This document is an abstract of offers for construction services solicited under solicitation number W912WJ22B0004. The U.S. Army Corps of Engineers, New England District is seeking bids for electrical upgrades at Birch Hill and Tully Lake Dams located in Royalston, Massachusetts. The work includes demolishing existing electrical equipment and wiring, installing new exterior generators, non-automatic transfer switches, panelboards, exterior safety fencing and equipment pads, running new interior wiring and conduit, coordinating with the local electric utility to replace pole-mounted transformers, removing old mechanical piping, and installing new mechanical gate actuators. The project is set aside for small businesses with an estimated value between $500,000 to $1,000,000. Three offers were received by the May 5th bid opening date from Midwest Electrical Construction, Inc., Lighting Resources USA, and an unnamed offeror. Bid amounts ranged from approximately $678,132 to $994,156. The abstract evaluates and documents the offers received in response to the solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Vendor_Submit_Offer.pdf | ||
| Amendment 0003.pdf | ||
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| W912WJ22B0004.pdf | ||
| Specs.pdf | ||
| Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES
4/4/2022 5/5/2022 1
4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation. SIGNATURE DATE SIGNED
9. OFFERS
5. PROJECT TITLE (IFB) 8. GOVERNMENT ESTIMATE 1 2
(Check A, B, C and complete D, E, and F) A. OFFEROR A. OFFEROR
A. HIRED LABOR
X B. REASONABLE CONTRACT B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)
100% Small Business Set-Aside (Without Profit)
6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED
(Including Profit)
7A. ITEM
NUMBER 7B. DESCRIPTION OF OFFERED ITEM
7C. EST.
QUANTITY D. UNIT E. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT
Electrical Upgrades Tully Lake Dam 1 JA 392,146.13$ $392,146.13
$428,000.00 $428,000.00 $470,073.00 $470,073.00
Electrical Upgrades Birch Hill Dam 1 JA 250,986.15$ $250,986.15
$424,750.00 $424,750.00 $489,083.00 $489,083.00
Allowance for Electric Utility Activities at Tully Lake Dam 1 JA 27,000.00$ $27,000.00
$27,000.00 $27,000.00 $27,000.00 $27,000.00
Allowance for Electric Utility Activities at Birch Hill Dam 1 JA 8,000.00$ $8,000.00
$8,000.00 $8,000.00 $8,000.00 $8,000.00
ESTIMATED TOTAL AMOUNT $678,132.28 $887,750.00 $994,156.00
W912WJ22B0004
Birch Hill & Tully Lake Dam Electrical Upgrades, Royalston, MA Midwest Electrical Construction, Inc.
Erin E. Bradley Bid Opening OfficerUS ARMY ENGINEER DISTRICT, NEW ENGLAND
696 VIRGINIA ROAD
CONCORD, MA 01742