W912WJ18B0024_Amendment_0001.pdf

PDF 713 KB Posted

Attached to
Townshend Dam Spillway Bridge Painting
Solicitation number
W912WJ18B0024
Issued by

About this file

Amendment 0001 to Solicitation for Requests for Information and pre-bid site visit sign in sheet.

View the file

Other files

File Type Posted
Revised_Bid_Abstract.pdf PDF
BidAbstract_Signed.pdf PDF
W912WJ18B0024_Amendment_0002.pdf PDF
Townshend_Lake_Spillway_Bridge_Inspection_2016.pdf PDF
Drawings.pdf PDF
Plans.pdf PDF
W912WJ18B0024.pdf PDF
SPECS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is necessary to post responses to Requests for Information, to publish the pre-bid site visit sign in sheet, and to post Information Draw ings.

All other aspects remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 04-Sep-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ18B0024

X 9B. DATED (SEE ITEM 11)

14-Aug-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

04-Sep-2018

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ18B0024

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

PRE-BID SITE VISIT ATTENDEES

Pre-Bid Opening Site Visit Attendees for W912WJ18B0024 Townshend Lake Dam, Spillway Bridge Paint, Townshend, Vermont Gene Ebbinhaus Coatings Unlimited John Levings Safespan Platforms Will Glaus Thomas Industial Coatings

REQUEST FOR INFORMATION

RFI- W912WJ18B0024 Townshend Dam Spillway Bridge Painting, Pre-Bid Opening site visit, 28 August 2018

Question 1.

Are the Contractors to repair the guardrails on both the north and south sides of the east side of the bridge?

Answer: No. As per Plan Sheet C-102, only the south side of the guardrail is to be repaired.

Question 2.

Prior to sealing, are the Contractors to clean out and seal the cracks that are in the concrete approach slabs of the bridge?

Answer: Refer to subparagraph 3.2.1 Surface Preparation Prior to Application of Sealer, in Spec Section 07 19 16 PENETRATING SEALER, which states “Prepare substrates in accordance with penetrating sealer manufacturer’s recommendation. All cleaning, patching, crack repairs, etc. shall be done and corrosion protection applied prior to application of sealer.”

Question3.

Is this a small business set aside?

Answer: Refer to Block 10 of Standard Form 1442.

Question 4.

What is the size limitation for the small business NAICS code?

Answer: Refer to Block 10 of Standard From 1442.

Question 5.

Are there as-built Plans for this bridge?

Answer: Yes, there are Information Drawings showing the As-Built condition of the Bridge. The 8 pages of Information Drawings were omitted from the initial Solicitation, and are included as part of Amendment 0001.

Question6.

When does the Government anticipate actually conducting the mobilization for this project?

W912WJ18B0024

Answer: Refer to Block 11 on the first page of the Solicitation, Standard Form 1442. This Contract has a 300-day Period of Performance. That means that the Contractor can complete the work elements of the contract any time between the Notice To Proceed (NTP) date and 300 days past the NTP date. However, there are environmental factors as stated in Spec Section 09 97 02 that may dictate when the painting can be completed.

(End of Summary of Changes)

File details come from the government source that posted it.