Amendment W912WJ20Q0020-0001.pdf

PDF 303 KB Posted

Attached to
Public Waterline Extension, Northfield Brook Lake, Thomaston, CT
Solicitation number
W912WJ20Q0020
Issued by

View the file

Other files

File Type Posted
Amendment W912WJ20Q0020-0003.pdf PDF
Amendment W912WJ20Q00200-002.pdf PDF
Specifications.pdf PDF
Solicitation W912WJ20Q0020.pdf PDF
Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W13G86002415630001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment is necessary to post the Site Visit Attendee List and to respond to questions from industry.

Closing remains March 20, 2020 at 5:00 PM

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Mar-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ20Q0020

X 9B. DATED (SEE ITEM 11)

24-Feb-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Mar-2020

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W912WJ

FACILITY CODECODE

Sheila.M.Winston@usace.army.milEMAIL:978-318-8159TEL:

SHEILA M WINSTONVINCUILLA / CHIEF, CONTRACTING DIVISION

W912WJ20Q0020

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

REQUEST FOR INFORMATION

SITE VISIT ATTENDEE LIST

NAME COMPANY

John Goodson Dayton Construction Co Inc.

Doug Fleming Groundbreaker Dev. Corp.

Terry Fleming Groundbreaker Dev. Corp.

Gary DeRosa John J Brennan Const.

Ed Hellauer Guerra Const.

Dhawal Patel P&S Construction Inc.

M. Pettirri P&S Construction Inc.

Nick Brown Classic Site Solutions Tim Calabrese Edward Paige Corp.

Dan Stoughton Mountain Top Trucking Jordan Kuczenski Schultz Corporation Richard Doughty USACE Amy Charlton USACE Marissa Wright USACE Dan DeFiore USACE Henry Phillips USACE Jennifer Samela USACE

REQUEST FOR INFORMATION

Question 1: What is to be done with the stumps that are left? Can they be left on site?

Answer: The layout of the water line should be such that cutting is minimized to the maximum extent practicable.

Stumps and small brush may be left on site on Government property in a way so as to not impede access to the area.

Question 2: Who is the water supplier? Who is liable for the tap?

Answer: Connecticut Water is the water supplier. It is recommended that contractors contact Connecticut Water to determine who can tap the line. Connecticut Water may indicate that only they can tap and may require payment to tap. These costs should be included in the quote.

Question 3: What are the power boards located on the path from the park up the hill for?

Answer: Power comes from Rt. 254 through the park and terminates at these boards. The power supplies the pumps that are located in the black plastic well.

Question 4: Is the water line location known for the private residence in the vicinty of the tap location?

Answer: The water line location is not known for 560 Michelle Lane. Other utilities may also be located in the area (power).

Question 5: Are there any provisions for ledge for excavation for the water line from along the park entrance road to the restrooms?

W912WJ20Q0020

Answer: The intent is to keep the water line as close to the road as possible. There are no provisions for ledge at this time.

(End of Summary of Changes)