RFI_Amendment_0001.docx
DOCX document 12 KB Posted
- Solicitation number
- W912WJ19R0026
About this file
This document is an amendment to a solicitation providing answers to a Request for Information. The solicitation is for engineering and design services as well as construction phase services for the Massachusetts Institute of Technology Lincoln Laboratory Engineering Prototyping Facility at Hanscom Air Force Base in Lexington, Massachusetts. The successful offeror for the engineering and design portion will be prohibited from competing for the subsequent construction contract in accordance with government regulations. The engineering and design contract will require the selected firm to provide commissioning services during the design phase, while the construction contract will mandate commissioning responsibilities during construction.
RFI Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0002_RFI.docx | DOCX document | |
| Solicitation_Amendment_0001.docx | DOCX document | |
| DD_1391.pdf | ||
| PAST_PERFORMANCE_QUESTIONNAIRE.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Will the successful engineer/designer be prohibited from also competing for the construction phase?
Yes, the awardee on this procurement will be prohibited from competing for the construction portion of the project, in accordance with FAR 9.505-2.
2. Will there be a commissioning need for this project, and will you be issuing a separate RFP for it?
There will be a commissioning need. The AE contract will include a requirement for the AE to provide the design phase commissioning specialist (CxD). The construction contract will require the construction contractor to act as construction Commissioning Specialist for the Construction Phase (CxC).