Bid Abstract

View the file

Other files for this federal contract opportunity

Other files attached to Bid Open Annoucement, newest first.
File Type Posted
BidAbstractofOfferors-Knightville.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID OPENING ABSTRACT

SOLICITATION NO. PROJECT DESCRIPTION

W912WJ-08-B-0004 Maintenance Dredging, North Cove, Old Saybrook, CT

BIDS OPENED BY: Rachael Raposa

RECORDED BY: Tina Krawczyk

BID OPENING OFFICER: Rachael Raposa

DATE: GOVERNMENT ESTIMATE:

22-Aug-08 $4,235,000.00

2:00 PM

APPARENT LOW CONTRACTOR: BID AMOUNT:

BIDDER: 2 Burnham Associates, Inc.

14 Franklin Street $4,058,338.00 Salem, MA 01970

BID NO. CONTRACTOR NAME BID AMOUNT

1 Newborn Construction $9,546,378.00 2 Burnham Associates $4,058,338.00 3 Cashman Dredging $5,480,650.00

E6CT9KBP

Cross-Out

E6CT9KBP

Cross-Out

E6CT9KBP

Cross-Out

E6CT9KBP

Cross-Out

Sheet1
Untitled
SOLICITATION NO. W912WJ-08-B-0004: W912WJ-15-B-0012
SOLICITATION NO. W912WJ-08-B-0004: Electrical Upgrades Knightville Dam and Littleville Lake, Huntington, Massachusetts
SOLICITATION NO. W912WJ-08-B-0004: Jessica Kidd

Elaine Law

Jessica Kidd

SOLICITATION NO. W912WJ-08-B-0004: 8/31/15
SOLICITATION NO. W912WJ-08-B-0004: $337,480.00
CONTRACTOR: Burnham Associates, Inc. 14 Franklin Street Salem, MA 01970:
BID AMOUNT: $4,058,338.00:
(3, <Row 1>): 3
(3, <Row 1>): 2
(3, <Row 1>): 1
(3, <Row 1>): $208,899.00
(3, <Row 1>): $201,759.00
($5,480,650.00, <Row 1>): $346,750.00
(3, <Row 2>): 4
(Cashman Dredging, <Row 2>): USNE, Inc.
($5,480,650.00, <Row 2>): $218,122.00
(3, <Row 3>):
(Cashman Dredging, <Row 3>):
($5,480,650.00, <Row 3>):
(3, <Row 4>):
(Cashman Dredging, <Row 4>):
($5,480,650.00, <Row 4>):
(3, <Row 5>):
(Cashman Dredging, <Row 5>):
($5,480,650.00, <Row 5>):
(3, <Row 6>):
(Cashman Dredging, <Row 6>): Power Line Contractor, Inc.
(Cashman Dredging, <Row 6>): TAAVI, LLC.
(Cashman Dredging, <Row 6>): Jay Harris, DBA Colony Construction, Inc.
($5,480,650.00, <Row 6>):
(3, <Row 7>):
(Cashman Dredging, <Row 7>):
($5,480,650.00, <Row 7>):
(3, <Row 8>):
(Cashman Dredging, <Row 8>):
($5,480,650.00, <Row 8>):
(3, <Row 9>):
(Cashman Dredging, <Row 9>):
($5,480,650.00, <Row 9>):
(3, <Row 10>):
(Cashman Dredging, <Row 10>):
($5,480,650.00, <Row 10>):
(3, <Row 11>):
(Cashman Dredging, <Row 11>):
($5,480,650.00, <Row 11>):
(3, <Row 12>):
(Cashman Dredging, <Row 12>):
($5,480,650.00, <Row 12>):
(3, <Row 13>):
(Cashman Dredging, <Row 13>):
($5,480,650.00, <Row 13>):
(3, <Row 14>):
(Cashman Dredging, <Row 14>):
($5,480,650.00, <Row 14>):
(3, <Row 15>):
(Cashman Dredging, <Row 15>):
($5,480,650.00, <Row 15>):
(3, <Row 16>):
(Cashman Dredging, <Row 16>):
($5,480,650.00, <Row 16>):
(3, <Row 17>):
(Cashman Dredging, <Row 17>):
($5,480,650.00, <Row 17>):
(3, <Row 18>):
(Cashman Dredging, <Row 18>):
($5,480,650.00, <Row 18>):
(3, <Row 19>):
(Cashman Dredging, <Row 19>):
($5,480,650.00, <Row 19>):
(3, <Row 20>):
(Cashman Dredging, <Row 20>):
($5,480,650.00, <Row 20>):
(3, <Row 21>):
(Cashman Dredging, <Row 21>):
($5,480,650.00, <Row 21>):
(3, <Row 22>):
(Cashman Dredging, <Row 22>):
($5,480,650.00, <Row 22>):
Burnham Associates: 1