AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to post responses to RFI's. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-Feb-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912WJ-17-R-0002
X 9B. DATED (SEE ITEM 11)
26-Jan-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-Feb-2017
CODE
US ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA ROAD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912WJ-17-R-0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by full text:
AMENDMENT 3
Solicitation Revisions
RFI
1. Please confirm the Phase 1 "Price & Proforma / Administrative" submission requirements.
Other than the SF14442, are we require to submit our Mentor Protégé Agreement? Reps & Certs? Bonding information? etc.? Please advise.
Response: See Section 0010 – Solicitation Contract Form, A. Proposal Submission Requirements, #2, (Proposal Submission Requirements) indicating the items required with Phase 2 submissions and #4. Content Requirement, (a) Phase 1, Factor 1: Team Experience, 6th Para.
Please also see the section entitled “NOTICE” on page three of the original solicitation. In addition, see amendment 0001 regarding mentor/protégé requirements.
2. For Factor 1, Team Experience, is there a certain format required for submitting past project information? If so please forward or advise.
Response: There is not a stipulated format for team experience under Factor 1.
3. For Factor 2 Past Performance, PPQ's are required. As you know these have become very cumbersome for Contractor folks to complete for every new submission. Is it acceptable to submit previously (from other Phase 1 solicitations) completed PPQ's that have similar formats as this RFP?
Response: No. PPQ’s should be submitted in a sealed envelope along with the offeror’s proposal. See Section 0010 – Solicitation Contract Form, A. Proposal Submission Requirements, #4. Content Requirement, (b) Phase 1, Factor 2: Past Performance, 4th Para.
4. For Factor 2 Past performance, is it acceptable to submit completed CCASS/CPARS evaluations in lieu of PPQ's?
Response: Yes. See Section 0010 – Solicitation Contract Form, E. Evaluation Approach, Section 3. Phase 1, Factor 2: Past Performance, Para (a).
W912WJ-17-R-0002
5. For Factor 1, Team Experience, it states additional consideration will be given to "... design and construction (aka Design-Build) of new....” However it also state that a project is defined as a "...single task order or contract which included both design and construction." This leads offerors to believe that only deign build projects will be considered. Are design only or construction only (DBB) projects considered acceptable?
Response: Design-Bid-Build projects may be submitted but may not be rated as highly as design build projects. See Section 00100, A. Proposal Submission Requirements, #4. Content Requirement, (a) Phase 1, Factor 1: Team Experience, 11th Para.
6. For Factor 1, Team Experience, it is stated "...If the Joint Venture does not have experience, at least one project shall be submitted for each Joint Venture partner." If we are submitting under a Mentor Protégé agreement, does this apply? Does the Team Experience criteria apply to the Protégé project? Normally, small businesses (Protégé) do not have the requisite experience required for a solicitation of this nature, thus the purpose of the Mentor Protégé program is meant to assist small business who do not have larger project experience.
Response: See Section 0010 – Solicitation Contract Form, A. Proposal Submission Requirements, #4. Content Requirement, (a) Phase 1, Factor 1: Team Experience, 6th Para. In addition, see amendment 0001.
7. For our non-Government clients, would the Government allow Offerors to provide recent, previously completed PPEs from these clients in lieu of asking them to complete new PPEs for this submission? We have found in the past that our requests to obtain new PPEs for every submission can create a burden for our clients.
Response: Please see the response to Amendment 0003, Question 3 above.
(End of Summary of Changes)