Amendment_W912WJ21Q0100_0001.pdf
PDF 1 MB Posted
- Attached to
- Sediment Removal, Townshend Lake, Townshend VT
- Solicitation number
- W912WJ21Q0100
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ21Q0100-0003.pdf | ||
| Amendment_W912WJ21Q0100_0002.pdf | ||
| Solicitation_W912WJ21Q0100.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to answ er technical questions. The closing date remains 25 May 2021 at 5:00PM, EST. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-May-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ21Q0100
X 9B. DATED (SEE ITEM 11)
13-May-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-May-2021
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
Sheila.M.Winston@usace.army.milEMAIL:978-318-8159TEL:
SHEILA M WINSTONVINCUILLA / CHIEF, CONTRACTING DIVISION
W912WJ21Q0100
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS AND ANSWERS
1. QUESTION: Can work occur 12 hours per day to increase production per day?
1. ANSWER: Yes with coordination with the TPOC.
2. QUESTION: Can work occur 7 days per week during the excavation window?
2. ANSWER: As noted in the schedule. The contractor must complete excavation activities five
(5) days after drawdown.
3. QUESTION: Where is the staging area for construction equipment? We need to know this if we need to put gravel from there to the work site as specified on Page 12.
3. ANSWER: As stated in bullet #8: Storage Area. “The storage area for use by the Contractor, for work and storage of equipment, materials, and trailers during the life of this contract will be determined at the Preconstruction Conference.” It is up to the contractors discretion on how much gravel they would want to use if any in the transition/storage areas. A few attachments to show potential storage areas are included in this amendment.
4. QUESTION: When is the estimated lake draw down to occur so we can plan accordingly if this is a summer or winter project?
4. ANSWER: This will be a summer project depending on the weather conditions and dry periods.
5. QUESTION: Can the material be temporarily staged in the parking lot prior to hauling to the dump area?
5. ANSWER: No, material will be loaded into trucks and hauled to the dump site.
6. QUESTION: The specs say that 2 days will be given for advance notice of excavation operations. Can this be increased to one week? It will be difficult to coordinate equipment and people within 2 days unless a heads up is given prior to the 2 days.
6. ANSWER: This project has to be done in a 5 day window. Often times the weather stations provide most accurate forecasts within a few days before the week ahead. Once the contract is awarded the TPOC and the contractor will be in communications constantly to allow for mobilization.
7. QUESTION: Can more legible plan drawings be provided as the one provided is unable to be read for important projection such as elevations and contours?
7. ANSWER: Drawings in the solicitation are the only ones on file. We recommend scheduling a site visit.
8. QUESTION: Can the 3” of clean sand for restoration of the swimming beach area be obtained from materials on site or is this to be brought in by truckload?
W912WJ21Q0100
8. ANSWER: It shall be clean beach sand. Not found onsite.
9. QUESTION: Can you provide information on what type of soils are to be dredged? Do you have any borings?
9. ANSWER: Silt, sand, gravel and organic material. There are no borings available.
(End of Summary of Changes)
Potential Equipment Storage Area