“For Official Use Only” See FAR 2.101 and 3.104
Control No: JA19-0004
Justification and Approval for Other Than Full and Open Competition
Architectural Engineering Services for CY ROKFC In-Kind, HAS Phase 1, 2 and 3 Kunsan
Airbase Korea
AMKOR A&E Inc
1. Contracting Activity: Contracting Division, US Army Corps of Engineers (USACE), Far East District (FED).
2. Description of Action: Approval is requested for non-competitive Architect Engineer
Services purchase order.
3. Description of Services: The AE’s services include fire protection engineering, electrical engineering and other services and tasks including BIM, interior design, energy modeling, landscape design, LEED support and rendering. The AE’s services supplements, and is coordinated to, that of the Far East District’s in-house design team which is performing the work of all other design disciplines.
The Architect-Engineer (A-E) shall perform all work necessary for the design and preparation of documents for the construction of those items identified in the project description. The work in general consists of field investigations, conducting all required studies/reports, attending meetings/conferences, for BIM support, preparation of Landscape Design, Architectural Renderings, Comprehensive Interior Design (CID), LEED Documentation online, LEED Design Notebook, Energy Modeling, and related pre-final, back check, and contract documents, and other A-E services described hereunder. The estimated price for the work is $30,000
4. Authority Cited: 10 United States Code 2304(c)(1) as implemented in Federal Acquisition Regulation 6.302-1(a)(2)(iii), Only one responsible source and no other supplies or services will satisfy agency requirements, it is likely that award to any other source would result in substantial duplication of cost to the Government that would not be recovered through competition and would result in unacceptable delays in fulfilling the Government’s requirements.
5. Reason for Authority Cited:
a. Use of competitive (i.e., Brooks Act – FAR 36.6) procedures for the desired AE design services for this modification will not result in any cost savings to the Government, and will likely cost it more in terms of money and time.
b. Task order W912UM-13-D-0003-0030 was awarded 30 July 2015 to AMKOR A&E INC for the design of Calendar Year (CY) 2015 Republic of Korea Funded Construction (ROKFC) In-Kind Combine Design Packages for Hardened Aircraft Shelters Phase 1, 2, and 3 at Kunsan Airbase, Korea. The construction of this design has begun, however, due to political protests that occurred during construction on 1 April 2019 from locals concerning the location of the currently designed drainage line "N". Current drainage system connects to off-base irrigation of local farmland. Construction of overflow drainage ceased immediately following the protest by direction of ROK Government officials. Immediate re-design is required in order to maintain project progress towards its scheduled completion of May 2020. Failure to perform the re-design will result in delay of project completion, resulting in additional costs to the Government for contractor's overhead, as well as impact to the using agency's occupancy plan for these 20 new aircraft shelters.
c. Because AMKOR A&E has already performed the majority of the services related to the design, using that architect engineer contractor’s services for the design of this project will avoid duplication in cost, amounting to an estimated $57,994 which was the total of the previous design. If we were to compete this requirement to a different firm, the Government would require the incoming A-E firm to assume responsibility for the entire design due to the additional requirement of contractor sequencing.
d. Selection of another AE for this modification would increase FED’s costs of obtaining the desired design services, since other AE firms would need to perform greater effort to evaluate and validate the existing AMKOR design and prepare their input towards the design of this modification. Moreover, selecting another AE would result in a scenario with 2 different designers of record for inter-related projects. Using competitive selection procedures would be unacceptable because such a selection would take an estimated 4 months just to advertise, negotiate and award. By comparison, negotiation and execution of the work under the projected purchase order is expected to take 1.5 months, which results in an estimated savings in 2.5 months in construction.
e. The estimated cost for these new tasks, plus validation of the original design and for another A-E to take full responsibility for the entire design would be $78,000. Therefore the comparison is $30,000 (current AE) to $75,270 (new AE) means $48,000 savings.
6. Efforts to Obtain Competition:
a. Effective competition is not anticipated for this acquisition. For the reasons stated in Paragraph 5 above it would be impractical to solicit work from A-E’s other than AMKOR.
b. Subcontracting competition. FED will advise AMKOR to place any work it needs to subcontract in accordance with the competitive procedures of the Brooks Ace and FAR 36.6
7. Actions to Increase Competition: In the future, FED will endeavor to use competitive (i.e., Brooks Act – FAR 36.6) selection procedures, in accordance with Engineer Pamphlet 715-1-7, whenever placing requirements against its IDIQ A-E services contracts or making public announcements for A-E services. FED will try to avoid situations in which designs for virtually identical projects are undertaken simultaneously or near simultaneously, by its in-house design forces and its A-E contractors.
8. Market Research: FED conducted market research by reviewing existing acquisitions among its existing IDIQ A-E services contractors to determine which contractor would best be able to provide the design services needed by the FED Engineering Division, Design Branch. FED’s market research concluded that AMKOR was the best qualified A-E contractor to provide the required services, given that it had recently produced a virtually identical design to the one being prepared by the FED Engineering Division, Design Branch for the project.
9. Interested Sources: To date, no other sources have written to express an interest. The notices required by FAR 5.201 were published on 17 June 2019, no proposals received.
10. Other Facts:
a. Procurement History
(1) W912UM-13-D-0003-0030 awarded on 15 July 2015. 100% design delivered on 31
August 2015.
(2) These contracts were awarded using procedures set out under the Brooks Act, Title 40 U.S.C Chapter 11, and FAR Subpart 36.6.
(3) Not applicable. This is the first time this specific requirement has been solicited.
(4) Not applicable. This is the first time this specific requirement has been solicited.
(5) No unusual patterns have been revealed by the history of this acquisition.
(6) Not applicable. This is the first time this specific requirement has been solicited.
b. Other Facts: None
11. Technical Certification:
I certify that the supporting data under my cognizance, which are included in the justification are accurate and complete to the best of my knowledge and belief.
Typed Name: Won Lee Date: __________________________
Title: Design Manager Signature: ______________________
12. Requirements Certification:
I certify that the supporting data under my cognizance, which are included in the justification are accurate and complete to the best of my knowledge and belief.
Typed Name: Daniel Novotny Date: __________________________
Title: Project Manager Signature: ______________________ j1edkwsl Typewritten Text 17 June 2019 j1ppfdn9 Text Box 17 June 2019
13. Fair and Reasonable Cost Determination:
I hereby determine that the anticipated cost to the Government for this contract action will be fair and reasonable.
I hereby determine that the negotiated price to the Government for this modification is fair and reasonable based on the prices for the contract previously awarded for similar projects in the past involving the contractor, AMKOR. No certified cost or pricing data will be required since the cost of this requirement is estimated to be below the $2,000,000 threshold.
Typed Name: Brady L. Hales Date: __________________________
Title: Contracting Officer Signature: ______________________
14. Contracting Officer Certification:
I certify that this justification is accurate and complete to the best of my knowledge and belief.
Typed Name: Brady L. Hales Date: __________________________
Title: Contracting Officer Signature: ______________________
Approval
Based on the foregoing justification, I hereby approve an other than full and open competition basis pursuant to the authority of 10 U.S.C. 2304(c) and FAR 6.302-1(a) (2)(iii), subject to availability of funds, and provided that the services and property herein described have otherwise been authorized for acquisition.
Date: ___________________ Signature: ___________________
Date Posted:
June 16, 2019
Posting Confirmation
Solicitation #:
W912UM19RAE08
Procurement Type:
Special Notice
Title:
Notice of Intent To Sole Source, AE Design for ROKFC In-Kind, Hardened Aircraft Shelter, Phase 1, 2 and 3 Kunsan Airbase Korea
Page 1 of 1Posting Confirmation - Federal Business Opportunities: Notices
6/17/2019https://www.fbo.gov/index.php?_paction=post&print_preview=1
A-E:
Project Number & Name:
Location:
Contract / Task Order Number: W912UM-19-D-0001 TBD
Scope of AE services:
Estimated Construction Cost (ECC): $500,000 SOW date:
I. COST ESTIMATE
A. LABOR (Direct Labor + Indirect/Overhead, Prime + Subs) Design Non-Design Total (D+ND)
PROJECT MANAGEMENT and MISC. TASKS N/A $8,965.12 $8,965.12
CIVIL $25,990 $22,014 $48,004
ARCHITECTURAL $0 $0 $0
STRUCTURAL $0 $0 $0
FIRE PROTECTION $0 $0 $0
MECHANICAL $0 $0 $0
ELECTRICAL $0 $0 $0
COMMUNICATIONS $0 $0 $0
COST ESTIMATING $863 $6,154 $7,017
$26,853 $37,133 $63,986
B. TRAVEL
(Airfare, Per Diem, Car Rental, Mileage, Tolls, Parking) N/A $5,952 $5,952
C. OTHER DIRECT COSTS
(Reproduction, Materials, Supplies, Soil Borings, Lab Tests) N/A $779 $779
$26,853 $43,864 $70,718
PROFIT 10.00% $2,685 $4,386 $7,072
DBA Insurance LS $0 $0 $0
$29,539 $48,251 $77,789
$29,539 / $500,000 = 5.91%
$77,789 / $500,000 = 15.56%
II. STATUTORY LIMITATION: Total Design Fee / ECC =
III. ADMINISTRATIVE LIMITATION: Total Fee / ECC =
HDR
CY15 ROKFC In-Kind, F16R610, F17R611 and F17R612 Construct 3RD Gen
Kunsan Air Base, Korea
Reroute connection of an overflow drainage line which is intended as an overflow for extreme rains over 8"/hour for the 3rd Generation Hardened Aircraft Shelter (HAS) Phase 1-3 project to an off-base open irrigation ditch.
SUBTOTAL, LABOR
TOTAL PRICE (Costs + Profit)
SUBTOTAL, ALL COSTS A+B+C (without Profit)
A-E PROPOSAL
TAB 1: SUMMARY
10-Jun-19
1-Summary
FOR OFFICIAL USE ONLY
Source Selection Information - FAR 2.101 and 3.104 Page 1 of 1
6/7/2019
Design Non-Design Total (D+ND) n/a $2,913 $2,913
$12,612 $5,032 $17,645
$0 $0 $0
$939 $3,521 $4,460
$13,551 $11,466 $25,018 n/a $1,500 $1,500 n/a $451 $451
$13,551 $13,417 $26,968
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
$13,551 $13,417 $26,968
10.00% $1,355 $1,342 $2,697
$14,907 $14,759 $29,665
$29,665
= / $500,000 = 2.98%
= / $500,000 = 5.93%
DATEIV. COORDINATION AND APPROVAL
Prepared by:
Design Manager
EDT-D
CEPOF-ED
Kwang Kyu Choe
Pamela J. LovaszApproved by:
Chief, Engineering Division
Endorsed by:
Chief, Design Management Section
Won K. Lee
EDT-D
The IGE preparer(s) and IGE approving reviewer(s) certify the IGE was developed independently and prior to receiving a formal proposal from the contractor.
INDEPENDENT GOVERNMENT ESTIMATE
II. STATUTORY LIMITATION
IGE TOTAL:
AMKOR
CY15 ROKFC In-Kind, F16R610, F17R611 and F17R612 Construct 3RD Generation Hardened Aircraft
Shelters, PH 1, PH 2 and PH 3
Reroute connection of an overflow drainage line which is intended as an overflow for extreme rains over
8"/hour for the 3rd Generation Hardened Aircraft Shelter (HAS) Phase 1-3 project to an off-base open irrigation ditch.
SUMMARY
$14,907
PROJECT MANAGEMENT and MISC. TASKS
Total Design Fee / ECC
SIGNATURE
$29,665
III. ADMINISTRATIVE LIMITATION
Total Estimated Fee / ECC
(Consultant 1)
COMMUNICATIONS
COST ESTIMATING
Reproduction
Additional consultants (without profit)
A-E costs (without profit)
PROFIT
A-E + consultants (with profit)
Professional Services (subtotal)
A-E + consultants (without profit)
(Consultant 2)
ARCHITECTURAL
Professional Services (without profit)
CIVIL
SOW date:
I. FEE ESTIMATE
STRUCTURAL
FIRE PROTECTION
MECHANICAL
ELECTRICAL
Travel
$500,000Estimated Construction Cost (ECC):
Scope of AE services:
Contract, Task Order Number:
IGE Summ
FOR OFFICIAL USE ONLY
Source Selection Information - FAR 2.101 and 3.104 Page 1 of 12
No. Sheets n/a n/a n/a n/a n/a n/a n/a n/a
1 2.0 4.0 6.0 6.0
0.0 0.0
1 2.0 8.0 10.0 10.0
2 4.0 8.0 12.0 24.0
4 2.0 8.0 10.0 40.0
4 2.0 8.0 10.0 40.0
2 2.0 8.0 10.0 20.0
14 ◄ SHEETS 32.0 108.0 0.0 0.0 0.0 0.0 0.0 0.0 CIVIL 140.0
4.0 8.0 12.0 0.0
2.0 4.0 8.0 14.0 0.0
4.0 8.0 8.0 20.0 0.0
2.0 8.0 8.0 18.0 0.0
0 ◄ SHEETS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 ARCH. 0.0
0 ◄ SHEETS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 STRUCT. 0.0
4.0 4.0 8.0 0.0
4.0 4.0 8.0 16.0 0.0
0 ◄ SHEETS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 FPE 0.0
EFFORT (per sheet)
TOTAL HOURS
(Labor
Category)
PER SHEET
TOTAL
Fire Alarm Riser Plan Schematic Diagrams
Details
Sequence of Operaioans
Fire Pump
DRAWINGS
Sheet Title
Cover / Index / Notes / Abbreviations
Fire Sprinkler Floor Plans
Fire Alarm Floor Plans
Foundation Plan(s)
Enlarged Ground Plans
Cross Sections
STRUCTURAL
Struct - Sr.
Struct -
Mid
FIRE PROTECTION
Schedules
Conection Details
Misc Details
FPE - Sr. FPE - Mid FPE - Jr. Drafter
Struct - Jr. Blast - Sr. Drafter
TOTALDRAWINGS
Interior Finish Schedule
Interior Elevations / Details
Door/Window Schedules/Details
Window and Louver Details
Signage plan/Details
Ceiling Details
Exterior Elevations
Building Sections
Enlarged Floor Plans
Wall Sections
Demo Plan(s)
Floor Plan(s)
Roof Plans
Reflected Ceiling Plan(s)
TOTALDRAWINGS
Errosion Control Plans
Pavement Plans/Details
Chain Link Fence
ARCHITECTURAL
Arch - Sr. Arch - Mid Arch - Jr. Drafter IntDes - Sr IntDes - Jr
Site Plan(s)
Grading and Drainage Plan(s)
Utilities Plan(s)
Sections/Profiles
Details(Water, Sewer, Drainage)
DRAWINGS
Cover/Location / Index / Notes / Abbrevs.
Boring Logs Plan and Location
Demolition Plan(s)
CIVIL
DRAWINGS - WORKSHEET
Complete/modify the drawing lists below, as needed to prepare the IGE.
Civil - Sr. Civil - Mid. Civil - Jr. Drafter Landscap e Arch.
IGE Drawings FOR OFFICIAL USE ONLY Page 2 of 12
Task Order Number:
Scope:
Estimated Construction Cost (ECC):
Design Manager (Prepare) Org:
Government Negotiator (Review): Org:
Reroute connection of an overflow drainage line which is intended as an overflow for extreme rains over 8"/hour for the 3rd Generation
Hardened Aircraft Shelter (HAS) Phase 1-3 project to an off-base open irrigation ditch.
Won K. Lee EDT-D
$500,000
CY15 ROKFC In-Kind, F16R610, F17R611 and F17R612 Construct 3RD Generation Hardened Aircraft Shelters, PH 1, PH 2 and PH 3
SOW Date: 6/7/2019
2. PROFIT: The profit factor estimate is based on UAI, Part 15, paragraph 215.404-73-102. Range
Lowest complexity 5.00%
Less than Average complexity 6.50%
1. TECHNICAL COMPLEXITY Average complexity 7.50% 7.50%
Higher than Average complexity 8.50%
Highest complexity 10.00%
1 month to complete design/service 2.00%
6 months to complete design/service 2.50% 2.50%
2. LENGTH 11 months to complete design/service 3.00%
16 months to complete design/service 3.50%
21 months to complete design/service 4.00%
No subcontracting
1-25% subcontracting 0.50%
26-50% subcontracting 1.00%
51-75% subcontracting 1.50%
>75% subcontracting 2.00%
TOTAL PROFIT PERCENTAGE
Percentage
a. The work to be performed is described in:
1. GENERAL:
N/A (OCONUS)
10.00%
3. SUBCONTRACTING IN SUPPORT OF SOCIO-ECONOMIC
PROGRAMS
Scope of Work dated: 7-Jun-19
b. The estimated design fee is developed by the detailed analysis method in accordance with FAR 36.605(A) & (B) and UAI 36.605-100.
BASIS OF ESTIMATE
IGE breakdown FOR OFFICIAL USE ONLY Page 6 of 12
Reroute connection of an overflow drainage line which is intended as an overflow for extreme rains over 8"/hour for the 3rd Generation
CY15 ROKFC In-Kind, F16R610, F17R611 and F17R612 Construct 3RD Generation Hardened Aircraft Shelters, PH 1, PH 2 and PH 3
Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category
PM QCM Arch - Sr. LEED BIM Translation (ID #) (ID #) (ID #) (ID #)
$121.36 $134.47 $117.69 $100.88 $109.27 $96.65
NON-DESIGN (PERSON-HOURS)
Field Investigation / Research 4
Kick Off meeting 4
Review Comments (management of) 4
QC/ITR (management of) 4
Coordination (FED, customer, etc) 8
Coordinating (AE's internal)
Deliverable prep (__submissions)
BIM Management
Rendering(s)
LEED Management
Value Engineering
Translations
NON-DESIGN HOURS (Subtotals) 24 24
NON-DESIGN COST $2,912.64 $2,913
Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category
Civil - Sr. Civil - Mid. Civil - Jr. BIM LEED Specs - Sr Specs - Jr (ID #) (ID #) (ID #)
$100.88 $56.38 $42.89 $109.27 $100.88 $109.27 $100.88
DESIGN (PERSON-HOURS)
Drawings 32 108
Specifications 8 8
Design Analysis 16
Cost Estimating coord / QTO's
DESIGN HOURS (Subtotals) 56 108 8 172
DESIGN COST $5,649.28 $6,089.04 $874.16 $12,612
Field Investigation / Research 8 8
Kick Off meeting 8 8
Review Comments 8 8
QC/ITR 8 8
Project Meetings
LEED/BIM
Coordinations
NON-DESIGN HOURS (Subtotals) 32 32 64
NON-DESIGN COST $3,228.16 $1,804.16 $5,032.32
CIVIL: TOTAL COSTS (D + ND) $8,877.44 $7,893.20 $874.16 $17,644.80
PROJECT MANAGEMENT
and MISC. TASKS
CIVIL TOTAL
PROFESSIONAL SERVICES
IGE breakdown FOR OFFICIAL USE ONLY Page 7 of 12
Reroute connection of an overflow drainage line which is intended as an overflow for extreme rains over 8"/hour for the 3rd Generation
CY15 ROKFC In-Kind, F16R610, F17R611 and F17R612 Construct 3RD Generation Hardened Aircraft Shelters, PH 1, PH 2 and PH 3
Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category Labor Category
Cost - Sr. Cost - Mid Cost - Jr. PM (ID #) (ID #) (ID #) (ID #) (ID #) (ID #)
$69.73 $47.64 $121.36
DESIGN (PERSON-HOURS)
Cost Estimate - US format 8 8
DESIGN HOURS (Subtotals) 8 8 16
DESIGN COST $557.84 $381.12 $939
DD 1354 2 2
Cost Estimate - MND/Korea format 20 20
Project Meetings 8 8
NON-DESIGN HOURS (subtotals) 30 30 $60
NON-DESIGN COST $2,091.90 $1,429.20 $3,521
COMMS: TOTAL COSTS (D + ND) $2,649.74 $1,810.32 $4,460
$188
$148
$336
$13,551
$11,466
$25,018
Trip activity
Travel
Cost / person
Per Diem # Days # People # of trips Subtotal
Kick Off meeting $120.00 $150.00 2 3 1 $1,260
OBR $120.00 1 2 1 $240
$1,500
TRAVEL
TOTAL, Travel
NON-DESIGN ( HOURS)
TOTAL (HOURS)
DESIGN COST
NON-DESIGN COST
Total Cost (D + ND)
COST ESTIMATING TOTAL
LABOR
(ALL
DISCIPLINE
S)
DESIGN (HOURS)
IGE breakdown FOR OFFICIAL USE ONLY Page 11 of 12
Reroute connection of an overflow drainage line which is intended as an overflow for extreme rains over 8"/hour for the 3rd Generation
CY15 ROKFC In-Kind, F16R610, F17R611 and F17R612 Construct 3RD Generation Hardened Aircraft Shelters, PH 1, PH 2 and PH 3
ITEM SHEETS # of SETS Total Unit Price Full Size - B&W $1.42 Half-size- B&W 14 20 280 $0.71
8.5x11 (A4) B&W 200 20 4000 $0.05
11x17 (A3) B&W $0.10
CD ROM 2530 50 50 $1.04
$451
(Consultant 1) Rate Hours Cost
(Activity/labor category)
Design (Totals):
Travel (total):
Non-Design (Totals):
Consultant 1 (Total proposal):
(Consultant 2) Rate Hours Cost
Design (Totals):
Travel (total):
Non-Design (Totals):
Consultant 2 (Total proposal):
TOTAL, Reproduction
$52.17
REPRODUCTION
COST
$198.80
$200.00
END.
DESIGN
NON-DESIGN
CONSULTANT SERVICES
DESIGN
NON-DESIGN
IGE breakdown FOR OFFICIAL USE ONLY Page 12 of 12
| 2019-06-17T12:18:05+0900 | |
| LEE.WON.KYUNG.1094971736 |
| 2019-06-17T13:12:02+0900 | |
| NOVOTNY.DANIEL.CHRISTOPHER.1379520843 |
| 2019-06-17T14:06:26+0900 | |
| HALES.BRADY.L.1382862500 |
| 2019-06-17T14:06:48+0900 | |
| HALES.BRADY.L.1382862500 |
| 2019-06-17T14:20:21+0900 | |
| HALES.BRADY.L.1382862500 |