Solicitation Number:
W912WJ-16-B-0013
Maintenance Dredging, Federal Navigation Channel
Mianus River Greenwich, Connecticut
Construction Solicitation and Specifications
June 2016
Maint. Dredging, Federal Navigation Channel, Mianus River, CT
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 32 00
GEOTECHNICAL DATA
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 CONTRACTOR QUALITY CONTROL
01 45 01 QUALITY CONTROL SYSTEM (QCS)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 54 50 DREDGING PLANT AND EQUIPMENT
01 57 20 ENVIRONMENTAL PROTECTION
01 58 00 PROJECT IDENTIFICATION
01 71 23 FIELD ENGINEERING FOR DREDGING
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 DREDGING
35 20 24 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM: SCOW -
MONITORING PROFILE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 32 00
GEOTECHNICAL DATA
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 EXAMINATION OF SAMPLES
1.4 ANALYSIS OF SAMPLES
1.5 INTERPRETATION
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
DOCUMENT 00 32 00 Page 1
SECTION 00 32 00
GEOTECHNICAL DATA
PART 1 GENERAL
1.1 SUMMARY
The surface conditions indicated in the attachment at the end of specifications are the result of cores taken by TG&B Marine Services in 2005, with grain size analysis subsequently performed by Woods Hole Group Environmental Laboratories. Cores were taken using a manually operated hammer push corer and a powered mechanical vibratory corer, as appropriate for the location and depth. Samples were collected from 12 discrete locations within the Federal Channel, with one sample from each location.
Sample depths ranged from 1.5 feet to 5.8 feet below the channel bottom.
Additional sampling and grain size analysis was performed in 2015 by Alpha Analytical. Copies of the grain size analysis and locations at the site where subsurface investigations were performed are attached at the end of the specification.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D2216 (2010) Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass
ASTM D422 (1963; R 2007) Particle-Size Analysis of Soils
1.3 EXAMINATION OF SAMPLES
Pertinent subsurface information is shown in the attachment at the end of the specifications. Sample materials obtained from the subsurface explorations are not available for examination.
1.4 ANALYSIS OF SAMPLES
Analysis of samples included grain size analysis in accordance with ASTM D422 and water content in accordance with ASTM D2216.
1.5 INTERPRETATION
Subsurface investigation data are provided only for information purposes and for the convenience of the Contractor. The data shown in the attachment at the end of the specifications is for the specific locations indicated only and no assurance is given that these conditions are representative of conditions between sampling locations or areas adjacent thereto. The responsibility lies with the Contractor to interpret subsurface conditions that may affect his work.
DOCUMENT 00 32 00 Page 2
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
DOCUMENT 00 32 00 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.2 SUBMITTALS
1.3 PHYSICAL DATA
1.4 SUPERINTENDENCE BY THE CONTRACTOR
1.5 COORDINATION AND DIRECTION DURING CONSTRUCTION
1.6 SEQUENCING AND SCHEDULING
1.6.1 Hours of Operations
1.6.2 Work Sequence
1.6.2.1 General
1.6.2.2 Initial Project Schedule
1.6.2.3 Periodic Schedule Updates
1.6.3 Organization at the Site
1.6.3.1 General
1.6.3.2 Rate of Progress
1.7 CONTRACTOR'S USE OF UPLAND FACILITIES AND HAULING ROUTES
1.8 CONTRACTOR USE OF PREMISES
1.8.1 Access to the Site and Storage/Staging Areas
1.8.2 Temporary Facilities and Utilities, and Storage Areas
1.8.3 Work Limits
1.8.4 Protection and Security
1.8.5 Work By Other Contractors
1.8.6 Emergency Contacts
1.8.7 Damaged Property
1.8.8 Contractor's Receipt of Supplies
1.8.9 Daily Clean Up
1.8.10 Government Sanitary Facilities
1.9 QUALITY ASSURANCE
1.10 MOORINGS
1.11 METRO-NORTH BASCULE BRIDGE
1.12 COORDINATION
1.12.1 Notice to Mariners
1.12.2 Aids to Navigation
1.12.3 Harbormaster
1.12.4 Points of Contact
1.13 GENERAL SAFETY REQUIREMENTS
1.13.1 General
1.13.2 Contractor's Project Superintendent
1.14 ENVIRONMENTAL PROTECTION
1.15 PRECONSTRUCTION CONFERENCE
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 11 00 Page 1
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.
The work of this project involves maintenenance dredging of the Federal Navigation Channel in the Mianus River in Greenwich, Connecticut.
The Mianus River is a 20.3 mile long river in Westchester County, New York, and Fairfield County, Connecticut. It begins in the town of North Castle, New York, in a series of ponds at about 600 feet altitude. Flowing northeast into the town of Bedford, it abruptly turns south and passes through the Mianus River Gorge, a nature preserve, before entering Stamford, Connecticut, where it is dammed into the Mianus Reservoir. From there, it flows south through Stamford and Greenwich into Long Island Sound. The river flows under the Mianus River Bridge, which is part of Interstate 95, U.S. Route 1, and the Mianus River Railroad Bridge.
The maintenance dredging work in the Federal Navigation Channel consists of removal of approximately 49,500 cubic yards of material by mechanical dredge with the removed material transported by scow and disposed at the Western Long Island Sound Disposal Site (WLDS) which is located approximately eight (8) miles from the mouth of the Mianus River.
The Contractor shall dredge the upper most portion of the project first and place this dredged material in the Western Long Island Sound Disposal Area (WLDS) prior to the dredging and disposal of material from any other areas of the project.
Due to environmental restrictions, dredging and disposal operations at the project site will only be permitted from 1 October 2016 through 31 January 2017, inclusive. Therefore, the "No Dredging Season" is defined as all dates prior to 1 October 2016 and after 31 January 2017. Dredging operations are required to commence within 30 days of NTP.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Initial Project Schedule; G, RO
In accordance with the contract clauses, the Contractor shall, within 5 days after receipt of Notice to Proceed (NTP) or as
SECTION 01 11 00 Page 3 otherwise determined by the Contracting Officer, submit for approval a practicable project schedule. When changes are authorized that result in contract time extensions, the Contractor shall submit a revised project schedule for approval by the Contracting Officer.
Notice to Mariners
Submit a copy of Notice to Mariners to the Contracting Officer.
Aids to Navigation
Submit proof of coordination with the USCG for any necessary relocation or movement of aids to navigation.
Safe Harbor Plan; G, RO
The Contractor shall submit a Safe Harbor Plan to the Contracting Officer for approval prior to the start of on-site work. The Safe Harbor Plan shall include a written description of the Contractor's plan to provide for the safety and security of floating plant, equipment, and personnel in the event of a storm or other site emergency. The location for the docking of floating plant and the off-loading of equipment and crews shall be clearly indicated.
SD-07 Certificates
Periodic Schedule Updates; G, RO
1.3 PHYSICAL DATA
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
a. Site Conditions: The indications of physical conditions on the drawings and in the specifications are the result of site investigations and surveys. The conditions represented prevailed at the time the investigations and surveys were made. A pre-dredge survey will be performed by the Government prior to the start of Contractor dredging operations at the site. Before commencing work at the site, the Contractor shall verify the existing conditions indicated on the drawings and in the specifications. See CONTRACT CLAUSE entitled "SITE
INVESTIGATION AND CONDITIONS AFFECTING THE WORK".
b. Weather Conditions: Weather conditions for the site may be obtained by the Contractor from the National Oceanic and Atmospheric Administration's National Weather Service; www.NOAA.gov.
c. Transportation facilities: The Contractor shall make its own investigations on the use of municipal, State and Federal highways, roads, streets, and bridges.
d. Conditions of Channel: The Mianus River Federal Navigation Project was last dredged in 1985.
e. Channel Traffic: The Mianus River Federal Navigation Project is
SECTION 01 11 00 Page 4 used by small recreation and commercial craft, which may cause interference with contract operations. The Government will not undertake to keep the channels free from vessels or other obstructions, except to the extent of applicable regulations. The Contractor will be required to conduct the work in such a manner as to obstruct navigation as little as possible, and in the event the Contractor's plant so obstructs the channels as to make difficult or endanger the passage of any vessels, the plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage.
f. Tidal Conditions: The average tide range at the project site is
7.2 feet.
1.4 SUPERINTENDENCE BY THE CONTRACTOR
a. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.
b. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
c. Failure to comply with these requirements shall be deemed as cause for a non-compensatory stoppage and suspension of work until the deficiency is remedied.
1.5 COORDINATION AND DIRECTION DURING CONSTRUCTION
a. The Contractor shall not take or accept any direction or instructions issued by any person, employed by the Government or otherwise, other than the Contracting Officer that changes the terms and conditions of contract actions, the scope, or any change that impacts the cost, price, or schedule. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action received by the Contractor before the Contractor will act upon those changes. The Contractor will comply with the changes clause of this contract when the Contractor believes direction has been given from persons other than the Government Contracting Officer that equate to a change by notifying the Contracting Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority must be reported to the Contracting Officer.
b. The Contracting Officer Representative (COR) is limited to the authorities stated in the COR appointment letter. If a COR is appointed under this contract, they will be appointed by written letter from the Contracting Officer to the Contractor and COR specific to this contract only. COR appointment letters from previous contracts are not valid for this contract. See the Contracting Officer’s Representative clause of this contract.
SECTION 01 11 00 Page 5
1.6 SEQUENCING AND SCHEDULING
1.6.1 Hours of Operations
The Contractor will be allowed to perform all work 24 hours per day, seven days per week, including legal holidays, for the entire performance period. Refer to Subpart 1.1 WORK COVERED BY CONTRACT DOCUMENTS of this section for environmental requirements and restrictions to dredging and disposal activities.
The work hours stated above and work on Saturday, Sunday and legal holidays has been considered in computing the performance time of this contract.
The following legal holidays are observed:
January 1st Third Monday in January Third Monday in February Last Monday of May July 4th 1st Monday of September 2nd Monday of October 11th of November Fourth Thursday of November 25th of December
1.6.2 Work Sequence
1.6.2.1 General
There are certain essential criteria relative to the preparation of a work sequence and time schedule which the Contractor will be required to implement and follow during the prosecution of the work. Minor variations in the sequence of the items of work as approved may be made by the Contractor, provided such variations do not conflict with critical elements of the schedule. Proposed minor variations shall be noted on the progress charts submittal required by CONTRACT CLAUSE, entitled "SCHEDULES FOR CONSTRUCTION CONTRACTS". Variations shall be approved by the Contracting Officer prior to implementation. See Section 35 20 23 DREDGING, Subpart "Order of Work" for additional requirements.
1.6.2.2 Initial Project Schedule
The initial project schedule shall be in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed and indicating calendar days to completion. The Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion of the project. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the chart. This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised. Anticipated adverse weather delay days shall be included in the schedule.
1.6.2.3 Periodic Schedule Updates
An updated schedule showing actual progress shall be submitted monthly or with each pay request. Changes to the base-line schedule shall be outlined
SECTION 01 11 00 Page 6 in a narrative describing the reason for the change.
1.6.3 Organization at the Site
1.6.3.1 General
The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in Section 00 80 00 SPECIAL CONTRACT REQUIREMENTS, Subpart COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR
1984) FAR 52.211-10.
1.6.3.2 Rate of Progress
Should the Contractor fail to maintain a satisfactory rate of progress, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought up to schedule and maintained.
1.7 CONTRACTOR'S USE OF UPLAND FACILITIES AND HAULING ROUTES
a. Unless obtained by the Government or specified otherwise in the contract documents, the Contractor shall be responsible for the following:
(1) Locating, coordinating, and obtaining permission to use any land-based water access (docks, piers, ramps, etc.) that the Contractor deems necessary to complete the work.
(2) Determining, if necessary, the trucking and hauling routes and associated restrictions to and from the work, to include the coordination for the use of such routes with local, State, and Federal authorities.
(3) Complying with all local, State, and Federal regulations and restrictions when using any upland facilities or hauling routes.
b. The Government and its representatives will be allowed the use of the same land-based water access obtained by the Contractor.
1.8 CONTRACTOR USE OF PREMISES
1.8.1 Access to the Site and Storage/Staging Areas
a. The Contractor is responsible for maintaining access necessary for its equipment, material, and plant to and from the work area.
b. Access to temporary facilities and storage/staging areas shall be as noted under Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.
1.8.2 Temporary Facilities and Utilities, and Storage Areas
The Contractor shall conform to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS regarding temporary facilities, temporary utilities, and storage areas. Confine all operations (including storage of materials) to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
SECTION 01 11 00 Page 7
1.8.3 Work Limits
The limits of work consist of the shoaled areas of the Federal Channels as shown on the contract drawings, and the side slope areas which must be dredged to obtain the required depth.
1.8.4 Protection and Security
a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.
b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.
c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.
1.8.5 Work By Other Contractors
During the performance period of this contract, no other work is anticipated to occur by other contractors, except for pier and pile removal (see Note 11 on Contract Drawing G-002).
1.8.6 Emergency Contacts
The Contractor shall provide a list of emergency contacts in the event of an emergency. The list shall include the contact names, addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.8.7 Damaged Property
Work shall proceed in a manner which will minimize disturbance or risk of damage to boats, structures, and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.
1.8.8 Contractor's Receipt of Supplies
The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.
1.8.9 Daily Clean Up
The Contractor shall at all times keep rubbish from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be removed from the premises daily.
1.8.10 Government Sanitary Facilities
Toilet facilities are not available on site for Contractor's use. The Contractor shall provide portable toilets for its personnel and subcontractors as specified in Section 01 50 00 TEMPORARY CONSTRUCTION
FACILITIES AND CONTROLS.
SECTION 01 11 00 Page 8
1.9 QUALITY ASSURANCE
a. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.
b. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government.
Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.
c. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.
d. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.
e. The Contractor shall submit all requests for changes in writing to the CONTRACTING OFFICER. Do not proceed with changes without possession of written authorization of the Contracting Officer.
f. The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.
1.10 MOORINGS
See Section 35 20 23 DREDGING, Subpart "Derelict Moorings".
1.11 METRO-NORTH BASCULE BRIDGE
The Metro-North Railroad Bascule Bridge passes over the Mianus River in the work area of this project. The work of the project will require that Contractor plant and equipment pass under this bridge. The bridge has a 20 foot vertical clearance at Mean High Water (MHW) and tide range of 7.2 feet.
The Metro-North Bascule Bridge is owned by the Connecticut Department of Transportation and operated by Metro-North. The draw of the Metro-North bridge, mile 1.0 at Greenwich, operates as follows:
(a) From 5 a.m. to 9 p.m.:
(1) The draw shall open on signal immediately for the passage of commercial vessels and as soon as practicable but no later than 20 minutes after the signal to open for the passage of all other vessels.
(2) When a train scheduled to cross the bridge without stopping has passed the Greenwich or Riverside stations and is in motion toward the bridge, the draw shall open as soon as the train has crossed the bridge.
SECTION 01 11 00 Page 9
(b) The draw shall open on signal from April 1 through October 31, from 9 p.m. to 5 a.m., after at least a four-hour advance notice is given and from November 1 through March 30, from 9 p.m. to 5 a.m., after at least a twenty-four-hour advance notice is given by calling the number posted at the bridge.
The Contractor shall determine how the clearance, tide range, and bridge operational practices will impact his work and reflect this on the Project Schedule.
It is the Contractor's responsibility before submitting a bid and during the work to confirm the latest bridge opening schedule.
1.12 COORDINATION
1.12.1 Notice to Mariners
Before beginning dredging operations and also prior to starting work, the Contractor shall coordinate with the U.S. Coast Guard (USGG) to issue a "Notice to Mariners" regarding the work to be performed and the Contractor's proposed operations.
The U.S. Army Corps of Engineers and the USCG have agreed to phraseology when issuing navigational bulletins and notices. The information furnished shall be consistent with USCG Broadcast Notice to Mariners and Local Notice to Mariners. When requesting local USCG offices to issue navigational information for Corps of Engineers work involving marine construction, the following terminology shall be used, as applicable:
For cautionary areas: "Mariners are urged to use extreme caution in the area."
For dredging and work operations: "Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made."
1.12.2 Aids to Navigation
Aids to navigation (beacons, buoys, markers, etc.) have been placed by the USCG in the vicinity of the project area. The Contractor shall not interfere with these aids to navigation. If the work of this project requires the temporary movement or relocation of any aid to navigation, the Contractor shall notify the USCG and the Contracting Officer of the requirement 30 days in advance. USCG personnel will then move or relocate the aid to navigation as appropriate for the progress of the work. Under no circumstances shall the Contractor move or relocate an aid to navigation under his own authority with his own personnel. The Contractor shall also contact the USCG at the completion of all work and the removal of all marine plant.
1.12.3 Harbormaster
Before beginning dredging operations and scow transport of dredged materials, the Contractor shall coordinate his work operations with the Greenwich, CT Harbormaster.
1.12.4 Points of Contact
a. Coast Guard:
SECTION 01 11 00 Page 10
Mr. Matthew Stuck; 617-223-8365; matthew.b.stuck@uscg.mil.
Mr. John Mauro; 617-223-8355; john.j.mauro@uscg.mil.
For Notice to Mariners: Ms. Mary Swanson, 617-223-8356, "mary.f.swanson@USCG.mil".
b. Harbormaster, Town of Greenwich, Connecticut Mr. Ian Macmillan Telephone: 203-536-4578 e:mail: imacmillan@mindspring.com
c. Town of Greenwich Police Department Lt. John Brown Telephone: 203-622-8033
d. Town of Greenwich Public Works Department Commissioner: Ms. Amy Siebert Telephone: 203-622-7740
e. Town of Greenwich Parks and Recreation Department Marine Facilities Superintendant Mr. Jeff Freidag Telephone: 203-622-6476
f. Harbor Management Commission Mr. Frank Mazza Telephone: 203-622-7710 Cell: 203-962-8799
g. Metro-North Railroad
1. Point-of-Contact: Ms. Hong McConnell Telephone: 203-337-3601 e:mail: HMcConnell@mnr.org
2. Pont-of-Contact: Mr. Glen Hayden e:mail: hayden@mnr.com
1.13 GENERAL SAFETY REQUIREMENTS
1.13.1 General
The Contractor shall take all necessary precautions in observing safety regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and egress. Temporary closures shall not compromise life safety, security or fire safety.
1.13.2 Contractor's Project Superintendent
The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of violations, etc., and including that of any subcontractor's work.
SECTION 01 11 00 Page 11
1.14 ENVIRONMENTAL PROTECTION
To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 20 ENVIRONMENTAL PROTECTION, and all applicable federal, state, and local laws and regulations concerning environmental protection pollution control and abatement.
1.15 PRECONSTRUCTION CONFERENCE
The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the Corps Of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contractor's Superintendent and Quality Control Representative shall attend this conference.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 11 00 Page 12
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
1.2 JOB PAYMENT ITEMS
1.3 UNIT PRICE PAYMENT ITEMS
1.4 BIDDING SCHEDULE - PAYMENT ITEMS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-05 Design Data
Quantity Surveys
Submit originals of all field notes and all other records relating to quantity surveys.
1.2 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items. Submit originals of all field notes and all other records relating to Quantity Surveys.
1.4 BIDDING SCHEDULE - PAYMENT ITEMS
Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are described below. All costs for items of work, which are not specifically mentioned to be included in a particular Bidding Schedule job or unit price payment item, shall be included in the listed job item most closely associated with the work involved.
a. Item Number 0001, "Mobilization and Demobilization".
Payment will be made for costs associated with mobilization and
SECTION 01 22 00 Page 2 demobilization for dredging operations, as defined in Special Contract Requirements clause "PAYMENT FOR MOBILIZATION AND
DEMOBILIZATION".
Unit of Measure: Job.
b. Item Number 0002, "Maintenance Dredging of Material from the Federal Channel with Disposal at the Western Long Island Disposal Site".
The contract price per cubic yard for Item Number 0002 shall include all cost of removal and disposal of all materials encountered from the Federal channel to the specified depth, as indicated on the contract drawings.
The total amount of material removed and paid for under the contract for these Items, will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last pre-dredge survey made before dredging begins and the bottom surface shown by the soundings of a post-dredge survey made as soon as practicable after the removal of the material. Dredged material will be included that is within the limits of the side slopes and specified channel overdepth as described in Section 35 20 23 DREDGING, paragraph OVERDEPTH AND SIDE SLOPES, less any deductions that may be required for misplaced material described in paragraph DISPOSAL OF EXCAVATED
MATERIAL.
The contract drawings listed in Special Contract Requirements, Paragraph "Contract Drawings, Maps and Specifications" are believed to accurately represent conditions existing on the date of the survey shown on the drawings, but the depths and the specific areas to be dredged shown thereon may be verified and corrected by soundings taken by the Government before dredging begins. Determination of quantities removed and the deductions made to determine quantities after having once been made by the Contracting Officer, will not be reopened, except on evidence of collusion, fraud, or obvious error.
Monthly partial payments will be based on approximate quantities determined by Contractor quality control surveys. The pre-dredge survey made immediately before dredging, and the post-dredge survey made as soon as practicable after the removal of the material, will be performed by the Government at no cost to the Contractor.
Also refer to Section 35 20 23 DREDGING, Subpart "Overdepth and Side Slopes".
Unit of Measure: Cubic Yard (CD).
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
1.4.1.1 Approval Codes
1.4.2 Information Only
1.5 PREPARATION
1.5.1 Transmittal Form
1.6 QUANTITY OF SUBMITTALS
1.7 INFORMATION ONLY SUBMITTALS
1.8 VARIATIONS
1.8.1 Considering Variations
1.8.2 Proposing Variations
1.8.3 Warranting That Variations Are Compatible
1.8.4 Review Schedule Is Modified
1.9 SUBMITTAL REGISTER
1.9.1 Use of Submittal Register
1.9.2 Contractor Use of Submittal Register
1.9.3 Approving Authority Use of Submittal Register
1.9.4 Copies Delivered to the Government
1.10 SCHEDULING
1.11 GOVERNMENT APPROVING AUTHORITY
1.11.1 Review Notations
1.12 DISAPPROVED SUBMITTALS
1.13 APPROVED SUBMITTALS
1.14 APPROVED SAMPLES
1.15 WITHHOLDING OF PAYMENT
1.16 STAMPS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to start of construction (work) or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Safe Practice Manual
Certificates of Insurance
Surety Bonds
SECTION 01 33 00 Page 2
List of Proposed Subcontractors
List of Proposed Products
Construction Progress Schedule
Submittal Register
Schedule of Prices
Health and Safety Plan
Work Plan
Quality Control(QC) Plan
Environmental Protection Plan
Pre-Diving Submittals
Diving Plan
Activity Hazard Analysis
Emergency Management Plan
Dive Personnel Qualifications
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material
SECTION 01 33 00 Page 3 attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G, RO
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.4.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.
Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings."
1.4.1.1 Approval Codes
a. Construction/Operations Division {"AO" (Area Office), "RO" (Resident Office), or "PO" (Project Office) Reviewer}: An "AO", "RO", or "PO" in column "f" indicates that the submittal review action is by New England District Construction/Operations Division. Send all such submittals to the project Resident or Area Engineer, as applicable.
b. Engineering/Planning Division {"DO" (District Office) Reviewer): A
SECTION 01 33 00 Page 4
"DO" on the attached submittal register, column "f" indicates that the submittal review action is by the New England District, Engineering/Planning Division, or other organization in the District Office. Send all such submittals to the project Resident or Area Engineer for distribution to the appropriate approving authority.
c. Architect-Engineer Firm {"AE" reviewer): An "AE" on the attached submittal register, column "f" indicates that the submittal review action is by the Architect-Engineer firm asscociated with the project.
d. A "G" followed by "SJ" on the attached submittal register, column "f" indicates that the submittal review action is by the South Atlantic Division, Mobile District, 109 Saint Joseph Street, Mobile, Alabama 03668.
e. Government acceptance is required for submittals with a "G, A" designation.
1.4.2 Information Only
Submittals not requiring Government approval will be for information only.
They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.5 PREPARATION
1.5.1 Transmittal Form
Use the attached sample transmittal form (ENG Form 4025) for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor and are included in the QCS software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.6 QUANTITY OF SUBMITTALS
Submit an electronic PDF copy and seven paper copies of each submittal item with an attached ENG FORM 4025 Transmittal Form. The Contractor will be informed at the pre-construction conference to send all submittals to either the project Resident Office or to the project Area Engineer Office, or other office, as applicable.
1.7 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.
The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
SECTION 01 33 00 Page 5
1.8 VARIATIONS
Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.
1.8.1 Considering Variations
Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.8.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.
The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
1.8.3 Warranting That Variations Are Compatible
When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.8.4 Review Schedule Is Modified
In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.
1.9 SUBMITTAL REGISTER
Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and
(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 01 QUALITY CONTROL SYSTEM (QCS). The Government will provide the initial submittal register in
SECTION 01 33 00 Page 6 electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.
1.9.1 Use of Submittal Register
Submit submittal register. Submit with QC plan and project schedule.
Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.9.2 Contractor Use of Submittal Register
Update the following fields with each submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.9.3 Approving Authority Use of Submittal Register
Update the following fields.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
SECTION 01 33 00 Page 7
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
1.9.4 Copies Delivered to the Government
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
1.10 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A".
c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register".
1.11 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
a. Note date on which submittal was received.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph entitled, "Review Notations," of this section and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, stamp and date approved submittals. Two copies of the approved submittal will be retained by the Contracting Officer and five copies of the submittal will be returned to the Contractor. If the Government performs a conformance review of other Designer of Record approved submittals, the submittals will be so identified and returned, as described above.
SECTION 01 33 00 Page 8
1.11.1 Review Notations
Contracting Officer review will be completed within 30 calendar days after date of submission. Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" "or approved except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or…
This is the start of the file's text. The full file is on GovTribe.