Amendment_W912WJ21Q0055_0002.pdf
PDF 477 KB Posted
- Solicitation number
- W912WJ21Q0055
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ21Q0055-0001.pdf | ||
| SOW and Specifications.pdf | ||
| Solicitation_W912WJ21Q0055.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to answ er technical questions. The closing date remains 18 June, 2021 at 5:00PM, EST. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Jun-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ21Q0055
X 9B. DATED (SEE ITEM 11)
24-May-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Jun-2021
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE W912WJ
FACILITY CODECODE
Sheila.M.Winston@usace.army.milEMAIL:978-318-8159TEL:
SHEILA M WINSTONVINCUILLA / CHIEF, CONTRACTING DIVISION
W912WJ21Q0055
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS AND ANSWERS
1. QUESTION: Are GCs to price this project with the timbers as sized in plan sheet S-501? Or as sized per the as-built drawing? Or per the timber sizes currently installed? They differ.
1. ANSWER: Size members as currently installed to be replaced in-kind.
2. QUESTION: Are both the low water and upper horizontal braces connecting pile to pile, above and below the cross bracing at the bent ends to be removed and replaced?
2. ANSWER: Yes.
3. QUESTION: Can you confirm that all fender frame timbers are being removed and replaced on all bents? Are both the inner horizontal members and the outer vertical members being removed and replaced?
3. ANSWER: Yes. All fender frame timbers are to be removed and replaced in-kind.
4. QUESTION: Is the galvanized bolt size correct at 1 1/8” diameter bolts specified for replacement hardware?
4. ANSWER: Yes.
5. QUESTION: Section 06 13 33 Part 2.1.1 of the Contract Specifications for the project that is referenced requires the timbers to be supplied as pressure treated Coastal Douglas Fir Select Structural Grade. Given the small quantities of timbers that will be needed for this project we are having difficulty finding vendors that can supply Douglas Fir that can be shipped from the West Coast in a timely and/or a cost effective manner. Please advise if pressure treated Southern Yellow Pine of an equal structural grade will be allowed as an approved equal.
5. ANSWER: Southern Yellow Pine is acceptable, so long as it has an equal structural grade and the same level of treatment for a saltwater environment, as specified.