STAMFORD HURRICANE BARRIER

PO BOX 396 DYKE LANE

STAMFORD CT 06904-0394

TEL: FAX:

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W912WJ18Q0134 20-Aug-2018 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

14-Sep-2018(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

978-318-8814ROBERT C GARRAHAN

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

W912WJ18Q0134

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job SHB Pump Repairs

FFP

Requirement to provide Pump Repair Construction Services for the Stamford Hurricane Barrier located in Stamford CT. All work shall be performed in accordance with the Statement of Work.

FOB: Destination

NET AMT

QUOTATION INSTRUCTIONS

*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE

52.236-27 FOR ADDITIONAL INFORMATION.

PLEASE DIRECT QUESTIONS TO ROBERT C. GARRAHAN AT (978) 318-8814 OR

Robert.C.Garrahan@USACE.Army.mil. THE SOLICITATION AND RESULTING CONTRACT SHALL

BE THE GOVERNING DOCUMENT IN ALL CASES.

QUOTES CAN BE FAXED OR E-MAILED TO ROBERT C. GARRAHAN AT (978) 318-8207 or Robert.C.Garrahan@USACE.Army.mil. E-MAIL IS THE PREFERRED METHOD OF SUBMISSION.

Contractors must be registered in the System for Awards Management at www.SAM.gov (formerly the Central Contractor Registration (CCR) database and the On-Line Representations and Certifications (ORCA) (see DFARS clause 252.204-7004 Alt A). Please note that Google and Google Chrome are not supported browsers for SAM registration. Mozilla FireFox, Safari, and Internet Explorer are supported browsers.

SAM.gov registration takes approximately 3 weeks (DUNS registration 1-2 business days; CAGE code validation up to 10 business days; IRS validation and overall submission 7-10 business days). It is the contractor’s responsibility to track SAM.gov registration and follow-up with required tasks. SAM.gov registration does not have to be “active” to be able to submit a quote. However, contractors must have an active record before a contract award can be made. If SAM.gov registration is not completed in a timely fashion in accordance with the SAM.gov timelines, the Government reserves the right to disqualify the quote in accordance with FAR 52.204-7(d).

Contractors should note that 30 September is the end of the Government fiscal year. As that date approaches, the Government will be unable to delay year-end contract awards and will have to disqualify contractors without an active SAM.gov registration. If you have any questions, please contact the aforementioned point of contact.

Provide DUNS number: ___________________________ (telephone 866-705-5711 for DUNS)

Provide CAGE code: ____________________________

Provide TAX ID: __________________________

Per FAR Clause 52.212-3 Alt I, the Contractor is required to complete the On-line Representations and Certifications Application (www.SAM.gov) and paragraph (b) if applicable, OR to complete paragraphs (c) thru (m) of this clause and return with quote.

Section C - Descriptions and Specifications

SOW

VERTICAL PUMP 2 REHABILITATION

STAMFORD HURRICANE BARRIER

STAMFORD, CONNECTICUT

STATEMENT OF WORK

A. General Description of the Work to be Performed.

The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.

The purpose of this project is to repair vertical pump 2 at the East Branch Pumping Station on the West Abutment of the Stamford Hurricane Barrier. Rehabilitation of the pump assemblies includes but is not limited to:

disassembly, cleaning, inspection, and repair as specified herein. Government furnished shaft and impeller shall be installed.

Pump shall be re-assembled, re-installed, and tested as specified herein. Provide a written inspection report detailing findings, final critical tolerances, work performed, and operations and maintenance recommendations.

1. Project/Site Conditions and Operational Restrictions. The subject pump is a vertical axial flow pump manufactured by Johnston Pumps, model 24PO, rated at 23,000 gallons per minute at 16 feet TDH. Each pump is powered by a 460 Volt General Electric 705 RPM, 125 hp w/1.15 Service Factor electric motor. Manufacturer’s Operation and Maintenance manuals for both the pumps and the motors are available on site.

The pumps were last rehabilitated in September 2012. For both pumps, the major items included in the 2012 rehabilitation consisted of: cleaning, inspection and repair of the motors including new motor bearings and re-winding the motors. The pumps assemblies were cleaned inspected, recoated and repaired to include new bearing temperature sensor with temperature readout and alarm system.

While work is being done on pump 2, pump 1 shall remain operational at all times.

In the event that it becomes necessary to operate the hurricane barrier for flood risk management purposes, the Contractor will be given a minimum of 12 hours advance notice. Upon such notification, the Contractor shall suspend construction operations, and take such other actions and perform such additional work as directed by the Contracting Officer's Representative to prepare the barrier for flood risk management operations.

If the Contractor wishes to use the existing 3 ton capacity crane, he must have it inspected at his own expense, and provide inspection and testing documentation to the Government prior to its use in accordance with EM 385-1-1, Section 16.D.07.

The Contractor may be required to remove a 2 foot wide metal stairway leading from the operating floor to the mezzanine floor, if work on pump necessitates it.

Operation of the pumps and hurricane barrier for testing of completed work shall be coordinated with the Contracting Officer's Representative and the Project Manager. The Project Manager's approval shall be obtained in advance for all pump operations.

B. General Project Requirements

1. Contractor’s Responsibility. The Contractor shall furnish all plant, labor, equipment and materials and carry out all operations as necessary to accomplish the work of this project as described in this document.

2. Commencement, Prosecution and Completion of Work. The Contractor shall commence work under this contract within 15 days after the date of receipt of the Notice to Proceed, shall prosecute the work diligently, employing ample personnel and sufficient equipment, and shall complete the entire work ready for use not later than 180 calendar days after the date of contract award. The time included for completion shall include final cleanup of the project site. Additional restrictions concerning the prosecution and completion of work are as follows:

A. The Contractor shall attend a Preconstruction Conference prior to the start of on-site construction work (see paragraph entitled "Preconstruction Conference", below).

3. Superintendence by the Contractor. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.

Failure to comply with these requirements shall be deemed as cause for a non-compensatory stoppage and suspension of work until the deficiency is remedied.

4. Coordination and Direction During Construction. The Contractor shall not take or accept any direction or instructions issued by any person, employed by the Government or otherwise, other than the Contracting Officer that changes the terms and conditions of contract actions, the scope, or any change that impacts the cost, price, or schedule. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action received by the Contractor before the Contractor will act upon those changes.

The Contractor will comply with the changes clause of this contract when the Contractor believes direction has been given from persons other than the Government Contracting Officer that equate to a change by notifying the Contracting Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority must be reported to the Contracting Officer.

The Contracting Officer Representative (COR) is limited to the authorities stated in the COR appointment letter. If a COR is appointed under this contract, they will be appointed by written letter from the Contracting Officer to the Contractor and COR specific to this contract only. COR appointment letters from previous contracts are not valid for this contract.

5. Traffic Regulation and Control. During construction the Contractor shall provide access as necessary to maintain traffic and to provide vehicle access to all residential and commercial structures in the project area. The Contractor shall maintain and protect traffic on all affected roads during the construction period, except as otherwise specifically directed by the Contracting Officer. The traveling public shall be protected from damage to person and property. The Contractor's traffic on roads selected for hauling material to and from the site shall interfere as little as possible with public traffic. The Contractor shall investigate the adequacy of existing roads and the allowable load limit on these roads. The Contractor shall be responsible for the repair of any damage to roads caused by construction operations.

6. Access to the Project Site. Access to the project site is currently available for construction traffic. The presence of a USACE personnel is required for access to the site. The Contractor shall be responsible for providing and maintaining access necessary for his equipment and plant to and from the work site.

7. Construction Site Plan. Prior to the start of work, the Contractor shall submit a site plan showing the locations and dimensions of temporary facilities including layouts and details, equipment and material storage areas, access and haul routes, avenues of ingress/egress to fenced areas (e.g., the assigned storage and staging area), details of the fence installation (if used), and the number of trailers to be used. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas. The plan shall also show where temporary utility hook-ups are to be located, if required, and how grounding of equipment and trailers will be achieved, as appropriate. Any items removed from the property shall be recycled to the furthest extent possible.

8. Hours of Operation. Unless otherwise authorized in writing by the Contracting Officer, the project site will be available for construction activities between 7:00 a.m. and 3:30 p.m. Monday through Friday.

Normal work hours are from 7:00 a.m. through 3:30 p.m., Monday through Friday. The Contractor will not be permitted to work on Saturday, Sunday or legal holidays unless otherwise authorized by the Contracting Officer.

The exclusion of work on Saturday, Sunday and legal holidays has been considered in computing the performance time of this contract. The following legal holidays are observed:

January 1st Third Monday in January Third Monday in February Last Monday of May July 4th 1st Monday of September 2nd Monday of October 11th of November Fourth Thursday of November 25th of December

When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.

Work outside the normal hours of operation requires Contracting Officer approval. The request to work outside the hours of operation shall be made in writing to the Contracting Officer 10 calendar days prior to such work to allow arrangements to be made by the Government. The request application shall include specific dates, hours, location, type of work to be performed, contract number and project title, and names of all individuals who will be working outside the hours of operations. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.

9. Progress Schedule. The initial project schedule shall indicate the sequence proposed to accomplish each work feature or operation. The schedule shall be cost and resource loaded for contract monitoring and control purposes. Schedules should be established using a standard critical path method (CPM), or other industry approved standard. Each activity should have an early start/finish date, late start/finish date, task duration, and total float clearly indicated. The schedule shall be prepared to show the starting and completion dates of all work features beginning with date of Notice to Proceed and indicating calendar days to completion. The Contractor shall indicate on the schedule the important work features or operations that are critical to the timely overall completion of the project. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the schedule. This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised. Anticipated adverse weather delay days shall be included in the schedule.

An updated schedule showing actual progress shall be submitted monthly or with each pay request. Changes to the base-line schedule shall be outlined in a narrative describing the reason for the change.

10. Rate of Progress. Should the Contractor fail to maintain a satisfactory rate of progress in accordance with the Contractor's approved progress schedule, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought up to schedule and maintained.

11. Preconstruction Conference. The Contracting Officer will conduct a preconstruction conference after receipt of Notice to Proceed by the Contractor and prior to the start of on-site construction activities. The date, time, and place for this conference shall be mutually agreed upon by the Contractor and the Contracting Officer. It is mandatory that the Contractor's project site supervisory personnel assigned to this project attend the conference; no personnel substitutions will be permitted. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the U.S. Army Corps of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer's Representative will inform the Contractor concerning job safety, project phasing, work hour restrictions, traffic control, quality control, labor relations, and environmental protection. The Preconstruction Conference will be arranged by the Contracting Officer.

12. Material Substitutions. This contract is based on the materials and methods as shown on the contract drawings and as described in this document. The Contractor shall not substitute materials or methods unless such substitution has been specifically approved in writing by the Contracting Officer.

13. Quality Control.

The Contractor shall establish a three phase quality control system (the three phases are described below) to perform sufficient inspection of all items of work, including that of any subcontractors, to ensure conformance to this document with respect to materials, workmanship, construction, finish and functional performance. The system shall cover all construction operations, both onsite and offsite. The site project superintendent will be held responsible for the quality of work on the job and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. The site project superintendent in this context shall be the highest level manager responsible for the overall construction activities at the site, including quality and production. The site project superintendent shall maintain a physical presence at the site at all times, except as otherwise acceptable to the Contracting Officer, and shall be responsible for all construction and construction related activities at the site.

The Quality Control Manager shall be a construction person with a minimum of three years in related work. This Quality Control Manager shall be on the site at all times during construction and shall be employed by the prime Contractor. The QC Manager may also serve as the Site Safety and Health Officer (SSHO) as delineated in Paragraph C4, below, and may have other duties in addition to site safety and health, but may not be the Contractor’s Site Superintendent..

The Contractor shall employ a three phase Quality Control as follows:

Preparatory Phase: This phase is performed prior to beginning work after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:

a. A review of each paragraph of applicable specifications, reference codes, and standards. Maintain and make available in the field for use by Government personnel until final acceptance of the work.

b. Review of the contract documents.

c. Check to assure that all materials and/or equipment have been tested, submitted, and approved.

d. Review of provisions that have been made to provide required control inspection and testing.

e. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.

f. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to contract documents, and are properly stored.

g. Review of the appropriate activity hazard analysis to assure safety requirements are met.

h. Discussion of procedures for controlling quality of the work including repetitive deficiencies

i. Discussion of the initial control phase.

k. The Government must be notified at least 24 hours in advance of beginning the preparatory control phase.

Include a meeting conducted by the Quality Control Manager and attended by the superintendent, other Quality

Control personnel (as applicable), and the foreman responsible for the definable feature, as appropriate to the staffing of the project. Document the results of the preparatory phase actions on the daily Quality Control report.

Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.

Initial Phase: This phase is accomplished at the beginning of a definable feature of work. Accomplish the following:

a. Check work to ensure that it is in full compliance with contract requirements.

b. Verify adequacy of controls to ensure full contract compliance. Verify required control inspection and testing.

c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards.

d. Resolve all differences.

e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.

f. The Government must be notified at least 24 hours in advance of beginning the initial phase

Follow-up Phase: Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the Quality Control documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work.

14. Quality Assurance. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.

The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government. Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.

Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.

The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.

The Contractor shall submit all requests for changes in writing to the Contracting Officer. Do not proceed with changes without possession of written authorization of the Contracting Officer.

The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.

15. Utilities. Water and electricity required in the prosecution of the work shall be available to the Contractor at existing points of supply.

16. Temporary Electrical Equipment and Connections. The Contractor, as needed, and at his own expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. All required temporary electrical equipment and lines shall be furnished, installed, connected, and maintained by the Contractor according to EM 385-1-1, Section 11.E, NFPA 241,and NFPA 70, Article 305-6(b), "Assured Equipment Grounding Conductor Program". All temporary equipment and lines shall be removed prior to final acceptance of the work. Materials and equipment need not be new, but must be in good repair and serviceable condition. Periodic inspections of systems and devices will be made by the Contractor at intervals not to exceed one week.

17. Environmental Protection. The Contractor shall minimize environmental pollution and damage that may occur as the result of construction operations. The environmental resources within the project boundaries and those affected outside the limits of permanent work shall be protected during the entire duration of this contract. Comply with all applicable environmental Federal, State, and local laws and regulations. Any delays resulting from failure to comply with environmental laws and regulations will be the Contractor's responsibility.

A. Environmental Protection Plan: Prior to commencing construction activities or delivery of materials and equipment to the site, the Contractor shall submit an Environmental Protection Plan for review and approval by the Contracting Officer. The purpose of the Environmental Protection Plan is to present a comprehensive overview of known or potential environmental issues which the Contractor must address during construction. Issues of concern shall be defined within the Environmental Protection Plan. The Contractor shall address each topic at a level of detail commensurate with the environmental issue and required construction task(s). The Environmental Protection Plan shall be current and maintained onsite by the Contractor.

B. Obtaining and complying with all environmental permits and commitments required by Federal, State, Regional, and local environmental laws and regulations is the Contractor's responsibility.

C. Temporary Erosion and Sediment Controls: The Contractor shall be responsible for providing temporary erosion and sediment control measures for storage and staging areas and other areas as appropriate for the work, in accordance with Federal, State, and local laws and regulations. The erosion and sediment controls selected and maintained by the Contractor shall be such that water quality standards are not violated as a result of the Contractor's construction activities. The area of bare soil exposed at any one time by construction operations should be kept to a minimum. The Contractor shall construct or install temporary and permanent erosion and sediment control best management practices (BMPs). BMPs may include, but not be limited to, vegetation cover, slope stabilization, silt fences, sediment traps, and inlet and outfall protection. Any temporary measures shall be removed after the area has been stabilized.

D. Fuels and Lubricants: Storage, fueling and lubrication of equipment and motor vehicles shall be conducted in a manner that affords the maximum protection against spill and evaporation. Manage and store fuel, lubricants and oil in accordance with all Federal, State, Regional, and local laws and regulations. Used lubricants and used oil to be discarded shall be stored in marked corrosion-resistant containers and recycled or disposed in accordance with State, and local laws and regulations. Storage of fuel on the project site is not allowed. Fuel shall be brought to the project site each day that work is performed. Storage and usage of lubricants and daily fueling of machinery and equipment shall occur at least 50 feet from any drainage inlets, water bodies (rivers, streams, lakes), environmentally sensitive areas (wetlands, vernal pools).

18. Waste. The Contractor shall provide on-site containers for the collection of demolition debris, waste materials, construction debris, and rubbish. The Contractor shall clean the project site on a daily basis to prevent the accumulation of waste materials and rubbish resulting from construction activities. The Contractor shall transport all solid waste off of the project site and dispose of it in compliance with Federal, State and local requirements for solid waste disposal. Upon completion of the construction work, the project site shall be returned to its pre-work condition.

19. Contract and Informational Drawings. There are no Contract drawings included in this Statement of Work.

Informational drawings are attached at the end of the document to provide the Contractor information on the site and pump locations. The drawings are attached for informational purposes only. The Contractor shall make their own investigations of existing conditions in the field prior to the start of work. The Contractor shall be responsible for any errors which could have been avoided by such investigations.

20. Photographs. Photographs showing the existing conditions of the work area are attached at the end of this document. The photographs are attached for informational purposes only. The Contractor shall make his own investigations of existing conditions in the field prior to the start of work. The Contractor shall be responsible for any errors which could have been avoided by such investigations.

21. Damages. The Contractor shall exercise caution and follow sound construction practices in the conduct of the work to avoid construction-related damage to existing features to remain

22. Sequence of Work. In general, the work shall be performed in the following sequence: existing conditions verification, preparation of submittals, material procurement, establish traffic control and site safety, construct new work, and project close out.

23. Contractor's Receipt of Supplies. The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.

24. Storage Area. The storage area for use by the Contractor, for work and storage of equipment, materials, and trailers during the life of this contract is limited and will be determined at the Preconstruction Conference. The storage area will be located on Federal Property at the Stamford Hurricane Barrier Facility. The Contractor shall confine its storage area to the limits as designated or approved by the Contracting Officer and shall be responsible for the security of the area. Upon completion of the contract, and at no additional cost to the Government, remove all equipment and materials, except as otherwise specified, and restore the site to its original condition as approved by the Contracting Officer.

Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on any given day. Do not stockpile materials outside the storage area in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment within the storage area at the end of each work day.

The Contractor may construct a temporary six foot high galvanized chain link fence around trailers and materials at the storage/staging area if desired. Galvanized chain-link fence shall have a minimum height of six feet. The fence posts shall be driven when installed in earth surfaces; concrete bases placed on the ground surface shall be used when installation is in paved or other hard surfaced areas. Except for equipment and materials which are in support of ongoing work on any given day or unless such equipment or materials are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the project site boundaries, equipment and materials shall be stored and placed inside the temporary chain-link fencing.

Trailers, if utilized by the Contractor for administrative or material storage purposes, shall present a clean and neat exterior appearance and shall be in a state of good repair. Trailers which, in the opinion of the Contracting Officer, require exterior painting or maintenance will not be allowed on the project site.

The temporary six foot high chain link fence, if used, shall be kept in a state of good repair and proper alignment.

Should the Contractor elect to traverse, with construction equipment or other vehicles, grassed or unpaved areas which are not established roadways, such areas shall be covered with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways; gravel gradation shall be at the Contractor's discretion. Grass located within the boundaries of the construction site shall be mowed for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers shall be edged or trimmed neatly.

25. Restoration of Storage Area and Other Areas. Upon completion of the project remove barricades, temporary utilities, sanitation facilities, construction vehicles, materials and equipment, temporary chain-link fencing, and any other temporary equipment, materials, or products from within and around the work areas and temporary storage areas. Clean and repair damage caused by installation or removal of temporary materials, equipment, or utilities.

Areas used by the Contractor for the storage of equipment or material, or other use, shall be restored to the original or better condition, including pavement repair, or top soil and seeding as necessary. Gravel used to traverse grassed areas shall be removed and the area restored to its original condition, including top soil and seeding as necessary.

26. Contractor Use of Premises. Work shall be restricted to the areas of the work described in this document, access routes to the work site, and to storage areas assigned to this Contractor. Access to the project site is currently available for construction traffic. The Contractor shall be responsible for providing and maintaining access necessary for his equipment and plant to and from the work site.

27. Protection and Security. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government. The Contractor shall protect all its personnel, Government personnel, and the general public from injury. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.

28. Damaged Property. Work shall proceed in a manner which will minimize disturbance or risk of damage to structures and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.

The Contractor shall ensure that construction work does not impact structures, or operations at the Stamford Hurricane Barrier, except as required accomplish the repairs and as described in other sections of this Statement of work. The hurricane barrier is of critical importance for flood protection.

29. Contractor's Receipt of Supplies. The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.

30. Sanitary Facilities. In accordance with Section 2 of EM 385-1-1, provide, maintain, and make available to all workers provisions for sanitation. Maintain these provisions at all times without nuisance. Upon completion of the work, all sanitary provisions and facilities shall be removed from the premises by the Contractor, leaving the premises clean and free from nuisance.

In accordance with Section 2, Subpart 02.C of EM 385-1-1, provide, maintain, and make available to all workers an adequate supply of potable water for both drinking and personal cleansing. During hot weather, provide cool drinking water.

In accordance with Section 2, Subpart 02.E of EM 385-1-1, provide, maintain, and make available to all workers adequate minimum field-type portable toilets. Portable toilets shall be properly secluded from public observation in such a manner as required or approved by the Contracting Officer. Periodically empty wastes into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility. Include provisions for pest control and elimination of odors. Any penalties and/or fines associated with improper discharge of wastewater shall be the responsibility of the Contractor. Government toilet facilities will not be provided.

33. Sustainability All reasonable efforts shall be made to use recycled, recovered and biobased materials in the execution of this work. Deliverables shall be printed double-sided on paper that contains post-consumer fiber content. To the extent feasible, materials with recycled content per EPA-Designated Recovered Materials Requirements as described at https://www.epa.gov/smm/comprehensive-procurement-guidelines-construction-products shall be used. Also the Contractor shall meet the USDA-Designated Biopreferred Program requirements at https://biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml as feasible.

C. Safety

1. Accident Prevention Plan: The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include an Activity Hazard Analysis (AHA) as described in Paragraph "2" below. All work shall be conducted in accordance with the APP, the U.S. Army Corps of Engineers Safety and Health requirements Manual (EM 385-1-1, 2014 edition), and all applicable Federal, State, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at Headquarters USACE website under publications using the following link:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

The APP shall detail how safety and health will be managed during the project. The APP format shall follow EM- 385-1-1, Appendix A, Minimum Basic Outline for Accident Prevention Plans. The APP shall address the requirements of applicable Federal, State and local safety and health laws, rules, and regulations. The Contractor shall comply with Federal Acquisition Regulation Clause No. 52.236-13 for Accident Prevention, which is added by reference. Special attention shall focus on the requirements of EM 385-1-1, specifically Section 01.A.11 through 01.A.18, Figure 1-2 AHA, and Appendix A, (Minimum Basic Outline for Accident Prevention Plan). The APP shall be developed by a qualified person. The Contractor shall be responsible for documenting the qualified person’s credentials. Work shall not proceed until the APP has been reviewed by the Government Designated Authority (GDA) and deemed acceptable for use on the project.

The APP shall interface with the Contractor's overall safety and health program. Any portions of the Contractor's overall safety and health program referenced in the APP shall be included in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the "controlling authority" for safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

The Contractor shall conduct a safety meeting at the project site on the first day of work, whenever a new activity or phase of work begins, or at least weekly during the progress of work. All safety meetings shall be documented. A copy of a suggested weekly safety meeting form will be provided by the Contracting Officer’s Representative.

Records of the safety briefings shall be submitted to the GDA weekly.

2. AHA: An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work. The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. Work shall not proceed on a phase of work until the AHA has been accepted by the GDA. A preparatory meeting shall be conducted by the Contractor to discuss the AHA contents with all engaged in the activity. The preparatory meeting shall be conducted by the prime Contractor and shall include all subcontractors and Government on-site representatives. The AHA shall be continuously reviewed and revised to address changing site conditions or operations as appropriate.

3. Accident Reporting: All accidents and near misses shall be investigated by the Contractor. All work-related recordable injuries, illnesses and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $5,000.00, shall be verbally reported to the GDA within 4 hours of the incident. Serious accidents as described in EM 385-1-1, Sections 01.D.04 and 01.D.05, shall be immediately reported to the GDA.

ENG Form 3394 (available from the Contracting Officer’s Representative) shall be completed and submitted to the GDA within five working days of the incident.

The Contractor shall complete the “USACE Contractor Monthly Summary Record of Injuries/Illness and Work Hour Exposure” (for prime and its subcontractors), an EXCEL spreadsheet available from the Contracting Officer’s Representative, and forward the completed form to the GDA no later than close of business on the 10th calendar day of the following month. The method of transmission by the prime contractor to the GDA shall be electronically.

4. Site Safety and Health Officer (SSHO): The Contractor shall designate one individual as the SSHO.

Documentation of SSHO qualifications shall be submitted for approval prior to initiating work. The SSHO shall have:

A. A minimum of five years of experience in implementing safety and health programs at similar projects;

B. Documented experience in personal protective equipment;

C. Working knowledge of construction safety procedures as well as Federal and state occupational safety and health regulations.

D. Completion of the 30-hour OSHA Construction Safety class or as an equivalent, 30 hours of formal construction safety and health training covering the subjects of the 30-hour course.

The SSHO may have other duties in addition to site safety and health, but may not be the Contractor’s Site Superintendent.

5. Equipment: The Contractor shall submit to the Contracting Officer’s Representative a current written safety inspection for all heavy equipment proposed for use on this contract. The Contractor, upon award of the contract, will be required to make available for suitability and safety compliance inspection all equipment proposed for use to perform the work of this contract. Equipment shall be made available for inspection by the Government Representative five working days prior to the start of construction. Any additional equipment added during the prosecution of the work shall also be made available for inspection prior to its use on the project. The Contractor shall keep equipment available for inspection by the Contracting Officer’s Representative during the construction process. Equipment not accepted by the Contracting Officer’s Representative should be repaired or replaced by the Contractor.

6. Fall Hazards. When the pump is removed, a fall hazard will be created on this project. As part of the Accident Prevention Plan, the Contractor shall prepare a Fall Protection and Prevention Plan. The plan must comply with the requirements of EM 385-1-1, Section 21.D and ASSE/SAFE Z359.2, be site specific, and address all fall hazards in the work place and during different phases of construction. A competent person or qualified person for fall protection must prepare and sign the plan documentation. Include fall protection and prevention systems, equipment and methods employed for every phase of work, roles and responsibilities, assisted rescue, self-rescue and evacuation procedures, training requirements, and monitoring methods. Review and revise, as necessary, the Fall Protection and Prevention Plan documentation as conditions change, reflecting any changes during the course of construction due to changes in personnel, equipment, systems or work habits. Keep and maintain the accepted Fall Protection and Prevention Plan documentation at the job site for the duration of the project. All floor openings shall be guarded in accordance with EM 385-1-1, Section 24.B.02.

NOTE: Competent Person in Fall Protection training must be completed in accordance with EM 385-1-1, Section 21.C.04 and requires a minimum 24 hours which is a combination of both formal classroom training and practical applications.

7. Confined Space: For contractor activities, NAE has designated the wet well as a permit-required confined space.

However, contractors who perform work within this space are allowed to re-classify the space to non-permit required following the procedures outlined in OSHA's Permit-Required Confined Space Regulation, 29 CFR

1910.146 and EM 385-1-1, Section 34.

8. Crane/Load Handling Equipment (LHE): The hurricane barrier has a Chester 3 ton, class II overhead crane. If the contractor chooses to utilize this LHE, they must meet the requirements outlined in EM 385-1-1, Section 16 as well as those detailed below:

a. General: All load handling and crane operations are required to be completed in accordance with EM 385- 1-1, Section 16. These requirements are applicable to load handling equipment (LHE) including cranes, derricks, hoists and power-operated equipment that can be used to raise, lower and/or horizontally move a suspended load. This includes excavators, forklifts, and other equipment when used with rigging.

b. Crane Submittals: A Standard Lift Plan is required to be submitted and approved by the GDA prior to any lifting operations. USACE will provide a non-mandatory, fillable template plan. However, the contractor is permitted to submit their own plan, but it must at a minimum include the items listed in EM 385-1-1, Section 16.A.03:

i. Personnel: roles, responsibilities, qualification/certifications, operator medical clearances;

ii. Area Preparation: load handling location and path of travel, blocking/cribbing, overhead lines, ground stability; control/restrict personnel access near lift;

iii. LHE Considerations: capacity/ratings, configuration, obstructions, inspection, ground support conditions;

iv. Load parameters: weight, center of gravity, radii, and configuration;

v. Rigging: type, inspection, rating, need for softeners;

vi. Environmental Considerations: wind, storms, precipitation, power lines in area of travel or load swing, counterweight swing area barricaded.

vii. Certificate of Compliance for LHE and Rigging (Form 16-1)

viii. Documentation of operational tests and annual/shift inspections;

ix. Documentation of the wire rope’s working load limit (WLL) from the manufacturer;

x. A copy of the crane’s specification/technical data sheets. (PDF version is acceptable).

c. Critical Lifts: A Critical Lift Plan (Form 16-3, or equivalent, in accordance with 16.H.02.d) is required for lifts involving the characteristics listed in EM 385-1-1, 16.H.01:

i. Lifts involving hazardous materials (e.g., explosives, highly volatile substances);

ii. Hoisting personnel with LHE;

iii. Lifts made with more than one LHE;

iv. Lifts where the center of gravity could change;

v. Lifts made when the load weight is 75% of the rated capacity of the LHE load chart or more (not applicable to gantry, overhead or bridge cranes);

vi. Lifts without the use of outriggers using rubber tire load charts;

vii. Lifts using more than one hoist on the same LHE;

viii. Lifts involving Multiple Lift Rigging (MLR) Assemblies or other non-routine or technically difficult rigging arrangements;

ix. Lifts involving submerged loads;

x. Lifts out of the operator’s view;

xi. Load Tests;

xii. When land-based LHE mounted on barges, pontoons or other means of flotation are required to travel while lifting the load;

xiii. Any lift the operator believes should be considered critical.

Crane-LHE Standard and Critical Lift Plan.pdf

d. Crane Operators: Crane Operators must meet the requirements of EM 385-1-1, Section 16.B. Prior to the start of crane activities, documentation of operator certifications, qualifications and designations must be submitted to the GDA for review. (See EM 385-1-1, Section 16.C.05 - 16.C.07 for specific information and exemptions on Class II cranes.)

i. Certification for all crane/hoist operators shall be achieved by successful completion of written and operational testing hosted by a Nationally Accredited Crane Operator Testing Organization (or other option as listed in 16.B.03.)

ii. Crane operators shall have a current medical exam certificate (signed by an M.D. or D.O.) dated within the past 2 years, that states the operator meets the proper physical qualifications listed in EM 385-1-1, Section 16.B.05. (Refer to the Crane Operator Medical Clearance Form included in Crane-LHE Lift Plan template).

e. Qualified Riggers (QRs): Employers must designate in writing which employees are QRs and the specific rigging tasks for which they are qualified. All QR’s must meet the requirements listed in EM 385-1-1, Section 15.B.01:

i. Have extensive knowledge, training & experience to sufficiently calculate loads, load weights, safe capacities and apply other safe rigging principles/procedures;

ii. Demonstrate the ability to utilize rigging materials and principles, and;

iii. Be capable of safely inspecting and performing rigging operations.

iv. Effectively communicate, be over 18 years of age, and have basic knowledge of LHE capabilities and limitations.

v. Have demonstrated knowledge and proficiency in the items listed in EM 385-1-1, Section 15.B.02:

1) Personnel roles…