A.2.11.3_Attachment_D_Price_Schedule.xlsx
XLSX spreadsheet 38 KB Posted
- Solicitation number
- W912UM-17-R-0003
About this file
Attachment D
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP_Amendment_17-R-0003-0002.pdf | ||
| A.2.11.3_RFP_Amendment_17-R-0003-0001.pdf | ||
| A.2.11.3_Attachment_D_Price_Schedule_(Revised).xlsx | XLSX spreadsheet | |
| A.2.11.3_RFP_17-R-0003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Total Attachment D - Price Proposal Schedule
| Item No. | Supplies/Service | Amount |
| 1 | Base Year | - 0 |
| 2 | 1st Option Year | - 0 |
| 3 | 2nd Option Year | - 0 |
| 4 | 3rd Option Year | - 0 |
| 5 | 4th Option Year | - 0 |
| 6 | Sample Task Order | - 0 |
| Total | - 0 |
Base Year
| Attachment D - Price Proposal Schedule | |||||
| Base Year | |||||
| Item No. | Supplies/Service | Unit | Qty | Unit Price ($) | Amount |
| 1 | Senior Contract Manager | Hours | 260 | $ - 0 | |
| 2 | Quality Control Manager | Hours | 260 | $ - 0 | |
| 3 | Senior Project Manager | Hours | 624 | $ - 0 | |
| 4 | Senior Environmental Engineer | Hours | 624 | $ - 0 | |
| 5 | Senior Environmental Scientist | Hours | 624 | $ - 0 | |
| $ - 0 | |||||
| Base Year Total | $ - 0 |
1st Option Year
| Attachment D - Price Proposal Schedule | |||||
| 1st Option Year | |||||
| Item No. | Supplies/Service | Unit | Qty | Unit Price ($) | Amount |
| 1 | Senior Contract Manager | Hours | 260 | $ - 0 | |
| 2 | Quality Control Manager | Hours | 260 | $ - 0 | |
| 3 | Senior Project Manager | Hours | 624 | $ - 0 | |
| 4 | Senior Environmental Engineer | Hours | 624 | $ - 0 | |
| 5 | Senior Environmental Scientist | Hours | 624 | $ - 0 | |
| $ - 0 | |||||
| 1st Option Year Total | $ - 0 |
2nd Option Year
| Attachment D - Price Proposal Schedule | |||||
| 2nd Option Year | |||||
| Item No. | Supplies/Service | Unit | Qty | Unit Price ($) | Amount |
| 1 | Senior Contract Manager | Hours | 260 | $ - 0 | |
| 2 | Quality Control Manager | Hours | 260 | $ - 0 | |
| 3 | Senior Project Manager | Hours | 624 | $ - 0 | |
| 4 | Senior Environmental Engineer | Hours | 624 | $ - 0 | |
| 5 | Senior Environmental Scientist | Hours | 624 | $ - 0 | |
| $ - 0 | |||||
| 2nd Option Year Total | $ - 0 |
3rd Option Year
| Attachment D - Price Proposal Schedule | |||||
| 3rd Option Year | |||||
| Item No. | Supplies/Service | Unit | Qty | Unit Price ($) | Amount |
| 1 | Senior Contract Manager | Hours | 260 | $ - 0 | |
| 2 | Quality Control Manager | Hours | 260 | $ - 0 | |
| 3 | Senior Project Manager | Hours | 624 | $ - 0 | |
| 4 | Senior Environmental Engineer | Hours | 624 | $ - 0 | |
| 5 | Senior Environmental Scientist | Hours | 624 | $ - 0 | |
| $ - 0 | |||||
| 3rd Option Year Total | $ - 0 |
4th Option Year
| Attachment D - Price Proposal Schedule | |||||
| 4th Option Year | |||||
| Item No. | Supplies/Service | Unit | Qty | Unit Price ($) | Amount |
| 1 | Senior Contract Manager | Hours | 260 | $ - 0 | |
| 2 | Quality Control Manager | Hours | 260 | $ - 0 | |
| 3 | Senior Project Manager | Hours | 624 | $ - 0 | |
| 4 | Senior Environmental Engineer | Hours | 624 | $ - 0 | |
| 5 | Senior Environmental Scientist | Hours | 624 | $ - 0 | |
| $ - 0 | |||||
| 4th Option Year Total | $ - 0 |
Sample TO
| Attachment D - Sample Task Order Schedule |
| Sample Task Order |
| Operation and Maintenance of Landfarm Facilities, USAG Humphreys | |||||
| Item No. | Supplies/Service | Unit | Qty | Unit Price ($) | Amount |
| 1 | Submittals | Hours | - 0 | ||
| 2 | Meeting | Hours | - 0 | ||
| 3 | Laboratory Costs | Hours | - 0 | ||
| 4 | Landfarm Activities | Hours | - 0 | ||
| 5 | Transporation of Treated Soil | Hours | - 0 | ||
| Sub-total | - 0 | ||||
| 6 | Profit % | - 0 | |||
| Grand Total | - 0 | ||||
| Note: Detailed cost break down shall be provided for sample task order. |
Cost Breakdown Please provide detail cost break down of sample task order.
File details come from the government source that posted it. Updated .