installed?
Answer: Please see the revised Statement of Work. Total existing light fixtures have been updated to 135 and existing locations of all of these have been identified. All 135 are to be replaced in the current locations.
Question 2: Would leaving the light fixtures in place and just using LED replacement bulbs be an option?
Answer: No, existing fixtures should be replaced, including bulbs.
Question 3: Do all of the light fixtures have to be made in the USA? Lead time for some of the fixtures are into february before we could get our hands on them. Is this an issue with the start and finish deadline?
Answer: All products must comply with Buy America. The Period of Performance has been revised to 150 days after Notice to Proceed.
Question 4: Could we be able to also work on weekends for this project?
Answer: No, hours are from 7:00- 3:30pm Monday through Friday. Work outside of these hours must be coordinated with and approved by the Techincal Point of Contact. There is no guarantee that staff will be available or permitted to work on weekends to accommodate the awarded Contractor.
Question 5: Also I noticed the specs for the lights if the lumen count is within 200 lumen would that be acceptable?
Answer: The specifications identify the minimum lumens required. Lower lumens are not acceptable.
Question 6: Can ceiling heights be provided on the rooms?
Answer: Ceiling heights are as follows:
Tully Park Office: Drop ceilings, 8 ft
Sign Shop: 11 ft
Basin Office: 8 ft
Basin Office Garage: 8 ft
Tully Gate House: 25 ft
Birch Hill Dam Gate House: 30 ft
Birch Hill Dam Utility Building: Drop ceilings, 8 ft. In cold bays, 12 ft
Birch Hill Dam Garage: 12 ft Question 7: Is there a location on site where we could drop ship the light fixtures?
Answer: The contractor is able to have fixtures/bulbs delivered to the site, however, the Contractor must be on site to receive and place fixtures/bulbs in the locations in which they are to be installed. The Government will not accept delivery of fixtures/bulbs for the Contractor, and there is not space available to store all 135 fixtures/bulbs in one location.
Question 8: Is a payment bond required?
Answer: A payment bond is required if the awarded Purchase Order is over $35,000. Payment bond will be required to be submitted within 10 days of contract award.
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 08-Dec-2021 05:00 PM to 17-Dec-2021 05:00 PM.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
STATEMENT OF WORK
LIGHT UPGRADES
U.S. ARMY CORPS OF ENGINEERS
TULLY LAKE AND BIRCH HILL DAM
ROYALSTON, MA
Statement of Work
I. General
1. Scope of work
The contractor shall provide all material, labor, and equipment needed to remove and dispose of existing lighting fixtures and bulbs and install new LED light fixtures and bulbs, install standard rocker switches and motion detection switches at Tully Lake and Birch Hill Dam.
2. Location
Tully Lake is located at 2 Athol-Richmond Road, Royalston, MA.
Birch Hill Dam is located at 68 Birch Hill Dam Road, Royalston MA.
3. Technical Point of Contact The Technical Point of Contact for this contract will be Park Ranger Hannah Speranza.
Park Ranger Speranza can be reached by phone at 978-318-8361 or by email:
Hannah.M.Speranza@usace.army.mil
4. Site Visit An appointment can be made by contacting the Technical Point of Contact, Park Ranger Hannah Speranza. Site visits are generally scheduled between 7:00am and 3:30pm Monday through Friday, holidays excluded. A site visit is highly recommended for this contract.
5. Schedule
Work shall commence within 14 days after the Contractor receives the Notice to Proceed.
The work shall be completed and ready for use no later than 150 days after Notice to Proceed. The Government shall be given 7 days notice prior to the start of work. The project area will be open to the contractor Monday through Friday 7:00 AM to 3:00 PM and all work must be done during those hours unless additional hours are approved by the Technical Point of Contact.
6. Safety Requirements All work shall be conducted in accordance with the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration, federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed at the project office or electronically at Headquarters USACE website under publications using the following link:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_3 85-1-1.pdf
Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.
a. Accident Prevention Plan:
The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include Activity Hazard Analyses (AHAs) as described below. A non-mandatory, fillable APP template is available upon request.
However, the contractor is permitted to submit their own plan, at a minimum it must meet the requirements of EM 385-1-1, Appendix A.
A preparatory meeting shall be conducted by the prime contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing their subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
b. Activity Hazard Analysis (AHA):
An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work. The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.
Note: As part of the APP and AHAs include site specific COVID-19 monitoring procedures which address, at a minimum, the following elements:
• Procedures for periodic sanitation inspections.
• Procedures for disinfecting project sites in accordance with Centers for Disease Control and Prevention (CDC) guidelines.
• Site specific measures to practice social distancing while working on the project.
• Employee training on the signs, symptoms, and protection measures in accordance with CDC guidelines.
• A list of Personal Protective Equipment (PPE) to be used in accordance with CDC and state guidelines.
c. Emergency Response:
Emergency procedures shall be documented in the Accident Prevention Plan and will include a map with directions to the nearest hospital, emergency contact numbers, and onsite First Aid/CPR responders.
d. Required Personnel:
The Contractor shall designate one employee as the site’s Competent Person (CP) who is responsible for ensuring a safe environment for all employees. The CP shall be present at the project site and report to the contractor’s upper management. The CP is required to have related construction and/or service experience.
When emergency medical services are not accessible within five (5) minutes of the work location and there are two (2) or more workers onsite, at least two (2) employees shall be trained in First Aid and CPR. Minimum qualifications are listed in EM 385-1-1, Section 03.A.02.c.
e. Accident Reporting:
All accidents and near misses shall be investigated by the Contractor. All work-related recordable injuries, illnesses and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $5,000.00, shall be verbally reported to the Technical Point of Contact within four (4) hours of the incident. Serious accidents as described in EM 385-1-1 Section 01.D shall be immediately reported to the Technical Point of Contact. ENG Form 3394 shall be completed and submitted to the Technical Point of Contact within five (5) working days of the incident.
The Contractor shall compile employee work hours (including subcontractors) and forward the total hours to the Technical Point of Contact no later than close of business on the 10th calendar day of the following month. The method of transmission by the prime contractor to the Technical Point of Contact shall be electronically.
7. Electrical:
a. General: All electrical work shall comply with EM 385-1-1 (Sections 11 & 12) and applicable National Electrical Safety Code (NESC), National Electric Code (NEC), National Fire Protection Association (NFPA), and OSHA regulations. In the circumstance there is a discrepancy between the codes and regulations listed above, the most stringent shall apply.
b. Qualified Person: Electrical work shall be performed by a Qualified Person (QP) with verifiable credentials who are familiar with applicable code requirements.
Verifiable credentials consist of State, National and/or Local Certifications or Licenses that a Master or Journeyman Electrician may hold, depending on the work being performed, and should be identified in the appropriate AHA.
Journeyman/Apprentice ration shall be in accordance with State, Local and Federal requirements applicable to where the work is being performed.
c. All electrical wiring and equipment shall be a type listed by a nationally recognized testing laboratory for the specific application for which it is to be used. Appropriate PPE will always be worn and/or utilized and adequately match the level of associated risk.
d. Emergency Procedures and Training. Employees exposed to shock hazard and those employees responsible for taking action in case of emergency shall be trained in accordance with EM 385-1-1 Section 03.A, OSHA 29 CFR 1910.151, and NEPA 70E 110.2c. The training shall include methods to release of victims from contact with exposed energized electrical conductors or circuit parts. Employees shall be regularly instructed in methods of first aid and emergency procedures, such as approved methods of resuscitation.
e. All equipment and circuits to be worked on shall be de-energized before work is started. Personnel shall be protected by a Hazardous Energy Control Program (HECP) and procedures in accordance with EM 385-1-1, Section 12. Positive means shall be provided for rendering controls or devices inoperative while repairs or adjustments are being made to the machines they control.
f. If work MUST be performed on an energized system, then the employer must first demonstrate that de-energizing introduces additional or increased hazards or is infeasible due to equipment design or operational limitations (i.e., testing, troubleshooting, etc.).
g. Energized work may never be performed without prior authorization. Once it has been determined that equipment must be worked on in an energized condition, an energized work permit shall be submitted to the Technical Point of Contact for acceptance. > See NFPA 70E and EM 385-1-1, Section 11.A.02.c for permit requirements.
8. Fall Protection
a. General: The requirements of this section are applicable to contractors when their employees are working at heights above 6 feet, exposed to fall hazards, and/or using fall protection equipment. Every Contractor is responsible for establishing, implementing, and managing a fall protection program in accordance with EM 385-1- 1, Section 21.
b. Submittals: A site-specific Fall Protection and Prevention Plan is required to be submitted and approved by the Technical Point of Contact prior to any work being completed at heights. USACE will provide a non-mandatory, fillable template plan.
However, the contractor is permitted to submit their own plan, at a minimum it must address the items listed in EM 385-1-1, Section 21.D.01:
i. Duties and responsibilities. Identify CPs and QPs and their responsibilities and qualifications;
ii. Description of the project or task performed;
iii. Training requirements to include safe use of fall protection equipment;
iv. Anticipated hazards and fall hazard prevention and control;
v. Location of anticipated anchorages that will be installed during the project;
vi. Rescue plan and procedures;
vii. Design of anchorages/fall arrest and horizontal lifeline systems:
viii. Inspection, maintenance and storage of fall protection equipment;
ix. Incident investigation procedures;
x. Evaluation of program effectiveness;
xi. Inspection and oversight methods employed
NOTE: It is realized that means of fall protection for the first person establishing anchorages can be difficult. In this situation, fall protection may not be required while the individual is installing the initial anchorage point. Once this is installed, fall protection is required. These activities need to be addressed in the AHA and Fall Protection and Prevention Plan.
c. Competent Person (CP): The person designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment, is capable of identifying, evaluating and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards. The CP shall:
i. Be onsite at all times while work at height is being performed;
ii. Be trained in accordance with EM 385-1-1, Section 21.C.04, to include a minimum of 24
iii. hour CP in fall protection training made up of classroom and practical hands-on components.
iv. Prepare, update, review and approve fall protection and prevention plans;
v. Review procedures as workplace activities change to determine if additional practices, procedures or training need to be implemented;
vi. Supervise the selection, use and inspection of non-certified anchorages;
vii. Verify End Users who work at heights are trained and authorized to do so;
viii. Inspect fall protection equipment at the frequency required by the manufacturer and EM 385-1-1.
d. Qualified Person (QP): A person with a recognized degree, or professional certificate, with extensive knowledge, training and experience in the fall protection and rescue field who is capable of designing, analyzing, evaluating and specifying fall protection and rescue systems. The QP shall:
i. Be trained to the applicable level, as described in EM 385-1-1, Section 21.C.03;
ii. Provide technical support for the fall protection program;
iii. Have advanced understanding and knowledge of the requirements, equipment, systems, physical sciences, and engineering principles that affect fall protection and rescue systems;
iv. Supervise the selection and inspection of certified anchorages and horizontal lifelines;
v. Be qualified to select proper fall protection and rescue equipment;
NOTE: CPs may only approve non-certified anchorages that are capable of holding 5000 lbs. All other anchorages and horizontal lifelines must be certified by a QP
e. End User: A person who has been trained and authorized by the employer on the use of assigned fall protection equipment in a typical fall hazard situation. They must have an understanding of workplace activities and follow the policy, procedures, and instructions of the Competent Person regarding the use of fall protection, rescue systems, and related equipment. They shall:
i. Be trained by a CP in accordance with EM 385-1-1, Section 21.C.05, to include hands-on training and practical demonstrations
ii. Bring all unsafe or hazardous conditions or actions that may cause injury to them or others, to the attention of the CP;
iii. Properly use, inspect, maintain, store and care for their fall protection equipment and systems;
iv. Inspect all fall protection equipment or damage or defects, prior to each use.
v. Understand the nature of fall hazards in the work area and how to properly mitigate them;
vi. Calculate free fall distances and clearance requirements of fall protection systems;
vii. Understand the site-specific rescue procedures;
f. Personal Fall Arrest System Requirements (PFAS): All PFAS shall meet the requirements contained in ANSI Z359, Fall Protection Code, to include fall restrain and positioning systems. A PFAS consist of a full body harness, connecting means, and an anchorage system. General this equipment is certified for users within the capacity range of 130 to 310 lbs., including the weight of the worker, equipment, and tools. A CP shall inspect the equipment at least once semi-annually and whenever the equipment is subject to a fall or impact.
i. Full body harnesses shall meet the requirements of ANSI Z359 and be used in accordance with EM 385-1-1, Section 21.I.06. Body belts and full body harnesses meeting only the requirements of the ANSI A10.14 shall not be used.
All full body harnesses shall be equipped with Suspension Trauma Preventers such as stirrups, relief steps, or similar in order to provide short-term relief from the effects of orthostatic intolerance.
ii. All energy free fall energy absorbing lanyards shall meet the requirements of ANSI Z359.13 and be used in accordance with EM 385-1-1, Section 21.I.07.
NOTE: When an anchor point is below the dorsal D-ring, a free fall (FF) distance greater than 6 ft (1.8 m) is created. For these situations, a 12 ft (3.6 m) FF energy absorbing lanyard shall be used in accordance with manufacturer’s instructions and recommendations. A 12 ft (3.6 m) FF energy absorbing lanyard does not refer to the lanyard length. Instead it refers to a FF that is greater than 6 ft (1.8 m) up to 12 ft which is created by the anchor point being located below the dorsal D-ring. The maximum length of the lanyard used shall not exceed 6 ft. (See Figure 21-4 in the EM 385-1-1.
Self-Retracting Devices (SRDs) shall meet the requirements of the ANSI/ASSE Z359.14 standard and be used in accordance with EM 385-1-1, Section 21.I.07.d
All scaffolding, aerial work platforms, scissor lifts, or similar must be used in accordance with EM 385-1-1, Section 22.
9. Preconstruction Conference Prior to the start of any work, the Technical Point of Contact will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Preconstruction conference the contractor shall provide the name of the project superintendent with a telephone number for project coordination.
The following is a general list of items for discussion during this Preconstruction Conference:
a. Authority of the Technical Point of Contact and Quality Assurance Inspectors.
b. Contractor’s Safety Program (including sub-contractors).
c. Accident Prevention Plan (Submitted & accepted prior to start of work on site)
d. EM 385-1-1 Fall Protection Requirements
e. Weekly Safety Meetings (Documented on NED Form 251)
f. Accident Reporting (ENG Form 3394)
g. Safety Data Sheet (SDS) requirements
h. Correspondence, Communication and Administrative Procedures.
i. Invoice and payment.
10. Permits
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.
11. Security The contractor will comply with all established security policies at Tully Lake and Birch Hill Dam. Due to periods of heightened security that may affect the access to the areas covered under this contract, the Government reserves the right to close any property or portion of property and reschedule and/or cancel any subsequent work. The Contractor shall be given at least 24 hour notice of any such closure.
12. Contractor Personnel
a. Minimum Personnel Requirements The Contractor shall provide an adequate number of fully qualified personnel to perform the specified work properly and efficiently within the time limits specified.
The Contractor shall provide a list of the names and contact phone numbers for all employees prior to them working on Government Property.
b. Employee Conduct
The Contractor shall be responsible for seeing that the firm’s employees strictly comply with all CFR 36 Rules and Regulations, Federal, State, and Municipal laws.
Any personnel activity, which, in the opinion of the Government, is deemed detrimental to the performance of the contract may result in the removal of Contractor employee/employees.
Examples of unbecoming actions or conduct include but are not limited to the following:
i. Cursing, harassment, or discrimination of and/or unwarranted physical contact with visitors, Corps personnel, or other contractors.
ii. Recurring written and/or verbal complaints from visitors, Corps personnel, or other contractors.
iii. Unsafe operation of vehicles while on US Army Corps of Engineers property.
c. Removal of Contractor’s Employees
The Technical Point of Contact may require the Contractor to immediately remove from the work site any employee of the Contractor or subcontractor, who, in the opinion of the Technical Point of Contact, is incompetent, who endangers persons or property, or whose physical or mental condition is such that it would impair the employee’s ability to satisfactorily perform assigned work. Notification to the Contractor shall be promptly made in writing if time and circumstances permit.
Otherwise, notification shall be verbal or by telephone, and shall be confirmed in writing as soon as possible. No such removal, however, will reduce the Contractor’s obligation to perform all work required under this contract, and immediate replacement will be made as required. This requirement shall not be made the basis of any claim for compensation or damages against the United States or any of its officers or agents.
13. Changes to Quantity
The Government reserves the option, should it become necessary, to decrease or increase quantities in any or all designated contract areas. The Government may also, at any time during the duration of this contract, remove any portion of the contract responsibility and delete any subsequent work in the selected area. The Contractor shall be given adequate notification to prepare for either contingency. This decrease or increase will be deducted from or paid for in accordance with the bidding schedule or a negotiated cost. Any increase in quantity must be negotiated with the Contracting Officer. The Contractor shall not perform any additional work until the issuance of a formal modification signed by the Contracting Officer. In addition, the Technical Point of Contact may, on special occasions decide to reschedule work in order to avoid conflict with visitation or unnecessary expense.
The Contractor shall be given at least 24 hours’ notice.
14. Payment
After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. The invoice must also include the company letterhead, and this must match the data that is registered in the System for Award Management (SAM) registry. For jobs greater than 30 days the contractor may request progress payment.
All invoices may be mailed to U.S. Army Corps of Engineers Tully Lake Dam 2 Athol-Richmond Road Royalston, MA 01368
Or Emailed to Hannah.M.Speranza@usace.army.mil
II. Technical Requirements Part 1 General:
1. Summary:
The contractor shall provide all material, labor, and equipment needed to remove and dispose of existing lighting fixtures and bulbs and install new LED light fixtures and bulbs, install standard rocker switches and motion detection switches at Tully Lake and Birch Hill Dam.
The Contractor will verify the quantity and sizes of the bulbs and fixtures with the Technical Point of Contact before purchasing.
A licensed electrician must follow NEC and other applicable building code standards and will be compatible with the existing requirements.
National Fire Protection Association (NFPA) o NFPA 70
National Electrical Code o NFPA 70E Standard for Electrical Safety in the Workplace
2. Submittals
Although the Government technically reviews submissions required by this scope of work, it is emphasized that the Contractor’s work must be prosecuted using proper internal controls and review procedures. The documents identified below must be prepared in accordance with the applicable standards, submitted for review and accepted by the government prior to the commencement of any field activities.
Accident Prevention Plan (APP) including detailed descript of fall protection measures
AHA
Manufacturer’s product data sheets, prior to ordering Manufacturer’s cut sheets for all new and replaced materials Warranty information Operational Test Results – Completion of field work and prior to final payment
3. Lighting Fixtures and Bulbs
Basin Office and Standalone Garage located at Tully Lake
Quantity Existing Fixture Watts
Single Light Bulbs
40.0
Fluorescent 4 ft 32.0W 2 Lamp per fixture
64.0
Restroom Fan/Light
50.0
Tully Lake Gate House
Strip/T8 Fluorescent 8 ft 32.0W 2 Lamp per fixture
128.0
1 Outdoor Flood Lights
150.0
2 Decorative Wall Packs
Tully Lake Park Office and Sign Shop
32.0 8 ft
4 ft 32.0W 4 Lamp per
96.0
Troffer/ T8 Fluorescent 4 ft
4 Lamp
Strip/T12 Fluorescent 4 ft 32.0
75.0
Single Light Bulbs
40.0
Light/Fan
Birch Hill Dam Utility Building and Standalone Garage
Strip/T8 Fluorescent 4 ft 32.0W
64.0
Troffer/ T8 Fluorescent 4 ft
4 Lamp
Light/Fan
Birch Hill Dam Gate House
Strip/T8 Fluorescent 4 ft 32.0W
4. Clean Up
The Contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work in an area, the contractor shall remove any tools, equipment, and materials that are not the property of the government.
Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.
5. Environmental Protection:
Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the contractor at the site, and the site will be inspected/ cleaned on a daily basis. No burning is permissible. Water, air, and land resources shall not be adversely impacted during the course of the work. Storage, fueling and lubrication of equipment and motor vehicles shall be conducted in a manner that affords the maximum protection against spills and evaporation. Storage and usage of lubricants and daily fueling of machinery and equipment shall occur at least 50 feet from any drainage inlets, water bodies (rivers, streams, and lakes), environmentally sensitive areas (wetlands, vernal pools). Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.
6. Sustainability
Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels.
Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.
Furthermore, the United States Department of Agriculture (USDA) designates certain bio-based products for federal procurement and specifies minimum bio based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio based content level. Visit the BioPreferred web site https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml for the complete list of designated products and the associated minimum bio based content level requirements.
As required in clause 52.223-15 Energy Efficiency in Energy-Consuming Products, https://www.acquisition.gov/sites/default/files/current/far/html/52_223_226.html#wp119 4323 the contractor shall only provide products that earn the ENERGY STAR label and meet ENERGY STAR specifications for energy efficiency. The contractor is encouraged to visit http://www.energystar.gov for complete product specifications and updated lists of qualifying products.
As required in clause 52.223-15 Energy Efficiency in Energy-Consuming Products, https://www.acquisition.gov/sites/default/files/current/far/html/52_223_226.html#wp119 4323 the contractor shall only provide products that meet Federal Energy Management Program (FEMP) purchasing specifications for energy efficiency under this contract, as applicable. Covered product categories and the applicable energy efficiency requirements can be found at https://energy.gov/eere/femp/find-product-categories-covered-efficiency-programs.
7. Building Protection
Any involved building or structure, and all of its contents shall be protected from the elements during the duration of this contract. The contractor shall keep on site the means to quickly cover and protect all areas open to the elements during an unforeseen weather related event that could cause damage to the building and or any of its contents during all phases of this contract.
8. Personal Protective Equipment It is the contractor’s responsibility to furnish and supply personnel with the proper personal protective equipment necessary for performing the work.
9. Government Resources The contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, telephone services or other resources.
10. Damage to Government and Private Property The Contractor shall be responsible for restoring any Government facilities or structures damaged as a result of the Contractor’s actions. The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the firm’s operations. The Contractor shall notify the Technical Point of Contact immediately of damage to Government and private property and injury to any person resulting from the Contractors’ operation. Also, the Contractor shall notify the Technical Point of Contact of damage to Government facilities due to vandalism or other causes on the day such damage is first noticed. Trucks and/or trailers will be driven on existing roads only and not across or through park areas to facilities.
11. Omissions:
This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.
12. Quality Assurance:
The contractor is responsible for the quality control of the contract work. The government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.
13. Other Contracts:
The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.
14. Receiving and Storing Materials:
The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods.
Government employees will not receive material or supplies for the contractor and will not be responsible for damage to contractor equipment or material.
Part 2 Products:
The Contractor will provide light fixtures and LED bulbs that meet or exceed the requirements listed below.
Ceiling fixtures, surface, 4 ft, 2 lamp and 4 lamp.
o 3500 K o 27 Watts o 120 Volts o 3400 Lumens (minimum) o White o Projected life of 50,000 hours (minimum)
Ceiling fixtures, round flat panel mount.
o 3000K o 15 Watts o 120 Volts o 950 Lumens (minimum)
Ceiling fixtures, strip, 8ft.
o 4000K o 65 Watts o 120 Volts o 8000 Lumens (minimum)
Flat panel, troffer, 2 x 4 ft.
o 4000K o 50 Watts o 120 Volts o 6400 Lumens (minimum)
Flush mount with exhaust fan.
o 12-inch, quantity 2 o 13-inch, quantity 1 o 4000K o 20 Watts o 120 Volts o 850 Lumens (minimum)
Flood Light Bulb.
o 5000K (minimum) o 30 Watts o 120 Volts o 3600 Lumens (minimum)
Wall Packs.
o Must be LED o Dusk to dawn sensor lights o Black or bronze finish on the metal o Opaque top and bottom o Weather resistant o Minimum size 7” x 12” 4”
These wall packs meet the requirements and are provided for informational reference only:
o Maxim Moon Ray 12” LED Wall Sconce in bronze, with additional photo eye installed by the contractor.
o Kichler 13” LED Wall Light Textured Black, with additional photo eye installed by the contractor.
o The Great Outdoors 1 Light 12” Height LED Outdoor Wall Sconce in Oil
Rubbed Bronze from the Bay View Collection, with additional photo eye installed by the contractor.
Part 3: Execution
All electrical work shall be performed by a licensed electrician in conformance with the applicable sections of NFPA.
Demolition:
Remove and lawfully dispose of existing light fixtures (including bulbs in all fixtures), at Tully Lake and Birch Hill Dam. Install 135 new fixtures and bulbs.
Current light fixtures that are to be replaced shall be installed in the same location as the existing fixtures.
Contractor shall safeguard the usable existing wiring and electrical boxes for re-use if practical with the replacement lights.
Installation:
The Contractor will verify these fixtures and bulbs with the Technical Point of Contact by conducting a site visit.
Install ceiling fixtures and bulbs, surface, 4 ft.
Install ceiling fixtures and bulbs, round, flat panel mount.
Install ceiling fixtures and bulbs, 8 ft.
Install flat panel troffers and bulbs, 2 x 4 ft.
Install 3 flush mounts with exhaust fan. These will fit the current size to match wall opening.
Replace 1 bulb with LED in flood light fixture on front of gatehouse. Remove and discard current wall packs and install 2 decorative wall packs on front side of the Tully Lake Gate House (see informational photo 1).
Install (10) ten motion-activated switches in garage bays at Tully Lake and Birch Hill Dam. Two (2) will be installed at the Tully Lake sign shop, three (3) at the Basin Office, and five (5) will be installed at Birch Hill Dam. These will activate in the space when someone enters the room, or the garage bays open. The recommended location is in the adjacent corner to the entryway, however the final location to be coordinated with the Technical Point of Contact. These will automatically shut off after approximately one minute of inactivity in the space.
Rewire lights in the Sign Shop to ensure all light switches are operational.
Rewire lights to turn on in Birch Hill Dam gatehouse. There is a nonoperational switch that needs to be replaced and/or rewired, adjacent to the entryway. The lights are currently turned on using breaker box (see informational photo 11).
Rewire lights to turn on in Birch Hill Dam standalone garage. There are currently two switches, one is operational, one is nonoperational and needs to be replaced and/or rewired, adjacent to the entryway. The nonoperational lights are turned on using breaker box (see informational photos 12-13).
Remove existing fixtures and switches in the Basin Office basement. Install LED fixtures and bulbs. Install one switch in approximate location of existing switch, ensuring it is operational with the fixtures below. Install one switch adjacent to the bulkhead emergency door (see informational photos 6-7).
Relocate two (2) of the three (3) light switches from the switch panel in the “workshop” of the Tully Lake sign shop and move to the adjacent cold bay (see informational photos 8-10). The wiring for the existing switches may be terminated in accordance with the
NEC.
All new wiring runs shall be secured to the wall or ceiling in accordance with the NEC to prevent a safety and fire hazard.
The Contractor shall perform an operation test of the system at the completion of the installation of the required components with the Technical Point of Contact. All lights, fixtures, and switches will be tested to make sure they operate as specified in the contract.
Contractor shall immediately notify the Technical Point of Contact of any previously unknown damage or unsuitable conditions discovered during any work listed above.
SECTION F - DELIVERIES OR PERFORMANCE
The following Delivery Schedule item for CLIN 0001 has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
90 dys. ANP 1 TULLY LAKE PARK OFFICE
HANNAH SPERANZA
2 ATHOL-RICHMOND ROAD
ROYALSTON MA 01368
978-318-8361 FOB: Destination
961313
To:
CAGE
150 dys. ANP 1 TULLY LAKE PARK OFFICE
HANNAH SPERANZA
2 ATHOL-RICHMOND ROAD
ROYALSTON MA 01368
978-318-8361
961313
The following Delivery Schedule item for CLIN 0002 has been changed from:
CAGE
90 dys. ANP 1 BIRCH HILL DAM PROJ OFC
HANNAH SPERANZA
68 BIRCH HILL DAM ROAD
ROYALSTON MA 01368
978-318-8361
W912WJ
To:
CAGE
150 dys. ANP 1 BIRCH HILL DAM PROJ OFC
HANNAH SPERANZA
68 BIRCH HILL DAM ROAD
ROYALSTON MA 01368
978-318-8361
W912WJ
SECTION I - CONTRACT CLAUSES
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 14 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 days after Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
(End of Summary of Changes)