Fox Point Hurricane Barrier Louver Replacement Federal contract opportunity
Solicitation number
W912WJ19Q0061
Issued by
Department of the Army Corps of Engineers Engineering District New England

About this file

Solicitation

View the file

Other files for this federal contract opportunity

Other files attached to Fox Point Hurricane Barrier Louver Replacement, newest first.
File Type Posted
Amendment_W912WJ19Q0061-0001.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOX POINT HURRICANE BARRIER

DEPT OF PUBLIC WORKS 700 ALLENS AVE

PROVIDENCE RI 02905

TEL: FAX:

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W912WJ19Q0061 12-Mar-2019 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

22-Mar-2019(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

978-318-8281BROOKE A MORGAN

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

W912WJ19Q0061

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Replace 10 Louvers

FFP

The contractor shall provide all materials, equipment, and labor to replace ten existing louvers with fixed and awning type hurricane rated windows, in accordance with the attached Scope of Work.

FOB: Destination

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job Replace 1 Fixed Window

FFP

The contractor shall provide all materials, equipment, and labor to replace one existing window with a fixed hurricane rated window, in accordance with the attached Scope of Work.

NET AMT

QUOTATION INSTRUCTIONS

*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE 52.236-27

ALT I FOR ADDITIONAL INFORMATION.

*PLEASE DIRECT QUESTIONS TO BROOKE MORGAN AT (978) 318-8281 or

BROOKE.A.MORGAN@USACE.ARMY.MIL. ANY INFORMATION RECEIVED AT THE SITE VISIT

WHICH CONFLICTS WITH THIS SOLICITAION SHOULD BE BROUGHT TO THE ATTENTION OF

BROOKE MORGAN. THE SOLICITATION AND RESULTING CONTRACT SHALL BE THE GOVERNING

DOCUMENT IN ALL CASES.

** QUOTES CAN BE FAXED OR E-MAILED TO BROOKE MORGAN AT (978) 318-8207 or

BROOKE.A.MORGAN@USACE.ARMY.MIL. E-MAIL IS THE PREFFERED METHOD.

NOTE 1: In accordance with FAR Part 28.102-1(c), the Contractor will be required to provide one of the following payment protections for all construction contracts greater than $35,000.00 but not greater than $150,000.00.

(i) Payment bond

(ii) Irrevocable letter of credit

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

NOTE 2:

QUOTATION INSTRUCTIONS:

1. If subcontractor will be used for this work, please provide company name and credentials/qualifications:

2. In accordance with FAR Part 52.204-7(b)(1) Contractors must be registered in the System for Award Management (SAM) database (www.SAM.gov) to submit an offer. (Formerly the Central Contractor Registration (CCR) database and the On-Line Representations and Certifications (ORCA).) Any reference to CCR or ORCA in any clause or provision is referring to the www.sam.gov website. Please note that Google and Google Chrome are not supported browsers for SAM registration. Mozilla FireFox, Safari, and Internet Explorer are supported browsers.

NOTE: SAM.gov registration takes approximately 3 weeks (DUNS registration 1-2 business days; CAGE code validation up to 10 business days; IRS validation and overall submission 7-10 business days). It is the contractor’s responsibility to track SAM.gov registration and follow-up with required tasks.

In addition, if you are registering a new entity in SAM.gov, you must provide an original, signed notarized letter stating that you are the authorized Entity Administrator. The Entity Administrator must establish a LOGIN.GOV account using the e-mail address that will be associated with the SAM registration. See https://www.gsa.gov/about-us/organization/federal-acquisition-service/office-of-systems-management/integrated-award-environment-iae/sam-update for additional information.

3. Provide business DUNS number: _______________________________ (phone 800-333-0505 for DUNS).

4. Provide business CAGE code: __________________________________

5. Tax Identification Number: ___________________________________

6. Contractors shall provide completed FAR clause 52.204-8 (Annual Representations and Certifications) found in Section K of this solicitation with their quote, if the Contractors have not completed their annual representations and certifications electronically via the SAM website at www.sam.gov. (See Paragraph 2 above).

7. Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful offeror will be required to submit this document upon award. The APP must be accepted by the Government Designated Authority prior to the preconstruction conference.

POTENTIAL QUOTERS ARE NOTIFIED THAT THE BASIS ON WHICH AWARD WILL BE MADE IS

PRICE ALONE.

ALL RESPONSIBLE SOURCES MAY SUBMIT A RESPONSE WHICH, IF TIMELY RECEIVED, MUST

BE CONSIDERED BY THE AGENCY.

INVOICES SHALL BE SENT TO TECHNICAL POINT OF CONTACT.

Section C - Descriptions and Specifications

SOW

REPLACE LOUVERS

FOX POINT HURRICANE BARRIER

U.S. ARMY CORPS OF ENGINEERS

Providence, RI Statement of Work

February 2019

I. General

1. Scope of work

Furnish all labor, equipment, tools and materials to replace ten existing louvers and one fixed window at the Fox Point Hurricane Barrier located in Providence, RI. New windows shall be hurricane rated with both fixed and awning type windows complete with all frames and hardware components to provide functional windows in accordance with this scope. Work includes demolition, removal and proper disposal or recycling of the existing louvers and windows.

2. Location The work site is within a pump station of the Fox Point Hurricane Barrier located in Providence RI. Access to the site is from 40 Point Street, Providence RI.

3. Site Visit

Contact the Technical Point of Contact to arrange a site visit. The Technical Point of Contact (TPC) for the project is Andrew LaBonte (978-318-8418 or andrew.s.labonte@usace.army.mil).

4. Schedule The work shall be completed within 210 days of notice to proceed. The project area will be open to the contractor Monday through Friday, 8:00 AM to 4:00 PM. All work must be done during these hours unless additional hours are approved by the Technical Point of Contact.

No work shall be done on weekends or Government holidays. Work on the windows shall be properly sequenced to protect the interior of the pump station from weather.

5. Safety Requirements

a. General: All work shall be conducted in accordance with the U.S. Army Corps of

Engineers Safety and Health Requirements Manual (EM 385-1-1, most recent edition), and all applicable OSHA, federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed at the project office or electronically at Headquarters USACE website under publications using the following link:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_3 85-1-1.pdf

b. Accident Prevention Plan: The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include Activity Hazard Analyses (AHAs) for all tasks. Work shall not proceed until the APP has been reviewed and accepted by the Government.

Contractors are responsible to ensure their subcontractors are in compliance with safety requirements. The Contractor shall conduct a safety meeting at the project site on the first day of work, whenever a new activity or phase of work begins, or at least weekly during the progress of work.

c. Activity Hazard Analyses: An AHA shall be submitted for each major phase of work.

The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. Work shall not proceed on a phase of work until the AHAs have been accepted. A preparatory meeting shall be conducted to discuss the AHAs with onsite employees. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

d. Required Personnel: The Contractor shall employ a minimum of one Competent Person (CP) at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO shall be present at the project site and report to the contractor’s upper management. The SSHO is required to have related construction experience and have completed a 10 Hour OSHA training (or more).

e. Accident Reporting: All accidents and near misses shall be investigated by the Contractor and reported to the Technical Point of Contact immediately. ENG Form 3394 shall be completed and submitted within five working days of an incident.

6. Fall Protection

a. A site-specific Fall Protection and Prevention Plan is required as part of the APP.

The Fall Protection part of the APP shall address: Location of anticipated anchorages, Rescue plan and procedures, Fall arrest and horizontal lifeline systems, Inspection and storage of fall protection equipment, and Inspection and oversight methods employed.

b. Workers using fall protection: Workers shall be trained and capable of using fall protection equipment in accordance with the manufactures instructions. Workers shall follow the policy, procedures, and instructions of the Competent Person regarding the use of fall protection, rescue systems, and related equipment. They shall:

i. Be trained by a CP in accordance with EM 385-1-1, Section 21.C.05

ii. Properly use, inspect, maintain, store and care for their fall protection equipment and systems;

iii. Inspect all fall protection equipment or damage or defects, prior to each use.

iv. Understand the site-specific rescue procedures;

c. Personal Fall Arrest System Requirements (PFAS): All components of the PFAS shall meet the requirements contained in ANSI Z359, Fall Protection Code, to include full body harnesses, connectors, lanyards and Self-Retracting Devices.

d. All scaffolding, aerial work platforms, scissor lifts, or similar must be used in accordance with EM 385-1-1, Section 22.

7. Preconstruction Conference

Prior to the start of any work, the Technical Point of Contact will schedule and conduct a “Preconstruction Conference.” The Contractor’s staff responsible for quality and safety on the job site will attend this meeting. This conference will be scheduled for a time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the requirements in terms of safety, quality, communications, inspections and payments. Storage areas for materials, equipment and dumpsters will also be coordinated at this meeting.

8. Permits

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

9. Security

The contractor will comply with all established security policies at the barrier project.

Potential periods of heightened security may affect access to work areas. During periods of heightened security, the Government reserves the right to close any property. The Contractor shall be given at least 24 hour notice of any such closure.

10. Contractor Conduct

The work area is located on Federal property. Contractor and employees must act in a professional manner at all times. Alcohol and firearms are prohibited on project grounds.

11. Payment

After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the proper name of the contractor, invoice date, contract number, dates of service, description of work, and total amount due. Payment for work accepted by the Government will be made within 30 days of receipt of a proper contractor invoice.

Invoices may be mailed to:

US Army Corps of Engineers Cape Cod Canal Field Office P.O. Box 1555 Buzzards Bay, MA 02532 Attn: Andrew LaBonte

Or Emailed to Andrew.s.labonte@usace.army.mil

II. Technical Requirements:

Part 1 General:

Summary:

Furnish all labor, equipment, tools and materials to replace ten existing louvers with hurricane rated window systems each approx. 11-foot in height x 4-foot wide and one existing fixed window approx. 4-foot x 4-foot wide. New windows shall be installed in accordance with the manufactures recommended means and methods to provide fully functional and weathertight new windows for the pump station.

Requests for Information:

Requests concerning the work of this project should be directed to the Technical Point of Contact at the Cape Cod Canal Office at 978-318-8418 or Andrew.s.labonte@usace.army.mil.

Submittals:

Although the Government technically reviews submittals that are required, it is the Contractor’s responsibility to ensure all work is completed in accordance with this scope.

The following submittals must be prepared and submitted for Government acceptance.

Submittals must be accepted by the government prior to the commencement of any field activities.

Product Shop Drawings, design and layout drawings for the replacement window systems. Include details of the frame materials and sizes, anchorage hardware, operating equipment for the awning windows, glass, weather stripping, screens, etc. Include documentation from window manufacturer certifying the window performance as specified herein.

Safety Submittal- Safety Plan with activity hazard analyses that lists potential hazards associated with the louver replacement field work and appropriate measures to mitigate the hazards. Safety Plan shall include expected method for workers to reach exterior of louver and window locations.

Warranty. The Contractor shall submit all applicable warranty documentation for the products installed.

Omissions:

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than fully functional hurricane rated windows.

Quality Control and Quality Assurance:

The contractor is responsible for the quality control of the work. The government has the right to inspect and test all items called for by the contract for Quality Assurance, to the extent practicable at all times and at all places during the term of the contract.

Other Contracts:

The Government has other contract work not related to this contract ongoing at the barrier. The contractor shall fully cooperate with other Contractors and Government employees. The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.

Clean Up:

The Contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials.

Upon completing work, the contractor shall remove all tools, equipment, and materials that are not the property of the government and shall clean up the job site to the satisfaction of the Government.

Access to Pump Station and Receiving and Storing Materials:

Access to the pump station is through property owned by an adjacent power generating facility.

Contractors will need to comply with security guard sign-in and sign-out requirements for access to the pump station. The contractor is responsible for receiving and unloading of delivered materials. The contractor is responsible for protecting any equipment and materials until they are placed in service. Areas for storage of materials and space for dumpsters will be coordinated at the preconstruction meeting. A single bathroom and 120 volt power for hand tools is available inside the pump station at the work site.

Part 2 Materials/Products:

Each of the ten existing louvers, on the upstream side of the pump station, shall be replaced with a set of windows that consists of two fixed windows on top with one awning type window that is operable while standing on the floor of the pump station (each of these windows will be approximately 3.5-feet tall x 4-feet wide). One existing fixed window, on the downstream side of the pump station, shall be replaced with a fixed window of the same size. Dimensions appropriate to fit in the rough openings of existing louver vents and window opening. Rough openings of existing louvers are approximately 11’ in height by 4’ wide. Rough opening of the one fixed window opening is 50 ½” in height by 48” wide. Windows shall have a minimum 10 year glass, parts and labor warranty. Contractor shall verify all dimensions and layout of openings.

New hurricane rated window systems and fixed window shall have the following minimum ratings.

I. Window projection and Integral hinges must open, adjust and lock at least out to 40 degrees

II. Cam lock: Double Cam locks III. Screen: Stainless steel insect screen with wicket IV. Screen Frame: Extruded Aluminum Alloy V. Frame color: Silver anodized

VI. Performance rating minimum of: AW-PG90-AP, 90psf pressure tested VII. Hurricane large missile impact rating minimum level: D

1: Below is an example of an acceptable hurricane rated impact window system that meets all the minimum requirements to replace each of the ten louvers, but the Government will accept will windows that meet the minimum requirements.

EFCO Series 321X Impact Hurricane rated projected and fixed windows

2: Below is an example of an acceptable fixed hurricane rated impact window that meets all the minimum requirements to replace the one fixed window, but the Government will accept will windows that meet the minimum requirements.

EFCO Series 321X Impact Hurricane rated fixed window

The listing of specific product names and manufacturers is to establish a standard of quality, characteristics and features. The contractor may propose windows from an alternate manufacturer that will be considered by the Government. Materials must be accepted by the Government prior to delivery.

Part 3 Execution:

The contractor shall ensure that all submittals have been approved prior to onsite work and shall coordinate the schedule for all onsite work with the Government technical point of contact.

Work includes demolition and removal of ten existing louvers and one fixed window. Removal of the existing louvers and window shall be done by appropriate means that will not damage the building’s brick walls and other equipment in close proximity. The entire frame of each existing louver and window shall be removed. Any damage caused by demolition shall be repaired by the contractor at no additional expense to the government. All existing utilities and equipment shall be protected from damage. Contractor shall ensure that dust from the demolition is contained.

Access to the exterior of louver and window locations will require staging, a man-lift, ladders or other means for workers. Contractor’s shall plan and install all required access equipment.

Installation of temporary anchors to secure access staging is acceptable based on their removal at completion of work. Note there is no vehicular access to the downstream side of the pump station near the one fixed window to be replaced. All access equipment shall be in good working order with all safety devices for fall protection.

New windows shall be installed in accordance with the manufactures recommended means and methods to provide fully functional and weathertight new windows for the pump station. Install windows plumb, level, square and neat. Trim shall be installed that looks neat and professionally finished. Anchorages shall be solid and interface between windows and building walls shall be in accordance with manufactures recommendations. Windows shall be adequately anchored to maintain positions permanently when subjected to normal thermal movement, building movement, and wind loads. Determination of proper perimeter anchors and spacing is the responsibility of the contractor. Use only skilled tradesmen with work done in accordance with approved shop drawings and manufacturers recommendations. Adjust windows for proper operation after installation.

Work shall be done such that no contaminants are released to the environment. Debris and demolition waste shall be cleaned up daily and properly disposed offsite by the contractor in accordance with local, state and federal laws and regulations. Areas for storage of materials and space for dumpsters will be coordinated at the preconstruction meeting.

Work shall be sequenced to minimize time that the openings are without functional replacement windows. The contractor shall provide temporary means to secure all openings overnight if work is not completed in one day. Work shall be sequenced to protect interior space from dust, dirt and weather.

Contractor will install one hurricane window system window first, and ensure window fits correctly and operates properly before proceeding to another louver vent/fixed window.

Contractor will contact technical point of contact to inspect first window installation before proceeding to ensure proper installation.

Although work is not specifically shown or specified, contract shall include miscellaneous items, appurtenances, devices and materials obviously necessary for a sound, secure and complete installation.

Contractor work on the windows shall not impact work by other contractors or Government operations. Contractor shall provide manufacturer’s warranty documents over to the Technical Point of Contact.

For a period of one (1) year from the date of complete installation, the contractor shall provide a warranty for satisfactory performance of the window installation which includes that of the operation of the windows, frame and parts.

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 210 dys. ANP 1 FOX POINT HURRICANE BARRIER

DEPT OF PUBLIC WORKS 700 ALLENS

AVE

PROVIDENCE RI 02905

961503

0002 210 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

961503

Section H - Special Contract Requirements

SECURITY INFORMATION

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the Technical Point of Contact not later than 5 calendar days after the completion of the training.

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the Technical Point of Contact no later than 3 business days after the initial award.

UAI 5152.231-9000

UAI 5152.231-9000 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 199)

(a) This clause does not apply to terminations. See UAI 5152.249-9000, Basis for Settlement of Proposals, and Federal Acquisition Regulation (FAR) part 49.

(b) Allowable costs for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor’s accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor’s accounting records, costs for that equipment shall be based on applicable provisions of Engineer Pamphlet (EP) 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region I. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rated for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization

WAGE RATES

General Decision Number: RI190001 01/11/2019 RI1

Superseded General Decision Number: RI20180001

State: Rhode Island

Construction Types: Building, Heavy (Heavy and Marine) and Highway

Counties: Rhode Island Statewide.

BUILDING CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories) HEAVY, HIGHWAY AND MARINE

CONSTRUCTION PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.60 for calendar year 2019 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.60 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2019. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/04/2019 1 01/11/2019

ASBE0006-006 06/01/2015

Rates Fringes

HAZARDOUS MATERIAL HANDLER

(Includes preparation, wetting, stripping, removal scrapping, vacuuming, bagging & disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems)..............$ 31.63 18.30

ASBE0006-008 09/01/2018

Rates Fringes

Asbestos Worker/Insulator Includes application of all insulating materials, protective coverings, coatings & finishes to all types of mechanical systems.$ 42.38 28.75

BOIL0029-001 01/01/2017

Rates Fringes

BOILERMAKER......................$ 42.42 24.92

BRRI0003-001 06/01/2018

Rates Fringes

Bricklayer, Stonemason, Pointer, Caulker & Cleaner.......$ 38.83 26.75

BRRI0003-002 03/01/2018

Rates Fringes

Marble Setter, Terrazzo Worker & Tile Setter.............$ 37.16 27.66

BRRI0003-003 03/01/2018

Rates Fringes

Marble, Tile & Terrazzo Finisher.........................$ 31.32 26.30

CARP0094-001 06/05/2017

Rates Fringes

CARPENTER (Includes Soft Floor Layer).....................$ 35.28 27.15 Diver Tender.....................$ 36.28 27.15

DIVER............................$ 47.08 27.15

Piledriver.......................$ 35.28 27.15

WELDER...........................$ 36.28 27.15

FOOTNOTES:

When not diving or tending the diver, the diver and diver tender shall receive the piledriver rate. Diver tenders shall receive $1.00 per hour above the pile driver rate when tending the diver.

Work on free-standing stacks, concrete silos & public utility electrical power houses, which are over 35 ft. in height when constructed: $.50 per hour additional.

Work on exterior concrete shear wall gang forms, 45 ft. or more above ground elevation or on setback: $.50 per hour additional.

The designated piledriver, known as the "monkey": $1.00 per hour additional.

CARP1121-002 10/01/2017

Rates Fringes

MILLWRIGHT.......................$ 36.85 27.50

ELEC0099-002 06/01/2018

Rates Fringes

ELECTRICIAN......................$ 39.21 57.24%

Teledata System Installer........$ 29.41 13.10%+14.15

FOOTNOTES:

Work of a hazardous nature, or where the work height is 30

ft. or more from the floor, except when working OSHA-approved lifts: 20% per hour additional.

Work in tunnels below ground level in combined sewer outfall:

20% per hour additional.

* ELEV0039-001 01/01/2019

Rates Fringes

ELEVATOR MECHANIC................$ 51.56 33.705+A+B

FOOTNOTES:

A. PAID HOLIDAYS: New Years Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.

B. Employer contributes 8% basic hourly rate for 5 years or more of service of 6% basic hourly rate for 6 months to 5 years of service as vacation pay credit.

ENGI0057-001 12/01/2018

Operating Engineer: (power plants, sewer treatment plants, pumping stations, tunnels, caissons, piers, docks, bridges, wind turbines, subterranean & other marine and heavy construction work) GROUP 1.....................$ 39.90 25.85+a GROUP 2.....................$ 38.90 25.85+a GROUP 3.....................$ 34.52 25.85+a GROUP 4.....................$ 31.67 25.85+a GROUP 5.....................$ 37.95 25.85+a GROUP 6.....................$ 28.75 25.85+a GROUP 7.....................$ 22.75 25.85+a GROUP 8.....................$ 34.60 25.85+a GROUP 9.....................$ 38.52 25.85+a

a. BOOM LENGTHS, INCLUDING JIBS:

150 feet and over + $ 2.00 180 feet and over + $ 3.00 210 feet and over + $ 4.00 240 feet and over + $ 5.00 270 feet and over + $ 7.00 300 feet and over + $ 8.00 350 feet and over + $ 9.00 400 feet and over + $10.00

a. PAID HOLIDAYS:

New Year's Day, President's Day, Memorial Day, July Fourth, Victory Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day. a: Any employee who works 3 days in the week in which a holiday falls shall be paid for the holiday.

a. FOOTNOTES:

Hazmat work: $2.00 per hour additional.

Tunnel/Shaft work: $5.00 per hour additional.

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

GROUP 1: Cranes, lighters, boom trucks and derricks

GROUP 2: Digging machine, Ross Carrier, locomotive, hoist, elevator, bidwell-type machine, shot & water blasting machine, paver, spreader, graders, front end loader (3 yds.

and over), vibratory hammer & vacuum truck, roadheaders, forklifts, economobile type equipment, tunnel boring machines, concrete pump and on site concrete plants.

GROUP 3: Oilers on cranes.

GROUP 4: Oiler on crawler backhoe.

GROUP 5: Bulldozer, bobcats, skid steer loader, tractor, scraper, combination loader backhoe, roller, front end loader (less than 3 yds.), street and mobile-powered sweeper (3-yd. capacity), 8-ft. sweeper minimum 65 HP).

GROUP 6: Well-point installation crew.

GROUP 7: Utility Engineers and Signal Persons

GROUP 8: Heater, concrete mixer, stone crusher, welding machine, generator and light plant, gas and electric driven pump and air compressor.

GROUP 9: Boat & tug operator.

ENGI0057-002 12/01/2018

Rates Fringes

Power Equipment Operator (highway construction projects; water and sewerline projects which are incidental to highway construction projects; and bridge projects that do not span water) GROUP 1....................$ 34.05 25.85+a GROUP 2....................$ 28.75 25.85+a GROUP 3....................$ 22.75 25.85+a GROUP 4....................$ 29.33 25.85+a GROUP 5....................$ 33.03 25.85+a GROUP 6....................$ 32.65 25.85+a GROUP 7....................$ 28.30 25.85+a GROUP 8....................$ 29.68 25.85+a GROUP 9....................$ 31.63 25.85+a

a. FOOTNOTE: a. Any employee who works three days in the week in which a holiday falls shall be paid for the holiday.

a. PAID HOLIDAYS: New Year's Day, President's Day, Memorial Day, July Fourth, Victory Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day & Christmas Day.

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Digging machine, crane, piledriver, lighter, locomotive, derrick, hoist, boom truck, John Henry's, directional drilling machine, cold planer, reclaimer, paver, spreader, grader, front end loader (3 yds. and over), vacuum truck, test boring machine operator, veemere saw, water blaster, hydro-demolition robot, forklift, economobile, Ross Carrier, concrete pump operator and boats

GROUP 2: Well point installation crew

GROUP 3: Utlity engineers and signal persons

GROUP 4: Oiler on cranes

GROUP 5: Combination loader backhoe, front end loader (less than 3 yds.), forklift, bulldozers & scrapers and boats

GROUP 6: Roller,skid steer loaders, street sweeper

GROUP 7: Gas and electric drive heater, concrete mixer, light plant, welding machine, pump & compressor

GROUP 8: Stone crusher

GROUP 9: Mechanic & welder

ENGI0057-003 12/01/2018

BUILDING CONSTRUCTION

Rates Fringes

Power Equipment Operator GROUP 1....................$ 39.17 25.85+a GROUP 2....................$ 38.17 25.85+a GROUP 3....................$ 37.95 25.85+a GROUP 4....................$ 33.95 25.85+a GROUP 5....................$ 31.10 25.85+a GROUP 6....................$ 37.25 25.85+a GROUP 7....................$ 36.82 25.85+a GROUP 8....................$ 34.14 25.85+a a.BOOM LENTHS, INCLUDING JIBS:

150 ft. and over: + $ 2.00 180 ft. and over: + $ 3.00 210 ft. and over: + $ 4.00 240 ft. and over: + $ 5.00 270 ft. and over: + $ 7.00 300 ft. and over: + $ 8.00 350 ft. and over: + $ 9.00 400 ft. and over: + $10.00

a. PAID HOLIDAYS: New Year's Day, President's Day, Memorial Day, July Fourth, Victory Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day & Christmas Day. a: Any employee who works 3 days in the week in which a holiday falls shall be paid for the holiday.

a. FOOTNOTE: Hazmat work: $2.00 per hour additional.

Tunnel/Shaft work: $5.00 per hour additional.

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

GROUP 1: Cranes, lighters, boom trucks and derricks.

GROUP 2: Digging machine, Ross carrier, locomotive, hoist, elevator, bidwell-type machine, shot & water blasting machine, paver, spreader, front end loader (3 yds. and over), vibratory hammer and vacuum truck

GROUP 3: Telehandler equipment, forklift, concrete pump & on-site concrete plant

GROUP 4: Fireman & oiler

GROUP 5: Oiler on crawler backhoe

GROUP 6: Bulldozer,skid steer loaders,bobcats, tractor, grader, scraper,combination loader backhoe, roller, front end loader (less than 3 yds.), street and mobile powered sweeper (3 yds. capacity), 8-ft. sweeper (minimum 65 hp)

GROUP 7: Well point installation crew

GROUP 8: Heater, concrete mixer, stone crusher, welding machine, generator for light plant, gas and electric driven pump & air compressor

IRON0037-001 09/16/2017

Rates Fringes

IRONWORKER.......................$ 34.89 26.87

LABO0271-001 06/05/2016

BUILDING CONSTRUCTION

Rates Fringes

LABORER

GROUP 1.....................$ 29.20 23.80

GROUP 2.....................$ 29.45 23.80

GROUP 3.....................$ 29.95 23.80

GROUP 4.....................$ 30.20 23.80

GROUP 5.....................$ 31.20 23.80

LABORERS CLASSIFICATIONS

GROUP 1: Laborer, Carpenter Tender, Mason Tender, Cement Finisher Tender, Scaffold Erector, Wrecking Laborer, Asbestos Removal [Non-Mechanical Systems]

GROUP 2: Asphalt Raker, Adzemen, Pipe Trench Bracer, Demolition Burner, Chain Saw Operator, Fence & Guard Rail Erector, Setter of Metal Forms for Roadways, Mortar Mixer, Pipelayer, Riprap & Dry Stonewall Builder, Highway Stone Spreader, Pneumatic Tool Operator, Wagon Drill Operator, Tree Trimmer, Barco-Type Jumping Tamper, Mechanical Grinder

Operator

GROUP 3: Pre-Cast Floor & Roof Plank Erectors

GROUP 4: Air Track Operator, Hydraulic & Similar Self-Powered Drill, Block Paver, Rammer, Curb Setter, Powderman & Blaster

GROUP 5: Toxic Waste Remover

LABO0271-002 06/05/2016

HEAVY AND HIGHWAY CONSTRUCTION

Rates Fringes

LABORER

COMPRESSED AIR

Group 1....................$ 46.63 21.80 Group 2....................$ 36.15 21.80 Group 3....................$ 48.63 21.80

FREE AIR

Group 1....................$ 38.70 21.80 Group 2....................$ 36.15 21.80 Group 3....................$ 40.70 21.80

LABORER

Group 1....................$ 29.20 21.80 Group 2....................$ 29.45 21.80 Group 3....................$ 30.20 21.80 Group 4....................$ 22.70 21.80 Group 5....................$ 31.20 21.80

OPEN AIR CAISSON,

UNDERPINNING WORK AND

BORING CREW

Bottom Man.................$ 35.20 21.80 Top Man & Laborer..........$ 34.25 21.80

TEST BORING

Driller....................$ 35.65 21.80 Laborer....................$ 34.25 21.80

LABORER CLASSIFICATIONS

GROUP 1: Laborer; Carpenter tender; Cement finisher tender;

Wrecking laborer; Asbestos removers [non-mechanical systems]; Plant laborer; Driller in quarries

GROUP 2: Adzeperson; Asphalt raker; Barcotype jumping tamper; Chain saw operators; Concrete and power buggy operator; Concrete saw operator; Demolition burner; Fence and guard rail erector; Highway stone spreader; Laser beam operator; Mechanical grinder operator; Mason tender; Mortar mixer; Pneumatic tool operator; Riprap and dry stonewall builder; Scaffold erector; Setter of metal forms for roadways; Wagon drill operator; Wood chipper operator;

Pipelayer; Pipe trench bracer

GROUP 3: Air track drill operator; Hydraulic and similar powered drills; Brick paver; Block paver; Rammer and curb setter; Powderperson and blaster

GROUP 4: Flagger & signaler

GROUP 5: Toxic waste remover

LABORER - COMPRESSED AIR CLASSIFICATIONS

GROUP 1: Mucking machine operator, tunnel laborer, brake person, track person, miner, grout person, lock tender, gauge tender, miner: motor person & all others in compressed air

GROUP 2: Change house attendant, powder watchperson, top person on iron

GROUP 3: Hazardous waste work within the "HOT" zone

LABORER - FREE AIR CLASSIFICATIONS

GROUP 1: Grout person - pumps, brake person, track person, form mover & stripper (wood & steel), shaft laborer, laborer topside, outside motorperson, miner, conveyor operator, miner welder, heading motorperson, erecting operator, mucking machine operator, nozzle person, rodperson, safety miner, shaft & tunnel, steel & rodperson, mole nipper, concrete worker, form erector (wood, steel and all accessories), cement finisher (this type of work only), top signal person, bottom person (when heading is 50' from shaft), burner, shield operator and TBM operator

GROUP 2: Change house attendant, powder watchperson

GROUP 3: Hazardous waste work within the "HOT" zone

PAIN0011-005 06/01/2018

Rates Fringes

PAINTER

Brush and Roller............$ 33.62 21.05 Epoxy, Tanks, Towers, Swing Stage & Structural Steel.......................$ 35.62 21.05 Spray, Sand & Water Blasting....................$ 36.62 21.05 Taper.......................$ 34.37 21.05 Wall Coverer................$ 34.12 21.05

PAIN0011-006 06/01/2018

GLAZIER..........................$ 37.18 21.05

FOOTNOTES:

SWING STAGE: $1.00 per hour additional.

PAID HOLIDAYS: Labor Day & Christmas Day.

PAIN0011-011 06/01/2018

Rates Fringes

Painter (Bridge Work)...........$ 49.75 21.05

PAIN0035-008 06/01/2011

Rates Fringes

Sign Painter.....................$ 24.79 13.72

PLAS0040-001 06/04/2018

BUILDING CONSTRUCTION

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 34.30 27.05

FOOTNOTE: Cement Mason: Work on free swinging scaffolds under 3 planks width and which is 20 or more feet above ground and any offset structure: $.30 per hour additional.

PLAS0040-002 07/23/2018

HEAVY AND HIGHWAY CONSTRUCTION

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 31.20 22.10

PLAS0040-003 07/02/2018

Rates Fringes

PLASTERER........................$ 35.65 27.40

PLUM0051-002 09/01/2018

Rates Fringes

Plumbers and Pipefitters.........$ 42.04 29.45

ROOF0033-004 12/01/2018

ROOFER...........................$ 36.75 26.12

SFRI0669-001 04/01/2017

Rates Fringes

SPRINKLER FITTER.................$ 43.92 21.49

SHEE0017-002 12/01/2018

Rates Fringes

Sheet Metal Worker...............$ 36.13 35.13

TEAM0251-001 05/01/2018

HEAVY AND HIGHWAY CONSTRUCTION

Rates Fringes

TRUCK DRIVER

GROUP 1....................$ 27.21 25.7525+A+B+C

GROUP 2....................$ 27.36 25.7525+A+B+C

GROUP 3....................$ 27.41 25.7525+A+B+C

GROUP 4....................$ 27.46 25.7525+A+B+C

GROUP 5....................$ 27.56 25.7525+A+B+C

GROUP 6....................$ 27.96 25.7525+A+B+C

GROUP 7....................$ 28.16 25.7525+A+B+C

GROUP 8....................$ 27.66 25.7525+A+B+C

GROUP 9....................$ 27.91 25.7525+A+B+C

GROUP 10....................$ 27.71 25.7525+A+B+C

FOOTNOTES:

A. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day, plus Presidents' Day, Columbus Day, Veteran's Day & V-J Day, providing the employee has worked at least one day in the calendar week in which the holiday falls.

B. Employee who has been on the payroll for 1 year or more but less than 5 years and has worked 150 Days during the last year of employment shall receive 1 week's paid vacation; 5 to 10 years - 2 weeks' paid vacation; 10 or more years - 3 week's paid vacation.

C. Employees on the seniority list shall be paid a one hundred dollar ($100.00) bonus for every four hundred (400) hours worked, up to a maximum of five hundred dollars ($500.00)

All drivers working on a defined hazard material job site shall be paid a premium of $2.00 per hour over applicable rate.

TRUCK DRIVER CLASSIFICATIONS

GROUP 1: Pick-up trucks, station wagons, & panel trucks

GROUP 2: Two-axle on low beds

GROUP 3: Two-axle dump truck

GROUP 4: Three-axle dump truck

GROUP 5: Four- and five-axle equipment

GROUP 6: Low-bed or boom trailer.

GROUP 7: Trailers when used on a double hook up (pulling 2 trailers)

GROUP 8: Special earth-moving equipment, under 35 tons

GROUP 9: Special earth-moving equipment, 35 tons or over

GROUP 10: Tractor trailer

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied…